This is an HTML version of an attachment to the Official Information request 'Costs of producing 'before the deluge' reports'.
Te Uru Kahika River Managers SIG Co-investment Business Case Roadmap - Project Plan Action Planning
DRAFT v2  12 July 2022
No. Activity Task Event
July
August
Sept
Oct
Nov
Dec/Jan
Feb
PHASE 1 - Project Establishment & 
Agreed Approach
1 Clarity on exactly what is required. 
21-Jul
(Ref JH Te Ura Kahika Paper 12 July)
2 Key milestone events timings: 
Final Cabinet Meetings for Budget 23
Feb March
Finalising of Implementation 
arrangements 
25-Nov  
Cabinet Strategic Phase Meeting   
 
Est 8 or 15 Nov
Final Detailed Business Case delivered
28-Oct
Delivery of Strategic Bus Case to 
Ministers
30-Sep
Final Draft Bus Case for RCEOs & DIA
23-Sep
 
RCEOs Mtgs incl RM SIG Kānoa CR Co-
investment Update
18-Aug
10-Nov
Governance Group & Steering Group 
with DIA MfE NEMA & Treasury 
Officials in place incl agreement on 
draft bus case contents. 
18-Aug
Kānoa CR Advisory Board Mtg 
12-Aug
Bus Case Project Core Team in place 
incl Outline stage for Initial Draft Bus 
Case
5-Aug
Communications engagement plan 
prepared and agreed to. 
18-Aug
3 RM Champions sign off Roadmap 
Project Plan incl prep budget
27-Jul
Roadmap Project Plan draft for RM 
Champions incl Initial Draft Bus Case 
Contents List & Draft Preparation 
Budget
21-Jul
Comms engagement plan outline 
prepared and agreed to by RM 
Champions 
27-Jul
PHASE 2 - Background Research
4 Review and progress investment 
intentions T+T & internal data 
gathering that is underway
21-Jul
Including: T+T LTPs 30 Year Strategies; 
National Regional Register of Assets; 
and Updating Hiding in Plain Sight Chap 
4 & 5 including Benefits.
Done 31 Aug
Request councils to develop prioritised 
projects that includes info to satisfy the 
nine enquiry areas, priority, timing and 
funding requirements of projects.
27-Jul
Done 31 Aug
Consolidate the results across regions.
31-Aug
5 Assess findings from DIA Westport Bus 
Case Review & DIA T+T NIWA RM 
Vulnerability Locations Study
27-Jul
Done 18 Aug
Commission 3rd party research as 
appropriate eg T+T, NIWA etal
18-Aug
 

6 RM SIG to use consolidated results to 
develop an Aotearoa Flood Risk 
Resilience cost share and project 
prioritisation proposal.
Done 31 Aug
PHASE 3 - Enquiry - test co-investment 
proposal
7 Steering Group & Governance review 
and finalising endorsement of 
proposed cost share and annual 
prioritisation formula.
23-Sep
PHASE 4 - Develop consolidated 
business case using the Better 
Business Case framework
8 Draft Business Case 
Draft components - initial draft
25-Aug
Draft consolidated business case - 
initial draft 
31-Aug
Review finalise with DIA Treasury etal 
as consolidated draft
23-Sep
Finalise and complete for delivery to 
Ministers
30-Sep
PHASE 5 - Budget-build process
9 Support from RM SIG & Advisors for 
budget-build process led by DIA 
officials.
PHASE 6 - Implementation 
arrangements
10 Establish arranagements through 
which agreed co-investment projects 
are managed and delivered on time 
and within the agreed budget.
25-Nov