Capital Programme Group Procedures Manual – (Form) 
 
Project Initiation Brief   
    
 
 
 
 
        05.003.1 
 
Sponsor: Steffan Thomas 
Date: 02/07/2021 
Customer: Citywide 
TRIM Ref: 21/931079 
Key Project: 930 
WBS: 542/001662 
Business Unit: Infrastructure, Planning & Regulatory Services - Transport 
Project Name:  Sockburn Roundabout Intersection Improvement 
Location(s) of Project: Al oy Street/Epsom Road/Blenheim Road/Main South Road Intersection 
Completion Date: FY24 to FY26 
Target Dates (Phases): 
01/07/2024 project initiation; 01/07/2026 detailed design, safety audit and consultation 
completed; 30/06/2026 Construction and post construction safety audit completed. 
 
Background:  
 
Transport Activity Management Plan 2021-31 under the safety pillar states that “We want to live in a city where people arrive 
at their destinations alive and unharmed – every time. Council shares the Government’s vision of a New Zealand where no one 
is killed or seriously injured in road crashes.
” It adds that “By 2031, we want to have reduced our road tol , with at least 40% 
fewer fatal and serious crashes on our local roads than in 2020.
” 
The plan includes a level of service (10.0.6.1) to “ Reduce the number of death and serious injury crashes on the local road 
network” with a target to reduce the number of the crashes from 115 reported death and serious injury crashes in FY20 to 
no more than 71 in FY31. 
The target has been set considering the national safety target of Vision Zero and follows the same system design principles.  
It recognises that whilst mistakes are inevitable – deaths and serious injuries from crashes are not. The Safe System 
approach seeks to create a safe and forgiving road system that makes the safety of people a priority. It does this through 
four guiding principles: 
-  We promote good choices but plan for mistakes. 
-  We design for human vulnerability. 
-  We strengthen all parts of the road transport system. 
-  We have a shared responsibility. 
The Sockburn roundabout intersection has been identified as a high risk site and is endorsed by Waka Kotahi, NZTA for 
delivery in the 3-year period of FY22-FY24. The project, however, has been budgeted in the current LTP over FY24 to FY26. 
As part of this project to address the safety concerns at the intersection and to gain maximum funding support from Waka 
Kotahi a faster delivery of the project need to be developed and it is proposed to swap financials between this project and 
the Minor Safety Improvements project. 
Define Need: 
Over the 10-year period of 2011-2021, there were 27 injury crashes including 2 serious injury crashes at the Sockburn 
roundabout.  Nearly 80% of all injury crashes occurred at the eastern corner of the roundabout between Main South Rd 
east and Blenheim Road.  The main crash movements reported were - 
•  Rear end (9); 
•  Lost control at bend (5); and 
•  Merging (5). 
The preliminary investigation suggested that the constant stream of eastbound vehicles from the Main South Road west 
approach especially during peak hours causes considerable long delays and frustration for the traffic exiting from the Main 
South Road east approach. Also the dual turning lanes through the roundabout and the proximity of the exits onto Main 
South Road and Blenheim Road on the eastern side of the roundabout leads to driver confusion, both for the turning 
vehicles to indicate their directions and also for the entering vehicles to recognise the turning vehicles’ intentions.  The 
combination of the above coupled with the high speeds limits inside the roundabout leads into the drivers entering to the 
roundabout from the eastern side misjudge the gap to enter the roundabout. This is further confirmed when investigated 
to all injury crash report, the primary causes were 
•  Driver frustration; 
•  Lane confusion; and 
Version 9 
 
 
16/06/2023 


Capital Programme Group Procedures Manual – (Form) 
 
•  High speeds. 
A preliminary investigation is completed and preferred treatment to address the main causes are developed in partnership 
with Waka Kotahi, NZTA. The preferred treatment includes: 
-  Reduction of the posted speed limit through the roundabout: posted speed limit through the roundabout and 
along Blenheim Road is 60kph. It should be reduced to 50kph to reduce the severity of crashes. 
-  Signalisation of Lowther Street/Main South Road: The eastbound direction of Main South Road at Lowther Street 
should be signalised. The traffic signal will provide gaps in the eastbound traffic flow, facilitating the discharge of 
traffic on the eastern side of the roundabout. The traffic signal has to be in coordination with the Main South 
Road/Springs Road traffic signal. Incorporation of an eastbound bus gate at the Lowther Street signal should be 
investigated. 
-  Upgrade of lane marking and gantries: A representation of the roundabout’s layout and advance lane marking 
need to be provided to minimise lane confusion at the roundabout. It should clearly suggest that the eastbound 
movement onto Blenheim Road is a right-turn movement to encourage drivers to indicate right. 
Project Objective(s):   
As part of this project, following high level key objectives are developed - 
-  To develop a preferred design for all treatments; 
-  Prepare a detailed design including costs 
-  Consult with affected parties and all key stakeholders 
-  Deliver the design within allocated time and budget. 
Known Risks, Dependencies, Constraints: 
budget limitations and scope increase, NZTA subsidy, deliverability, departure from the agreed intervention types 
As part of the funding agreement with Waka Kotahi, there is no need to prepare any business cases for the project, however 
treatment is required to be part of their listed intervention and should fit within the allocated budget. Any changes to the 
type of intervention or costing, however, need to be discussed with Waka Kotahi NZTA and an update to the endorsement 
sheet need to be sought. 
WBS 
FY 22 
FY 23 
FY 24 
FY 25 
FY 26 
FY27 
542/001662 
$0.00 
$0.00 
$83,804 
$108,448 
$796,823 
$0.00 
Budget 
           
           
           
           
           
           
           
Allocation: 
           
           
           
           
           
           
           
Totals 
$0.00 
$0.00 
$83,804 
$108,448 
$796,823 
$0.00 
Funding Source: Council’s LTP21-31 (49%) and Waka Kotahi Safe Network Programme (51%) 
Stakeholders: Waka Kotahi, KiwiRail, Council, Hornby, Halswel  and Riccarton Community Boards 
Attachments: trim://21/697305 (Waka Kotahi endorsement schedule) 
Customer Involvement:   
 
Link to LTP: CPMS #930 
Link to Strategy: Vision Zero 
Link to Level of Service: 
10.0.6.1 
The plan includes a level of service (10.0.6.1) to “ Reduce the number of death and serious injury crashes on the local road 
network” with a target to reduce the number of the crashes from 115 reported death and serious injury crashes in FY20 to 
no more than 71 in FY31. 
Comments: 
 
Initiated By: 
Hamid Mirbaha 
Date: 02/07/2021 
Prepared By: Hamid Mirbaha 
Date: 02/07/2021 
Approved By: Steffan Thomas 
Date:           
Accepted By: Ekin Sakin (acting Manager Planning and Delivery) 
Date:           
Project Manager: 
CPG Project Number:                             
 
Version 9 
 
 