This is an HTML version of an attachment to the Official Information request 'Briefing Documents Relating to Teitei Drive Housing Scheme in Ohakune'.

s 9(2)(a)
Ohakune Ratepayers and Residents' Society Inc 
A: s 9(2)(a)
E: s 9(2)(a)
 
M: s 9(2)(a)
29 November 2023 
Dear Hon Chris Bishop, 
I am writing to you with an update to a report emailed to you in the last week from the 
Soicety regarding this same matter 
We have grave concerns with respect to a letter received today by email and hand delivered 
in the neighbourhood surrounding the proposed build site at Teitei Drive Ohakune. (See 
Appendix 1) 
In summary, the letter explains that a new resource consent will be submitted in early 2024 
to enable earthworks at the site and that the new resource consent “does not include the 
subdivision of individual lots” and that “The land use and subdivision designs will be part of a 
second resource consent application”.  
We note that there is already two resource consents lodged with Ruapehu District Council in 
July 2023 and being processed with agreement that they will be notified and S.92 requests 
for further information extant and overdue. These two resource consents were submitted 
as Non Complying Activities rather than as Permitted Activities  - on the basis of them  being 
non notified, with less than minor effects - as per reports provided to the then Ministers to 
under the Official Information Act
approve the above funding, (See Appendix 3 & Appendix 4).  We suggest this is a serious 
breach of duty to the then Minister by KO and officials and was a big part of the reason 
funding was finally approved.  
We also note that the applicants have belatedly lodge applications with Horizons Regional 
Released 
Council in August 2023 and that these have requests for further applications outstanding 
AND agreement the applications will be notified and a joint hearing held. 
It appears that this change in tack is a clear attempt to meet the initial condition of the 
funding agreement between HUD and KO relating to the IRG Covid Relief Government Grant 
for ‘shovel ready projects – this requires the project to be started within 12 months and the 
cut off date is 31 March 2024. 
Ohakune Ratepayers and Residents' Society Inc.  


There is also still to be lodged a follow-up application for land use consent due on the initial 
time-line in mid 2024 (but likely delayed) to address the siting of the non-complying 
dwellings, access and parking breaches.  Our independent technical and legal research 
shows that these current and the future resource consents would likely (as presently 
presented) fail to meet the policies and rules on a number of matters, including 
infrastructure design. 
 
In addition, we note KO’s own 2023 Policy Document Building Design requirements are also 
not complied with.  With this knowledge and the prospect of protracted litigation – Judicial 
Review and/or Environment Court appeals - KO has now changed tack in a last gasp attempt 
to obfuscate the real issues surrounding the development. That is that there is a real issue  
around the use of the taxpayer’s moneys via the aforesaid Grant. 
 
We advise originally funding was declined on two occasions, due to concerns that the 
project was not “Shovel Ready” and that there were concerns with both the Working Group 
(WG) and the Steering Group” (SG). (See Appendix 2) 
 
“CIP working group perspective difficult to bring back Project 2 again to SG” 
 
“cannot see SG changing their minds” 
 
This Teitei Housing project has already incurred consultancy costs of over $600,000 (not 
counting staff time) before breaking ground, before any infrastructure is put in place. 
Other development costings have been advised (but not verified), before appropriate 
consents have been approved (and conditions known if approved) and clearly without 
community support. We consider the proposal at this stage to not be practical or credible.  
We estimate that figure for consultants will rise to in excess of $1m before works 
commencing, being a large amount of the balance Grant approved and that the overall 
project cost will continue to skyrocket. 
 
In summary - With the addition of another consent relating solely to “earthworks”, Kainga 
under the Official Information Act
Ora & Ruapehu District Council hope to achieve compliance with the CIP/IRG Funding, viz. 
Breaking ground within 12 months of contract, being a condition of the agreement for this 
“Shovel Ready” Grant. They also are trying to get an approval that would then permit an 
add-on consent for subdivision (Because ‘you’ approved the earthworks.)   
 
As taxpayers and ratepayers we are deeply concerned. We have currently troubled fiscal 
Released 
times, and there is doubt as to who is to pay for the very likely blowout in costs to achieve 
this unwanted development. 
 
I ask that you carry out a full audit and investigation into this development proposal, its 
costings and future liability as a priority as it is time sensitive and critical. 
 
 
 
Ohakune Ratepayers and Residents' Society Inc.   



under the Official Information Act
Released 


Appendix 1 – Letter drop and email received 29 Nov 2023 
under the Official Information Act
Released 
 
Ohakune Ratepayers and Residents' Society Inc.   




Appendix 2 – CIP Minutes 11 December 2020 
under the Official Information Act
 
Released 
 
 
Ohakune Ratepayers and Residents' Society Inc.   



Appendix 3 – Project Risks, see highlighted 
 
under the Official Information Act
Released 
 
 
 
 
Ohakune Ratepayers and Residents' Society Inc.   



Appendix 4 – Key terms of agreement, see highlighted 
 
 
under the Official Information Act
Released 
Ohakune Ratepayers and Residents' Society Inc.