O2NL - review of draft collateral for public engagement. 
Thursday 20th August 2020 9am to 9.45am. MS Teams meeting.  
Attendees - Robyn Elston; Emma Speight; Raewyn Pudsey; Chris Gasson; Phil Peet; Rob Napier. 
Feedback re draft material 
Colour scheme  
Out of scope
OrdOut of scope
ACT 1982
Draft content re bridlepath 

Content currently reflects this out of scope but leaves open to further investigations.

Some discussion re in/out of scope; Noted the potential additional costs based on PP2O
enquiries; approx. $6M excluding property, bridges, etc; Robyn reminds that it is out of the
Crown-determined scope and budget hence should no longer be investigating.

Noted that there is some (limited) community interest so we should clarify with them when
INFORMATION 
appropriate that its regrettably outside of scope;
Other minor comments re content 
Out of scope