This is an HTML version of an attachment to the Official Information request 'National Library of NZ'.

ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 Out of scope
ACT
3. What is the problem to solve or opportunity to maximise? 
It is the Department’s obligation under the Public Records Act 2005 and section 11(2A) of the 
National Library of New Zealand Act 2003 to ensure that our documentary heritage is protected and 
preserved over time, that the risk of loss or damage is reduced, and that it is made accessible to New 
Zealanders now and in the future. 
Wairere House is not in a fit state to protect this documentary heritage. A number of leaks through 
multiple floors over the last few years have damaged collections1. 
Out of scope
INFORMATION 
The shelving systems used at Wairere House are not compliant with European Standard EN 16893, 
resulting in a Health and Safety risk. 
OFFICIAL 
Loss of any of the collections at Wairere House would cause considerable loss of confidence in the 
ability of the NZ Government to safeguard New Zealand’s documentary heritage. 
3.1.  Benefits 
THE 
The benefits gained from fixing these problems include: 
•  Improve protection of heritage collections; 
o  Increase proportion of building and storage systems that meet archival standards 
o  Improve safety of the environment for our people. 
•  Optimise value for money 
UNDER 
•  Reduce risk of loss of trust in government. 
                                                      
 
RELEASED 
1 Agenda Item 5. Wairere House Property Report.doc 13 September 2017 
2 The seismic rating is 56% of the new building standard (NBS) and 40% of importance level (IL) 3 standards. This is 
considered below the acceptable level of seismic reliance for contents of high value 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 

 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
4. What are the options? 
 
4.1.  Location 
A wide variety of location options for holding the re-housed col ections were considered, including 
alternative: 
ACT
• 
regional centres 
• 
cities (e.g. Christchurch). 
However, the significant additional cost and risk of transporting col ections removed Christchurch and 
other South Island locations from consideration. 
The remaining North Island regions suffer from the same issue as Whanganui;  that there are no 
suitable National Library staff available to curate or access the collections when needed. The only staff 
available are based in Wellington; but Wellington is not suitable as a location for the Wairere House 
2°C collections since they are the master copies of the ones available for access in Wellington. For 
disaster protection, master copies should be held in a different location. 
The only other viable location is Auckland, providing that Auckland Archives staff are cross-trained to 
support the unique nature of the material. 
INFORMATION 
Wellington was considered an acceptable medium-term location for the newspaper col ection items, 
with Rugby House able to create capacity by removing items from the Overseas Published Collections 
(OPC) which no longer meet the National Library col ection requirements. 
4.2.  Scope 
The  rest of the options considered  were scope  related. As Table  1  shows, the shortlisted options 
differed primarily by quantity of collections removed from Wairere House. 
4.3.  The options 
OFFICIAL 
Option 1Do Nothing. This was the “do nothing” option of leaving the collections in Wairere House. 
Option 2Complete Exit. The complete removal of all items from Wairere House, which would be 
returned to LINZ for disposal. Out of scope
 
THE 
 
 
 
This option assumes that the majority of the OPC col ection wil  be disposed of once selected 
items that meet the current col ections policy are identified for retention. 
Option 3Do Minimum. This option only removed the ground floor items from Wairere House. Out of sco  
UNDER 
 
 
Option 4Relocate ATL Collections, Retain OPC Collection. This option was added because of the cost 
of sorting and disposing of the OPC collection. It removes all Alexander Turnbull collections, but allows 
for the continued storage of the OPC collection on the second floor of Wairere House, and the storage 
in boxes of the OPC col ection items removed from Rugby House in Wel ington. This option assumes 
that Wairere House could stil  be disposed of as a Government Asset, but that the second floor could 
be leased back. 
RELEASED 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 

 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
Option 2 (Complete Exit) is the best value for money of al  the exit options reviewed. Although Option 
1 (do nothing) looks like a better value for money option, it carries a significant risk that building repairs 
and maintenance would exceed current estimates over the next ten years, and if it was assessed over 
a longer term than 10 years, it would quickly become the higher cost option due to ongoing costs.  
If the sensitivity of the cost-benefit analysis is reviewed, it can be seen that a 10% variation in costs 
would eliminate any significant difference in whole of life costs between options 1, 2 and 4. 
ACT
Table 3. Sensitivity of Financial Analysis 
Sensitivity
Option 1
Option 2
Option 3
Option 4
Whole of Life Cost
        3,
  939,489         4,
  121,006         5,
  316,037         4,
  298,039
Low range @ 10%
        3,
  545,540         3,
  708,905         4,
  784,433         3,
  868,235
High Range @ 10%
        4,
  333,438         4,
  533,107         5,
  847,641         4,
  727,843  
Options were also assessed against the investment objectives of: improve protection of collections, 
reduce risk of loss of trust in government, and optimise value for money. Critical Success Factors were 
considered, including whether an option was in line with The Departments and Government Strategy, 
Value for Money, Level of Risk, Capability to Deliver, Affordability and Achievability. The assessments 
made by members of the Wairere House Col ections Steering Committee are shown in Table 4 below. 
INFORMATION 
Table 4. Options Assessment 
Scope (What)
Option 1
Option 2 
Option 3
Option 4
Do nothing - leave all 
 Complete Exit. Remove  Minimum scope. Remove  Remove al  ATL 
collections in Wairere 
all collections from 
only ATL collections held  collections from Wairere 
House
Wairere House. Relocate  in Control ed Atmosphere House.  Retain NL OPC 
ATL col ections, dispose  2  C Room on Ground 
Collection on 2nd floor
of majority of OPC
Floor to Ak Archives new 
CA room
Wairere House Floors Vacated
Investment Objectives

OFFICIAL 
Improve protection of heritage col ections
no
yes
partial
yes
Reduced risk of loss of trust in government
no
yes
partial
yes
THE 
Optimise value for money
no
yes
no
yes
Critical Success Factors (Must Meet)
Strategic Fit and business need
no
yes
yes
no
Value for Money
no
yes
no
yes
UNDER 
Acceptable Risk
no
yes
no
yes
Capability and capacity to deliver
yes
yes
yes
yes
Affordable
no
yes
no
yes
Achievable 
yes
yes
yes
partial
Whole of Life Cost (10 year)
$3.9 M
$4.1 M
$5.3 M
$4.3 M
Capital Cost
$3.9 M
$1.4 M
$4.4 M
$1.4 M
RELEASED 
preferred
 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 

 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
 
Option 2 Complete Exit from Wairere House is the Preferred Option. It delivers the best protection for 
the heritage col ections and trust in government, as well as being the lowest risk option since the new 
storage environments meet workplace safety standards. It is the best value for money option that 
meets organisation requirements and supports property group strategy. 
ACT
6. Procurement and commercial arrangements 
The arrangements detailed below relate to the preferred Option 2 Complete Exit. 
6.1.  Required outcomes 
The sourcing strategy for the Architect, Contract Project Manager and Change Manager was 
approved by the PtNM Board, and appointments have either been made or are about to be made. 
The Col ections Relocation Manager will be appointed internally. 
The remaining sourcing to be approved includes: 
1.  Main Contractor – this organisation will build the new insulated room within Auckland 
Archives, including the air conditioning and cooling components and oversee the contractors 
providing other components (shelving, electrical, flooring etc). INFORMATION 
2.  Furniture supplier – to provide and instal  shelving as per the requirements. 
3.  Training and Change Deliverables - to develop and deliver training and communications 
deliverables as outlined in the change plan. 
4.  Relocation Services – to assist with the physical move to new premises. 
5.  Disposal Services – for secure disposal. 
Each of these requires a different sourcing strategy. These wil  be documented in the procurement 
OFFICIAL 
plan produced by the Contract Project Manager, and will be signed off by the PtNM board. The key 
Contract Project Manager responsibilities are detailed in Appendix E. 
7. Deliverables (preferred op
THE tion) 
The project will deliver the following: 
Out of scope
UNDER 
•  New shelving designed to efficiently and safely house collections. Services to install the new 
shelving.4 
•  Services to dismantle or move old shelving. 
•  Packaging boxes. Some temporary until the packed items are unpacked, and some 
permanent storage boxes that wil  be used to move and then store col ection items. 
                                                      
 3 For detailed specifications, refer to the enhanced requirements documented by Stephenson and Turner: Outline 
specifications    
RELEASED 
Out of scope
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 

 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
•  Services to pack and move collection items out of Wairere House and to move collections 
around within Rugby House to accommodate the items coming from Wairere House. 
•  Services to catalogue or withdraw collection items. 
•  Services to securely dispose of collection items. 
•  Change Management, Communications and training collateral and services. 
ACT
Out of scope
•  Floor filling and alignment to ensure shelving tracks can be installed.  
Business Requirements for the collections and their final locations are shown in Appendix B. 
8. What is the total cost? 
 
8.1.  Key financial assumptions 
•  Life Time of Shelving is 15 years 
•  Life Time of Buildings and rooms is 30 years 
INFORMATION 
•  Analysis Period for Cost Benefit is 10 years 
•  The book value of the Overseas Published Col ection (OPC) is nil 
•  All options assume an off-set of ongoing costs from rental received from the lease of the top 
floor to 9(2)(g)(ii)
 There is a risk that the tenant will move 
out before DIA has disposed of the building, but this risk exists independently from this project 
and its options. 
8.2.  Project budget 
OFFICIAL 
This Project requires a total investment of $3.684m for the recommended option, funded from PtNM 
Budget 2019 bid: 
THE 
•  $1.410m capital expenditure (including $0.235m contingency, being 20% of the capital 
investment) 
•  $2.274m operating expenditure. 
 
Table 5. Project Costs 
Project Budget requirements for preferred Option 2
UNDER 
2019/2020 2020/2021
$000
Year 0
Year 1
Total
Capital expenditure
1,410.3
-
1,410.3
Operating expenditure
1,134.5
1,139.4
2,273.9
Total Project Budget
2,544.7
1,139.4
3,684.1  
 
Detailed project costs are shown in Appendix F. 
 
RELEASED 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 

 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
 
 
9. Ongoing costs and benefits: 
Ongoing costs of $2.501m over ten years, made up of other operating ($0.588m), depreciation 
ACT
($1.224m) and capital charge ($0.689m). Other operating costs (maintenance and utility bills) for the 
preferred option over a 10 year period is $0.711m less than the “do nothing” option baseline costs of 
$1.299m and represents the benefit of exiting the building. The ongoing costs wil  continue to be 
funded from the Property Group baseline. 
It is noted that as PtNM (excluding AIMS) only received 2-year funding in Budget 2019, ongoing 
funding for depreciation and capital charge will be sought as part of the proposed PtNM Budget 2020 
submission. 
Table 6. Ongoing Operating Expenditure 
Total Project and Ongoing Costs for preferred Option 2-Complete Exit and Dispose of Majority of OPC Col ection
2019/2020 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029 2029/2030
$000
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
Year 10
Total
Capital expenditure
1,410.3
-
-
-
-
-
-
-
-
-
-
1,410.3
Operating expenditure
1,347.0
1,386.3
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
4,774.7
Project operating expenditure
1,134.5
1,139.4
-
-
-
-
-
-
-
-
-
2,273.9
On-going operating expenditure
212.6
246.9
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
2,500.8
Total expenditure
2,757.3
1,386.3
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
6,184.9
INFORMATION 
-
Revenue
-
-
-
-
-
-
-
-
-
-
-
-
Capital funding required
1,410.3
-
-
-
-
-
-
-
-
-
-
1,410.3
Operating funding required
1,347.0
1,386.3
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
4,774.7
Realisable cash benefits
-
-
-
-
-
-
-
-
-
-
-
 
10. Whole of life costs: 
Whole of Life Costs for the preferred option are $4.121m. 
Economic case - Potential value for money
OFFICIAL 
Option 1
Option 2
Option 3
Option 4
Move 2° CAR to 
Auckland and ATL 
Collection to Rugby 
House, Move OPC 
Move 2° Control ed  Col ection out of 
THE 
Complete Exit and  Atmosphere Room to  Rugby House back 
Dispose of Majority 
Auckland Archives  to rented floor at 
Do nothing
of OPC Collection
Building
Wairere House
(Preferred)
Key Outputs
Unit
Analysis period
years
10
10
10
10
Capital cost
$
                 3,
  860,000                 1,
  410,259
4,
                        370,259
1,
               410,259
Whole of life costs
$
                 3,
  939,489                 4,
  121,006
5,
                        316,037
4,
               298,039
Cost-Benefit Analysis of monetary costs and benefits at the Public Sector Discount Rate of 6%
Present value of rental received
$
                              - 
-
                              
                                  - 
                         - 
Present value of total costs
$
(3,939,489) 
(4,121,006) 
(5,316,037) 
(4,298,039) 
UNDER 
Benefit Cost Ratio
x : 1
0x : 1 
0x : 1 
0x : 1 
0x : 1 
Net present value (NPV)
$
(3,939,489) 
(4,121,006) 
(5,316,037) 
(4,298,039) 
NPV rank 
Out of 4
1
2
4
3
Payback period
years
No payback
No payback
No payback
No payback
Payback period rank
Out of 4
4
4
4
4  
The detailed financials can be accessed here. 
RELEASED 
7 June 2019 
 



ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
11.3. 
Impact analysis 
An impact analysis has been completed with members of the Steering Committee5. The impact analysis 
focussed on people, processes, systems and tools, organisational model, management and policy. 
There are no major systems or process impacts. People impacts are relatively minor, with one part-time fixed-
ACT
term employee affected. There are two other employees who currently use Wairere House as an office 
location, but their jobs are not at risk from the exit of the building. It is assumed it will take up to three years 
to dispose of the building, so this gives some time for these staff and their managers to come up with 
alternative remote work place arrangements. 
9(2)(f)(iv)
 
 Also, many National Library staff will be significantly involved in the 
project itself, with a large volume of inventory and catalogue work required as part of the change. 
11.4. 
Key risks and issues 
Risks and issues wil  be documented using the Project Management methodology, and any risks that 
change status wil  be reported to the relevant governance group. 
Risks 
INFORMATION 
The primary risks6 that result from the project and their mitigations are: 
•  Negative response by the public to the disposal of the OPC collection. This wil  be mitigated by the 
process of offering the collection to libraries first, and clear communications about the nature of 
the items marked for disposal). 
•  Negative public and political reaction to divestment from the Whanganui region. This will be 
mitigated by communication with political bodies with an interest in regional economic, stressing 
that labour impact is virtually nil, and pointing out that a prime waterfront site will become 
available to develop with more economically active tenants. 
OFFICIAL 
•  Inaccurate estimates of packaging and removal costs for any taonga not yet identified within the 
collections, and potential damage to government relationships if not handled appropriately. This 
will be mitigated during the inventory assessment, when items of likely significance to local iwi are 
identified, the relevant iwi wil  be brought in to consult on movement of the item. 
THE 
Issues 
The key issue (and constraint) is the amount of internal staff time available to deliver the collection 
inventory, packing and cataloguing work. If sufficient staff time is not available, then it is likely that the 
dates for relocation will slip. This slippage is unlikely to affect Whole of Life Costs because it is assumed that 
the current costs for Wairere House will continue for three years beyond the date of removal. 
11.5. 
Dis-benefits 
UNDER 
The project will reduce the overall storage available to the National Library and could impact on the 
National Library’s ability to collect future heritage items. To offset this, annual savings from the property 
disposal could be used to contribute to future storage options. 
 
 
                                                      
 
5 Impact Analysis, Stakeholder Engagement Analysis and Plan 
6 See Appendix D for details.  
RELEASED 
 
7 June 2019 
 
12 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
Appendix B: Business requirements 
A summary of key business requirements for each of the collections is as follows; 
Out of scope
ACT
INFORMATION 
OFFICIAL 
National Library Overseas Published Col ections (OPC) 
THE 
Divestment of the items in the OPC stored in Wairere House and Rugby House that do not fit with the 
current collecting plan will create enough space to store 5-10 years of expected OPC growth Out of scope
 
Environmental conditions required for storage are Standard “2” - a dry environment, free from leaks with 
air filtering, preferably dark. 
UNDER 
                                                      
 
RELEASED 
8 None of the Wairere House shelving meets this standard currently, with significant gaps in Health and Safety 
requirements 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 
16 
 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 


ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 

ACT
DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
 
INFORMATION 
OFFICIAL 
THE 
UNDER 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 
20 
 
RELEASED 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
Out of scope
ACT
INFORMATION 
OFFICIAL 
THE 
UNDER 
RELEASED 
7 June 2019 
IN CONFIDENCE 
21 

DEPARTMENT OF INTERNAL AFFAIRS. 
IN-CONFIDENCE 
 
Appendix F: Detailed financials – note from 
Heather – only anything relating to OPC in 
these tables is in scope 
ACT
Project Costs 
Budget Year
19-20
20-21
Project Costs
Capex
Out of scope
Fit Out Rugby House and room B21C (Shelving)
       500,
 
000
contingency @20%
       235,
 
043
Project Capex Total
   1,
  410,259                - 
Opex
External Services/Products
Moving Company
               - 
       300,
 
000
Out of scope
Property PM 25% 6 months = 225 hr @ $170/hour
         38,
  250
INFORMATION 
Rugby House OPC Disposal 
       365,
 
000
Wairere House OPC Disposal 
       115,
 
000
Legal and Misc consultant fees
         50,
  000
Internal Staff Time
Out of scope
Business PM 12 months @ 75% @100,000pa *30% burden          97,
  500
Staff Set up /label/move Shelving in Rugby House 
         30,
  000
Retrieving OPC collection items that will stay
       158,
 
000
Moving col ections around and out of Rugby House, 
corporate library out of WH
         50,
  000OFFICIAL 
Project Opex Total
   1,
  134,450    1,
  139,400  
 
Total Project and Ongoing Costs for preferred Option 2-Complete Exit and Dispose of Majority of OPC Col ection
2019/2020 2020/2021 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029 2029/2030
$000
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
Year 10
Total
THE 
Capital expenditure
DIA project cost
-
-
-
-
-
-
-
-
-
-
-
-
External vendor costs
1,410.3
-
-
-
-
-
-
-
-
-
-
1,410.3
Purchase of tangible assets
-
-
-
-
-
-
-
-
-
-
-
-
Software
-
-
-
-
-
-
-
-
-
-
-
-
Others
-
-
-
-
-
-
-
-
-
-
-
-
1,410.3
-
-
-
-
-
-
-
-
-
-
1,410.3
Operating expenditure
-
Project operating expenditure
-
Personnel
-
-
-
-
-
-
-
-
-
-
-
-
Software maintenance
-
-
-
-
-
-
-
-
-
-
-
-
Internal Staff Time
591.5
513.0
-
-
-
-
-
-
-
-
-
1,104.5
UNDER 
Others
543.0
626.4
-
-
-
-
-
-
-
-
-
1,169.4
Total project operating expenditure
1,134.5
1,139.4
-
-
-
-
-
-
-
-
-
2,273.9
On-going operating expenditure
-
Personnel
-
-
-
-
-
-
-
-
-
-
-
-
Other operating expenditures
127.9
93.4
93.4
93.4
30.0
30.0
30.0
30.0
30.0
30.0
-
588.1
Depreciation & amortisation
-
73.3
73.3
73.3
73.3
73.3
73.3
73.3
73.3
73.3
73.3
1,223.9
Capital charge
84.6
80.2
75.8
71.4
67.0
62.6
58.2
53.8
49.4
45.0
40.6
688.8
Total on-going operating expenditure
212.6
246.9
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
2,500.8
Total expenditure
2,757.3
1,386.3
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
6,184.9-
Revenue
-
Revenue Crown
-
-
-
-
-
-
-
-
-
-
-
-
Third party revenue
-
-
-
-
-
-
-
-
-
-
-
-
Total revenue
-
-
-
-
-
-
-
-
-
-
-
-
-

Capital funding required
1,410.3
-
-
-
-
-
-
-
-
-
-
1,410.3
Operating funding required
1,347.0
1,386.3
242.5
238.1
170.3
165.9
161.5
157.1
152.7
148.3
113.9
4,774.7
RELEASED 
Realisable cash benefits
-
-
-
-
-
-
-
-
-
-
-
-
 
7 June 2019   
 
 
IN CONFIDENCE 
 
 
 
 
22