ICPE Seismic Strengthening and Concrete Durability Project 
Timeline 
 
February 2016, Receipt of letter from Dunning Thornton 
March/June. Fundraising for at least $22,000 
July. Grant Applications to the Wellington City Council (WCC) and the Lottery Grants Board Heritage  1985
Fund 
August 11. Grant approval or otherwise from WCC 
August. When funding is in place authorise Dunning Thornton to undertake Monastery Engineering 
Act 
assessment and Strengthening Concept. 
October. Grant approval or otherwise from Lottery Grants Heritage 
 Late October. When funding is in place authorise Dunning Thornton to undertake Church 
Strengthening Concept and concurrently to employ a specialist to carry out testing to establish the 
durability of the concrete in the Church and Monastery. 
Target completion date 30 November 2016. 