This is an HTML version of an attachment to the Official Information request 'Building Consent structural engineering reviews by internal and external contract engineers'.

Structural engineers processing checklist 
 
 
Address: 
 
Consent No:   
Processed by:   
Date: 
 
Description of 
 
work: 
Code clauses 

reviewed 
☐ B1 
☐ B2 
 
 
Brief description of the work reviewed 
☐  Acceptable Solution (describe) 
☐  Verification Method (describe) 
☐  Alternative Solution (describe) 
☐  Full review (refer SESOC Practice Guideline – SESOC Journal Volume 23,  N0: 2 September 2010) (describe) 
☐  Partial review (describe)  
☐  Structural Systems (refer SESOC Interim Design Guidance – Design of Conventional Structural Systems following the  
Canterbury Earthquakes) (describe) 
 
 
 
 
 
Decision 
Structural documentation supplied 
Reasons for decision / comments 
Yes 
RFI 
N/A 
Design features report 
☐ 
☐ 
☐ 
 
Structural calculations 
☐ Clear 
☐ 
☐ 
☐ 
 
☐ Complete 
Structural specifications  
☐ 
☐ 
☐ 
 
Structural drawings 
☐ 
☐ 
☐ 
 
 
Design / detailing of structural elements for durability 
Acceptable Solutions 
☐ NZS 3604 
☐ NZS 3101 
☐ Other 
(describe) 
Alternative Solutions 
☐ AS/NZS 2312 
☐ NZS 3404:Part 1:2009 
☐ Other 
(describe) 
 
 
 
 
 
Page 1 of 5 
January 2023 
AC0810 (v.7) 

Decision 
Section 112.1 the BCA is satisfied that after the alteration the building wil : 
N/A ☐ 
Yes 
No 
1(b) Continue to comply with the provisions of the Code that relate to structural performance, to at least the same 
extent as before the alteration 
☐ 
☐ 
 
 
 
Decision 
Section 115  
N/A ☐ 
Yes 
No 
Complies as near as is reasonably practicable with the provisions of the Building Code that relate to structural 
performance 
☐ 
☐ 
 
 
 
Decision 
Items checked 
Reasons for decision / comments 
Yes 
RFI 
N/A 
Design loadings 
☐ Dead 
☐ Live 
☐ 
☐ 
☐ 
 
☐ Wind 
☐ Seismic 
☐ Other specific loadings 
GIS special land features 
☐ 
☐ 
☐ 
 
Geotechnical / soil report 
☐ Completeness of geotechncial report 
☐ 
☐ 
☐ 
 
☐ Slope stability 
☐ Expansive soils 
Site subsoil class (NZS 1170.5) 
☐ 
☐ 
☐ 
 
Excavation and construction near boundary 
☐ Excavation procedure 
☐ 
☐ 
☐ 
 
☐ Surcharge loads 
☐ Retaining wall design (strength & stiffness) 
Landscape retaining walls 
☐ Surcharge (driveway, buildings, backslope) 
☐ 
☐ 
☐ 
 
☐ Height >1.5m 
Basement retaining walls 
☐ Type 
☐ Surcharge (driveway, buildings, backslope) 
☐ 
☐ 
☐ 
 
☐ Retained height 
☐ Design and detailing 
Drain bridging details 
☐ 
☐ 
☐ 
 
Strip footings and pads 
☐ Size   
☐ 
☐ 
☐ 
 
☐ Depth  
☐ Reinforcing 
Bored piles 
☐ Pile size   
☐ 
☐ 
☐ 
 
☐ Pile depth 
Page 2 of 5 
January 2023 
AC0810 (v.7) 

Decision 
Items checked 
Reasons for decision / comments 
Yes 
RFI 
N/A 
Concrete  
☐ Strength    
☐ 
☐ 
☐ 
 
☐ Specifications 
Driven piles  
☐ Calculations 
☐ Hammer drop  
☐ Hammer weight 
☐ 
☐ 
☐ 
 
☐ Pile set   
☐ Pile size   
☐ Pile depth 
Screw piles 
☐ Eccentricity  check 
☐ 
☐ 
☐ 
 
☐ Adequate specification 
Block walls          ☐ A   ☐ B   ☐ C 
☐ Height 
☐ 
☐ 
☐ 
 
☐ Shear wal s           
☐ Reinforcing 
Slabs 
☐ Raft            
☐ 
☐ 
☐ 
 
☐ On-grade          
☐ Suspended 
Slab 
☐ Thickness   
☐ 
☐ 
☐ 
 
☐ Reinforcement 
☐ Construction joints 
Floor design loads 
☐ Recorded on plans          
☐ Line loads         
☐ 
☐ 
☐ 
 
☐ Point loads 
☐ Vibration check          
Proprietary floor system 
☐ Manufacturer’s information     
☐ 
☐ 
☐ 
 
☐ Support details 
Columns and posts 
☐ Calculations     
☐ Combined action   
☐ 
☐ 
☐ 
 
☐ Detailing  (size, connections) 
☐ Concrete columns detailed for ductility    
Concrete moment resisting frames 
☐ Ductility    
☐ 
☐ 
☐ 
 
☐ Calculations       
☐ Detailing  (reinforcing, beam/column joints) 
Steel moment resisting frames 
☐ Ductility    
☐ Calculations     
☐ 
☐ 
☐ 
 
☐ Restraint points   
☐ Detailing  (size, connections) 
Timber wall framing outside scope of NZS3604   
☐ Calculations     
☐ Height   
☐ 
☐ 
☐ 
 
☐ Loadings 
☐ Openings 
Page 3 of 5 
January 2023 
AC0810 (v.7) 

Decision 
Items checked 
Reasons for decision / comments 
Yes 
RFI 
N/A 
Steel braced frames 
☐ Ductility    
☐ 
☐ 
☐ 
 
☐ Type 
Rafters,  beams and lintels outside scope of 
NZS3604   
☐ Calculations     
☐ 
☐ 
☐ 
 
☐ Point loads 
☐ Lateral restraint 
Purlins and girts 
☐ Size     
☐ Spacing in relation to cladding     
☐ 
☐ 
☐ 
 
☐ Local wind press. effects at knee, ridge & end 
☐ Lateral restraints 
☐ Number of braces per bay 
Trusses 
☐ Member sizes     
☐ 
☐ 
☐ 
 
☐ Connections     
☐ Support details 
Bracing 
☐ Roof     
☐ Wall     
☐ 
☐ 
☐ 
 
☐ Mezzanine 
☐ Lateral load paths to bracing elements 
Firewall 
☐ Stability 
☐ 
☐ 
☐ 
 
☐ Connections (NZS 3101 cl 4.8) 
Precast panels 
☐ Development length of starters 
☐ No wire mesh as primary reinforcement 
☐ 
☐ 
☐ 
 
☐ Thickness and reinforcement    
☐ Embedded anchors 
Welded connections   ☐ Grade G ☐ Grade S 
☐ Weld type/size 
☐ Fatigue considerations 
☐ 
☐ 
☐ 
 
☐ Adequately specified and detailed 
☐ Inspection requirements 
Bolted connections 
☐ Shear and tension 
☐ Fatigue considerations 
☐ 
☐ 
☐ 
 
☐ Adequately specified and detailed 
☐ Edge and end distances 
Vertical load paths to foundations 
☐ 
☐ 
☐ 
 
Building lateral deflection under ULS wind or 
earthquake loading vs. boundary separation 
☐ 
☐ 
☐ 
 
Serviceability deflections (under gravity and / or 
wind loadings) 
☐ 
☐ 
☐ 
 
Wind pressures mapped for cladding / glazing 
design 
☐ 
☐ 
☐ 
 
Page 4 of 5 
January 2023 
AC0810 (v.7) 

Decision 
Items checked 
Reasons for decision / comments 
Yes 
RFI 
N/A 
Note on drawings that manufacturer to provide 
shop drawings for design engineer’s approval 
☐ 
☐ 
☐ 
 
before construction 
Balustrades (refer AC2223 Timber barriers and 
MBIE guidance document on Barriers) 
☐ Design loading 
☐ Height 
☐ 
☐ 
☐ 
 
☐ Connections 
☐ Infil  
Pallet racking (refer AC2246 Pallet racking) 
☐ 
☐ 
☐ 
 
Heritage buildings (refer AC2248) 
☐ 
☐ 
☐ 
 
Structural steel 
☐ Imported structural steel. Has compliance with 
NZS3404 been demonstrated? 
☐ 
☐ 
☐ 
 
☐ How was this achieved? 
 
Decision 
Requests for further information 
Date requested 
Date resolved 
Yes 
N/A 
Information requested 
☐ 
☐ 
 
 
Information requested 
☐ 
☐ 
 
 
Information requested 
☐ 
☐ 
 
 
Information requested 
☐ 
☐ 
 
 
 
Decision 
Decision 
Final check / sign off 
Final check / sign off 
Yes 
N/A 
Yes 
N/A 
PIM issues resolved 
☐ 
☐ 
Conditions completed 
☐ 
☐ 
Agreement to provide PS4 required 
☐ 
☐ 
Computer tasks completed  
☐ 
☐ 
Specialist inspections identified 
☐ 
☐ 
 
☐ 
☐ 
Superseded plans separated / retained 
☐ 
☐ 
 
☐ 
☐ 
 
Final sign off (signature) 
Yes 
No 
The structural engineering specialist input on this building consent has been completed and I am satisfied resolves any 
items identified 
☐ 
☐ 
Engineers name:   
Date:                          
 
Notes / comments/ RFI summary 
 
 
 
 
 
Page 5 of 5 
January 2023 
AC0810 (v.7)