This is an HTML version of an attachment to the Official Information request 'Miscoding of half-hourly generation data for the Ngawha geothermal power station(s) produces confusion.'.



 
 
20 August 2021 
 
Nicky McLean 
Email to: [FYI request #15833 email] 
 
 
 
Dear Mr McLean 
Thank you for your request, received on 28 July 2021 via the FYI website, for clarification of 
data published on the Authority’s EMI website. 
We acknowledge the feedback you have provided regarding the data available, and your 
concern over its accuracy. As a result of your query we asked Top Energy for an explanation on 
the change in reporting and they provided the following response: 
“Data reported against the Ngawha power stations changed as a result of Ngawha Generation 
initially applying the loss category code for the existing generation plant (GEN1) rather than the 
new loss category code for the new generation plant (GEN2). After being notified by the 
Authority that data was being submitted incorrectly, the correct loss category code (GEN2) has 
been applied to the new generation station and the data corrected through the standard washup 
process. The loss category codes GEN1 and GEN2 both have the same value of 1.00 but a 
separate loss category code is a requirement of the Electricity Industry Participation Code 2010 
as the new embedded generating station has a capacity 10MW or more.”
 
We trust this answers your query. 
You have the right to seek an investigation and review by the Ombudsman of our response. 
Information about how to make a complaint is available at www.ombudsman.parliament.nz or 
freephone 0800 802 602.  
If you wish to discuss this decision with us, please feel free to email ministerial[Electricity Authority request email]. 
Yours sincerely 
 
Sarah Gillies 
General Manager – Legal, Monitoring, and Compliance