Awarua Shelter Upgrade
ID
Task Name
Duration
3 Jul '23
10 Jul '23
17 Jul '23
24 Jul '23
31 Jul '23
7 Aug '23
14 Aug '23
21 Aug '23
28 Aug '23
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1
Instal primary steel columns
2 days
2
Disconnect lighting and cameras 1 day
3
Prep subgrade and box footings 3 days
4
Pour concrete
2 days
5
Instal blocking
9 days
6
Reroof and barge flashings
3 days
7
Manufacture and instal
13 days
secondary posts
8
Lay asphalt
1 day
9
Screen site measure
1 day
10
Finish blocking
2 days
11
Run electrical and data services
1 day
12
Painting
3 days
13
Instal timber battens
8 days
14
Instal screens and seating.
5 days
15
16
17
Task
Project Summary
Manual Task
Start-only
Deadline
Project: Project Programme
Split
Inactive Task
Duration-only
Finish-only
Progress
Date: Wed 5/07/23
Milestone
Inactive Milestone
Manual Summary Rol up
External Tasks
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 1