This is an HTML version of an attachment to the Official Information request 'I-Rex schedual update'.
Ferry operations continue throughout.
Public engagement ongoing.
2022
2023
2024
2025
2026
Planning and detailed design
 
Waitohi Culvert 
improvements
 
Ground and marine 
preparation work
Environmental and cultural 
Terminal precinct 
 
monitoring throughout
construction finishes 
Appointing contractors
 
with fresh landscaping, 
 
Main construction work 
wayfinding and cultural 
Constructing temporary 
underway – ground works, 
Environmental management 
expression
terminal building for 
terminal buildings, wharves, 
and monitoring continues
 
Waitohi Picton
sea-walls, and vehicle and 
 
First new ferry arrives 
Second new ferry arrives 
 
rail marshalling yards
Main construction continues
for service
for service
Environmental, biodiversity, 
 
 
 
 
and cultural management 
Construction begins on 
Steel cutting and keel laying 
Exciting new customer 
All construction activity and 
plans developed.
Dublin Street Overbridge.
for building new ferries.
experience.  
close out work complete.