Common Template: Repair/Rebuild Trade Summary
D Reference:
Customer name:
Property address:
Date prepared
Revision
A
Section Headings & Definitions
Interpretation notes for NZS4202:1995
•1
Preliminaries
site supervision, site facilities, site access, internal and external scaffolding
•2
Demolition
repair deconstruction works
•3
Excavation
site scrape, earthworks
1992
•5
Piling
specialist engineered deep piling
•6
Concrete work
foundation repairs including ground re-levelling specialists
•7
Sprayed concrete
•4
Underpinning
•9
Reinforcing Steel
ACT
•8
Precast concrete
on & off site panels, flooring systems, columns, beams & associated propping
•10
Structural steel
opening Lintels, structural steel frames
•12
Brickwork
exterior and interior cladding including omaru stone
•13
Block work
foundations, Integral retaining walls, tanking, external / internal wall construction
•14
Stone masonry
schist stone cladding
•15
Metal work
balustrades, metal stairs
•16
External windows and doors
Include glazing, flashings and associated works, timber/aluminium/PVC
Structural timber beams, timber, framing, linings, internal trim, preparation for cladding systems
•17
Carpentry
(battens), door hardware supply & install, jack and pack work to timber floors
•18 Laminated timber
•30 Plasterboard linings
•31 Grid suspended ceilings
•21 Insulating panel systems
•20 Proprietary partitions
•19
Joinery
Kitchen, timber stairs, in built joinery, shelving, internal doors & skylights
•22
Roofing
Roof cladding, guttering, downpipes & flashings, butynol roofing
INFORMATION
•11 Mastic asphalting and similar treatments
•23
Plumbing and gas fitting
Including supply to capped services.
•24
Drainage
Including supply to capped services.
•25
Mechanical services / Heating & ventilation
Solar, heat pumps, fires, under floor heating
*26
Fire protection
Sprinklers
•27
Lifts and escalators
Plant and car supply & install
Security systems, smoke alarms, switch boards, including mains supply connections,
•28
Electrical services
appliances including gas
•29
Solid plaster and Specialist exterior claddings
Plaster cladding systems, metal cladding (excludes substrate and painting)
•32
Tiling
To walls & floors including water proofing
OFFICIAL
•33 Terrazzo work
•34
Floor coverings
Vinyl, Timber flooring & overlay's, glued carpet
•35
Painting paper hanging and Specialist finishes
Internal & external, textured ceilings/walls, water proof deck paint, garage floor paint
*36
Glazing
Mirrors, glass balustrades, glass shower screens, (excluding glazing to external windows/doors)
•37
Site works
fences, paths, drives, outdoor swimming pool, decks, non-integral retaining walls, carports
•38
Included sums for miscellaneous Items
Indoor swimming pools, sauna, spa, detached garage
Builders margin
UNDER
Documentation
Drawings & specifications, engineering, geotech, consent fees, CWI insurance
Subtotal
Excludes Margin, P&G, documentation and demolition
Total construction
Includes Margin, P&G, Documentation, demolltion and external works, excludes GST
Including GST
Reviewed by:
RELEASED
Total included in estimate
Summary / m2
Dwelling cost including margin
External works Including margin
Preliminary and general / scaffolding
Consent
Documentation
Total construction
Total estimate including GST