Dear Jack Jones
Thank you for your email of 30 January 2024 requesting information relating to the Land for Housing
Programme following information under the Of icial Information Act 1982 (the Act). I will answer each
of your questions below.
1. How much of the $722m of recyclable funding allocated to the Land for Housing
programme since its conception and to March 2022, as referred to in CBC-22-MIN-0015,
has been spent?
As at 31 December 2023, $693m of the $722m has been spent.
2. How many of the estimated 9,491 homes to be delivered through the allocation of funds
referred to in 1. above, have been completed and received CCC and title?
Of the estimated 9,491 homes originally estimated, 1,531 homes have been completed and have
received CCC and Title.
3. How many of the estimated 9,491 homes to be delivered through the allocation of funds
referred to in 1. above, have received building consent and are in construction?
Of the estimated 9,491 homes originally estimated, and the sites not completed 1,127 homes have
received building consent and are in construction.
4. How many of the estimated 9,491 homes to be delivered through the allocation of funds
referred to in 1. above, are yet to receive building consent?
Of the estimated 9,491 homes originally estimated, 6,068 homes are yet to receive building
consent. The vast majority of these homes relate to the Carrington site which is estimated to build
4,000 homes. This particular site is nearing a Development Agreement.
5. When does the Ministry expect to recycle the funding referred to in 1. above, back to the
Crown?
• 31% of sites have already recycled funds back to the Crown.
• 3% of sites wil recycle funds to the Crown before the end of the 2023/24
• 10% of sites wil recycle funds to the Crown before the end of the 2024/25
• 49% of sites wil recycle funds back to the Crown between July 2025 and 2030
• 7% of sites do not relate to recycling of funds.
For sites that are not yet contracted, there is a relatively high probably of change for the period that
funds are likely to be recycled.
6. Please supply a table with the following information:
a. Names of the 34 sites/developments acquired by the Land for Housing Programme,
the region they are in and the date of each contract (as referred to in CBC-22-MIN-0015)
Please see annex A. Some information has been withheld under section 9(2)(b)(ii) of the Act, to
protect information where the making available of the information would be likely unreasonably to
prejudice the commercial position of the person who supplied or who is the subject of the
information.
b. And for each site listed in a. above, the number of homes contracted to be built, the
number of homes completed, the number of homes under construction, the number of
homes yet to receive building consent and the forecast completion dates of both the
unconsented and under construction homes.
Please see annex B. Some information has been withheld under section 9(2)(b)(ii) of the Act.
7. How many of the 22 sites referred to as in the 2022 pipeline (as outlined in CBC-22-MIN-
0015) are under construction?
Eight of the sites are in the construction phase.
8. Of the estimated 4,000 homes referred to in the 2022 pipeline (as outlined in CBC-22-
MIN-0015), are complete, how many are under construction and how many are awaiting
consent.
Of the 22 sites 716 homes are complete, 1,127 homes are in construction and 6,068are yet to
receive consent.
9. How much of the additional $311.132 mil ion al ocated to the Land for Housing
programme as agreed in CBC-22-MIN-0015 has been spent and how many homes wil
that spend enable?
CBC-22-MIN-0015 allocated a total of $505.35m to the Land for Housing Programme (see rec 10
of CBC-22-MIN-0015). This included $55.354m which had already been incorporated in the prior
funding allocated under a previous appropriation, therefore reducing the new funding to
$449.996m.
Subsequently, $100.000m was allocated to the Build Ready Development Pathway under the
Affordable Housing Fund reducing this to $349.996m.
Of the revised $349.996m, the full amount is unspent and remains available for allocation. It is not
yet known how many homes this wil enable given due diligence assessments are yet to be
completed and Development Agreements are yet to be negotiated for remaining funds unspent.
10. When are the homes enabled by the spend referred to in the answer to 9. above forecast
to be completed.
It's too early to be able to determine when homes enabled by the spend are forecast for completion
because due diligence assessments are yet to be completed and Development Agreements are
yet to be negotiated for remaining funds unspent.
2
In terms of section 9(1) of the Act, I am satisfied that, in the circumstances, the decision to withhold
information under section 9 of the Act is not outweighed by other considerations that render it
desirable to make the information available in the public interest.
You have the right to seek an investigation and review of my response by the Ombudsman, in
accordance with section 28(3) of the Act. The relevant details can be found on the Ombudsman’s
website at:
www.ombudsman.parliament.nz.
As part of our ongoing commitment to openness and transparency, the Ministry proactively releases
information and documents that may be of interest to the public. As such, this response, with your
personal details removed, may be published on our website.
Yours sincerely
Matt Fraser
Head of Land Acquisition and Development
Te Tūāpapa Kura Kāinga – Ministry of Housing and Urban Development
3
4
Annex A
Territorial authority
Address
Development Agreement
Contract date
Christchurch City
Yaldhurst Road / Racecourse Road, Riccarton
05/15/17
Auckland
Moire Road, Massey
09/28/16
Auckland
Tuatahi - New North Road, Mt Albert
04/06/17
Auckland
Titoki Street, Te Atatu
10/10/18
Auckland
Great North Road, Waterview
10/14/19
Auckland
Belmont Rd, Pukekohe
12/21/18
Auckland
Great North Road, Waterview
05/04/17
Auckland
Great North Road, Avondale
12/03/20
Auckland
Kerrs Road, Great South Road, Wiri
03/15/21
Auckland
Browns Road, Manurewa
07/07/21
Queenstown-Lakes District Wakatipu High School, Queenstown
07/01/19
Wel ington City
Victoria Street, Te Aro
12/17/21
Auckland
Puhinui Park- Barrowcliffe Place, Manukau
08/15/18
Auckland
Glenfield School, Kaipatiki Road, Glenfield
06/29/23
Auckland
Ormiston Fields, Flat Bush School Road, Flat Bush
06/13/21
Auckland
Hospital Road, Middlemore Hospital, Otahuhu
06/24/21
Auckland
Jordan Avenue, Onehunga
07/08/21
Auckland
Alexander Crescent, Ōtara
08/31/23
Auckland
76 and 76a Waihoehoe Road, Drury, Auckland
Contracting in progress
Marlborough District
Hospital Road, Blenheim
Contracting in progress
Auckland
St Johns Road, St Johns
Contracting in progress
Waipa District
Laurent Road, Cambridge
Contracting in progress
Auckland
Unitec, Mt Albert
Contracting in progress
Tauranga City
Tara Road, Papamoa
Contracting in progress
Kapiti Coast District
Poplar Ave & Matai Road, Raumati South, Kapiti Coast
Contracting in progress
[9(2)(b)(ii)]
Auckland
Mt Albert (part of Unitec site)
Contracting in progress
Auckland
Carrington Road (part of Unitec site)
Contracting in progress
Auckland
MIT - Sth Campus + North Campus, Ōtara
Contracting in progress
5
Annex B
Homes
Recycle
Under
Forecast
Funding
Territorial authority
Address
Total
Completed
Yet to receive
Yield (CCC and Title) BC (Q3) (Q4) Constructio completion
Period
(Q2)
n (Q3)
date
(Financial
Year)
Christchurch City
Yaldhurst Road / Racecourse Road, Riccarton
153
153
Received BC Completed Completed Completed
Auckland
Moire Road, Massey
197
197
Received BC Completed Completed Completed
Auckland
Tuatahi - New North Road, Mt Albert
119
119
Received BC Completed Completed Completed
Auckland
Titoki Street, Te Atatu
37
37
Received BC Completed Completed Completed
Auckland
Great North Road, Waterview
95
95
Received BC Completed Completed Completed
Auckland
Belmont Rd, Pukekohe
93
93
Received BC Completed Completed Completed
Auckland
Great North Road, Waterview
121
121
Received BC Completed Completed Completed
Auckland
Great North Road, Avondale
117
117
Received BC Completed Completed Completed
Auckland
Kerrs Road, Great South Road, Wiri
430
79
Received BC
351
2025-26 H1
2023/24
Auckland
Browns Road, Manurewa
161
58
Received BC
103
2024-25 H1
2024/25
Queenstown-Lakes District Wakatipu High School, Queenstown
292
27
Received BC
265
2027-28 H2
2030/31
Wel ington City
Victoria Street, Te Aro
110
41
Received BC
69
2025-26 H2
2024/25
Auckland
Puhinui Park- Barrowcliffe Place, Manukau
189
138
Received BC
51
2026-27 H2
N/A
Auckland
Glenfield School, Kaipatiki Road, Glenfield
96
0
BC in progress
0
2028-29 H2
2028/29
Auckland
Ormiston Fields, Flat Bush School Road, Flat Bush
168
46
Received BC
122
2024-25 H2
2025/26
Auckland
Hospital Road, Middlemore Hospital, Otahuhu
440
0
BC in progress
(109 received)
109
2028-29 H1
2028/29
Auckland
Jordan Avenue, Onehunga
210
210
Received BC
0
Completed Completed
Auckland
Alexander Crescent, Ōtara
57
0
Received BC
57
2024-25 H1
2024/25
Auckland
76 and 76a Waihoehoe Road, Drury, Auckland
301
0
301
0
2029/30 H1
2030/31
Marlborough District Hospital Road, Blenheim
85
0
85
0
2025-26 H2
2026/27
Auckland
St Johns Road, St Johns
60
0
60
0
2027-28 H1
2027/28
Waipa District
Laurent Road, Cambridge
180
0
180
0
2025-26 H2
2026/27
Auckland
Unitec, Mt Albert
4,000
0
4,000
0
2031-32+
2031/23
Tauranga City
Tara Road, Papamoa
400
0
400
0
2029-30 H1
2031/32
Kapiti Coast District
Poplar Ave & Matai Road, Raumati South, Kapiti
Coast
170
0
170
0
2026-27 H1
2027/28
[9(2)(b)(ii)]
Auckland
Mt Albert (part of Unitec site)
Unitec
Unitec
2031/23
Auckland
Carrington Road (part of Unitec site)
Unitec
Unitec
2031/23
Auckland
MIT - Sth Campus + North Campus, Ōtara
445
0
445
0
2028-29 H1
2031/32
Total
29
8,726 1,531
6,068
1,127
When the Land for Housing Programme acquires a site and moves to a Development Agreement, the delivery date can change through a
variation and the number of homes to be delivered can change (given the yield for a site is always the minimum).
7