Thank you for your email which we received on 4 August in which you asked -  
 
How much has Auckland Council spent upgrading Spraggs Bush tracks to the 31st of July 2020 
including the cost of disposing of the old boardwalks? and how much was original y budgeted 
for this work? 
 
The cost of the construction contract for the upgrade of the Spraggs Bush Track was $397,933. As we 
have previously advised,  budgets are determined based on the estimated work required in each 
location. This is not strictly allocated on a per track basis, as the actual costs for track upgrades are not 
finalised until the procurement process is completed.   
 
Following our initial scoping of this track and based on average unit costs being charged for the various 
track methodologies to be used, we had expected the construction costs to be around $372,000. This 
did not take into account some additional work that was included after the initial scope was completed. 
 
Please note the above does not include the helicopter services associated with the flying in and out of 
materials which was not included in the construction contract. Helicopter costs were $45,210. 
 
The decision to release this information to you was made by Mark Bowater, Head of Parks Services
 
You have the right to seek an investigation and review of this response by the Ombudsman. Information 
about how to make a complaint is available at www.ombudsman.parliament.nz or freephone 0800 802 
602. 
 
Yours sincerely 
 
 
Grace Ray 
Senior Privacy & LGOIMA Business Partner 
Democracy Services 
 
Private Bag 92300, Auckland 1142  |  aucklandcouncil.govt.nz  |  Ph 09 301 0101