Attachment 4
ASBESTOS MANAGEMENT PLAN
FOR
1 SHEA TERRACE
TAKAPUNA
AUCKLAND
GW ENVIRONMENTAL LTD | 23 SHADDOCK STREET, EDEN TERRACE,
AUCKLAND, 1021
Project Number – AMP029
26/03/2019
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
Contents
1
Introduction .................................................................................................................... 1
2
Roles and Responsibilities ............................................................................................. 1
3
Work and Visitor Protocols ............................................................................................. 1
4
Identification of asbestos or ACM ................................................................................... 1
5
Emergency Procedures .................................................................................................. 1
6
Training and Competency .............................................................................................. 1
7
Air Monitoring and Clearance ......................................................................................... 1
8
Appendix ........................................................................................................................ 1
Legend:
-
Inspected, Not Sampled but Presumed to Contain Asbestos
-
Inaccessible (Presume)
Disclaimer:
GW Environmental Ltd has prepared the following document within the scope provided by the
client for the sole use by the client in their undertakings within the scope of works. GW
Environmental believes the information contained herein to be accurate at the time of
assessment. GW Environmental takes no responsibility for any reliance on the contained
information herein for any future undertaking outside of the scope of works for which this
report was compiled. The responsibility lies with the client to provide GW Environmental a full,
factual and accurate scope of the works. GW Environmental takes no responsibility for any
lack of information from the client that may impact on the scope of this report. This report must
not be altered in anyway by any parties without the consent of GW Environmental.
2
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
1. Introduction
The Asbestos Management Plan was compiled from data derived from the Asbestos
Management Survey carried out by
David Young and Yu Zhang on 26/03/2019.
All internal areas were inspected excluding Wall Voids, Ceiling Voids and beneath
Carpets and Floor Coverings and behind concrete/plasterboard to the Building were
accessed and inspected as far as is reasonably practicable.
This Asbestos Management Plan sets out the actions to be taken within the premises, to
manage Asbestos and Asbestos Containing Materials (ACM’s) in accordance with the Health
and Safety at Work (Asbestos) Regulations 2016.
Asbestos is a microscopic mineral fibre that is so small that it can’t be seen with the naked
eye. Once disturbed, fibres can remain in the air for hours. If fibres are inhaled, they can
cause serious health hazards which might not become apparent for years.
Note: Asbestos should only be disturbed or maintained by specialist personnel, who will be
licensed contractors, working under strictly controlled conditions.
3
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
Roles and Responsibilities
The following person(s) have responsibilities under this Asbestos Management Plan
Name
Title
Role
Responsibilities
Asbestos
Oversee &
To ensure the Hazard and Risk Register
Manager /
Implement all
is kept up to date and that action plans
appointed
aspects of Health & for isolation, mitigation and elimination
person
Safety in relation to are in place in accordance with the
this document
Health and Safety regulations.
3. Work Protocols
Contractors
All contractors attending site to carry out work will be required to review the Asbestos
Survey and Asbestos Management Plan before commencing with their works. This will
be provided by the Companies appointed Asbestos representative.
Where there are (ACM’s) that are to be worked on or nearby, no work will take place
until an Asbestos Removal Control Plan
(ARCP) has been compiled and approved
by
the Companies appointed Asbestos representative.
Emergency Services
Emergency Service Personnel attending site must be given access to the Asbestos
Survey and Asbestos Management Plan upon their arrival.
4
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
4 Identification of asbestos or ACM’s
This Asbestos Survey
Item
Location of ACM
Material
Contains
Condition
Action Plan
Reason for decision for
Inspection
Risk
Asbestos
managing Asbestos
frequency
level
Y / N
Presumed Asbestos
Beneath all Floor
If Likely to be
Thermo plastic Floor
Presume
Coverings throughout
Unknown
Disturbed, sample
Unlikely to be Disturbed
5 Yearly
Low
Tiles and or
Level 1
for Asbestos
Adhesives
If Likely to be
All Internal Partition
Presumed Asbestos
Presume
Unknown
Disturbed, sample
Unlikely to be Disturbed
5 Yearly
Low
Walls throughout
Insulation
for Asbestos
Level 1
If Likely to be
Ceiling Voids
Presumed Asbestos
Presume
Unknown
Disturbed, sample
Unlikely to be Disturbed
5 Yearly
Low
throughout Level 1
Materials
for Asbestos
5
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
5 Emergency Procedures
Where asbestos containing materials (ACMs) have been damaged, or materials suspected to
be Asbestos are seen to be damaged or have deterioration the appointed Asbestos
representative will instigate the emergency procedure below:
• Secure the area affected ensuring no access is permitted (signage will be displayed,
and barriers erected where appropriate);
• Contact the Health & Safety team who can provide advice and guidance as necessary.
• Consider the need for further inspection, air monitoring, and arrangement and
management of any associated remedial works required;
• Maintain controlled access to the area until formal clearance has been confirmed; and
• Maintain effective communication with all staff and other relevant parties providing
updates as necessary to ensure the access arrangements are not breached.
6 Training and Competency
For workers carrying out work involving asbestos, include information about:
-
Training that has been and will be provided to workers;
-
Roles and responsibilities of the workers carrying out work involving asbestos; and
-
Any health monitoring that has been or will be undertaken.
7 Air Monitoring and Clearance
All air monitoring results and clearance certificates should be appended to this Asbestos
Management Plan.
8 Appendix A
a) Asbestos Inspection Record
b) Record of Contractors (ARCP) Inspection
9 Appendix B
a)
Asbestos Survey Report
b)
Site Plan of redevelopment
c)
Air Monitoring Results
d)
Clearance Certificates
6
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
10. Summary
•
Several areas on this level had Carpet Tiles lifted and no asbestos
materials were present but other areas of carpet within Level 1 could not
be accessed due to rooms being occupied so we have Presumed
Asbestos Floor Tiles or Adhesives to be present until proven otherwise
•
The cavities in the partition walls were unable to be accessed due to
occupied rooms so we have presumed them to contain asbestos material
until proven otherwise.
•
The Ceiling Voids were unable to be accessed due to rooms being
occupied so we have presumed them to contain asbestos materials until
proven otherwise.
No refurbishment works should take place within the property without a fully
compliant R & D Survey
7
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
Appendix A
Asbestos Inspection Record
Item (see
Date
Section 4.0)
Location of Findings/condition
Inspected
Necessary remedial
Date to be
Date
ACM
(note any
by
action
completed by
completed
damage/deterioration)
8
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
Appendix A
(B) Record of contractors’ inspection of asbestos report This sheet should be signed by all those carrying out work on the premises (including volunteers, cleaners and staff). Persons signing this
sheet are signing to say that they have seen the asbestos management plan and checked whether there is any known or presumed asbestos in
the area in which they will be working.
If the contractor encounters suspected asbestos containing materials (ACM) that have not been previously identified they will immediately stop
work, inform the Companies appointed Asbestos representative and seek their further instructions.
Note: The asbestos survey was a Management Survey so there is a possibility that there may be further ACM which were inaccessible at the
time of the survey.
Date
Company name
Work being carried out/location on site
Name of person who has
Signature
inspected the asbestos report
9
GW Environmental Limited
23 Shaddock Street
Eden Terrace
Po Box 56355, Dominion Road
Auckland 1440
Date
Company name
Work being carried out/location on site
Name of person who has
Signature
inspected the asbestos report
10