Golden Mile Corridor Economic Analysis
1982
Description
Cost Range
Inclusive of Option 1 on Lambton Quay, Option 2 on Willis, Option
Option 1
$15-23M
Act
1 on Manners and option 1 on Courtenay
Corridor Indicative Costs
Inclusive of Option 2 on Lambton Quay, Option 1 on Willis, Option
Option 2
$21-32M
1 on Manners and Option 2 on Courtenay
Inclusive of Option 3 on Lambton Quay, Option 1 on Willis, Option
Option 3
$52-78M
1 on Manners and Option 3 on Courtenay
Description
Benefits Range
Present value costs
Inclusive of Option 1 on Lambton Quay, Option 2 on Willis, Option
Option 1
$31 - $36M
1 on Manners and option 1 on Courtenay
Inclusive of Option 2 on Lambton Quay, Option 1 on Willis, Option
Corridor Indicative Benefits Option 2
-$17 - $5M
1 on Manners and Option 2 on CourtenayInformation
Inclusive of Option 3 on Lambton Quay, Option 1 on Willis, Option
Option 3
$48 - $297M
1 on Manners and Option 3 on Courtenay
Description
BCR Range
Inclusive of Option 1 on Lambton Quay, Option 2 on Willis, Option
Option 1
1.5 - 2.5
1 on Manners and option 1 on Courtenay
Inclusive of Option 2 on Lambton Quay, Option 1 on Willis, Option
Official
Value for Money
Option 2
-0.55 - 0.25
1 on Manners and Option 2 on Courtenay
Inclusive of Option 3 on Lambton Quay, Option 1 on Willis, Option
Option 3
0.63 - 5.9
1 on Manners and Option 3 on Courtenay