This is an HTML version of an attachment to the Official Information request 'Railway bridges, - Westport to Sergeants Hill'.
 
 
 
 
 
2 October 2007 
 
 
New Zealand Railways Corporation 
Enquiries to: 9(2)(a) Privacy  
C/- McNulty Engineering Management Ltd 
Our Reference:  RC07176 
PO Box 193 
HOKITIKA 
Attention: 9(2)(a) Privacy
 
 
 
Dear 9(2)(a) Privacy  
 
NEW ZEALAND RAILWAYS CORPORATION 
RESOURCE CONSENT FILE NUMBER RC07176 
COASTAL PERMITS RC07176/8-12 
LAND USE CONSENT RC07176/13 
DISCHARGE PERMIT RC07176/14 
 
By  delegated  authority  of  Council  you  are  advised  that  the  above  application  for  resource 
consent has been granted. 
 
Please note that this letter is not the actual resource consent document (refer to Objection and 
Costs Sections at end of the letter). 
 
DECISION 
 
Pursuant  to  Sections  104B,  104C  and  105  of  the  Resource  Management  Act  1991,  five  (5) 
Coastal Permits, one (1) Land Use Consent and one (1) Discharge Permit have been granted to 
New  Zealand  Railways  Corporation  for  the  purpose  as  described  below  and  subject  to  the 
following conditions. 
 
PURPOSE OF RESOURCE CONSENT 
 
Consent No 
Consent Type 
Activity / Location 
RC07176/8 
Coastal Permit 
To occupy space in the Coastal Marine Area for Railway 
Bridge 123, north of Westport. 
 
 
RC07176/9 
Coastal Permit 
To remove an existing bridge, and erect a replacement 
bridge  within  the  Coastal  Marine  Area,  north  of 
Westport. 
RC07176/10 
Coastal Permit 
To  remove  and  deposit  material  within  the  Coastal 
Marine  Area  at  Orowaiti  Lagoon  for  the  purpose  of 
replacing Railway Bridge 123, north of Westport. 
RC07176/11 
Coastal Permit 
To  take  coastal  water  from  the  Orowaiti  Lagoon 
associated with the replacement of Railway Bridge 123, 
north of Westport. 

Consent No 
Consent Type 
Activity / Location 
RC07176/12 
Coastal Permit 
To  incidentally  discharge  sediment  to  the  Coastal 
Marine  Area  at  Orowaiti  Lagoon  associated  with  the 
replacement of Railway Bridge 123, north of Westport. 
RC07176/13 
Land Use Consent 
To  undertake  earthworks  and  clear  vegetation  within 
the  riparian  margins  of  the  Orowaiti  Lagoon  for  the 
purpose  of  replacing  Railway  Bridge  123,  north  of 
Westport. 
RC07176/14 
Discharge Permit 
To discharge liquid from the dewatering of bridge piles 
to  land,  associated  with  the  replacement  of  Railway 
Bridge 123, north of Westport. 
 
LOCATION 
 
Railway Bridge 123, Orowaiti Lagoon 
 
MAP REFERENCE 
 
At or about NZMS 260 K29: 961-374 
 
CONSENT CONDITIONS 
 
Pursuant to Section 108 of the Resource Management Act 1991, the Resource Consents include 
the following conditions: 
 
1.  Works and activities shall be carried out in general accordance with the details contained in 
the consent application submitted to the Consent Authority, except where inconsistent with 
these  conditions.    Any  change  or  cancellation  of  consent  conditions  shall  be  done  in 
accordance with Section 127 of the Resource Management Act 1991. 
 
2.  The Consent Holder shall supply any agent or contractor working under these consents with 
a copy of the consents.  
 
3.  Any  person  working  under  these  consents  shall  have  a  copy  of  the  consents  on  site  and 
present it to an officer of the Consent Authority upon request. 
 
4.  While exercising these consents the Consent Holder shall ensure that: 
 
a) 
The Westport water main is not damaged; 
b) 
Unnecessary damage to lagoon banks and lagoon bank vegetation is avoided; 
c) 
No land instability or erosion occurs; 
d) 
Existing access points are used where practicable; 
e) 
No refuelling or fuel storage occurs in the lagoon bed or within 3 metres of the 
banks of the lagoon; 
f) 
Machinery activity in the wet bed of the lagoon is kept to a minimum; 
g) 
All machinery is cleaned before entering the lagoon bed; and 
h) 
All  refuse,  rubbish  and  debris  are  removed  and  disposed  of  at  a  suitably 
approved site. 
 
 
 

5.  All  disturbed  vegetation,  soil  or  debris  shall  be  deposited  or  contained  to  prevent  the 
movement of the disturbed matter so that it does not result in: 
 
a) 
The diversion or blockage of any water body; or 
b) 
The passage of fish being impeded; or 
c) 
Flooding or erosion. 
 
6.  The Consent Holder shall ensure that sediment losses to natural water from the exercise of 
these consents are avoided. 
 
7.  Refuelling,  lubrication  and  any  mechanical  repairs  of  any  equipment  used  under  these 
consents  shall  be  undertaken  in  such  a  manner  so  as  to  ensure  that  no  spillages  of 
hazardous substances onto the land surface or into water occur. If a fuel spillage in excess 
of 20 litres occurs, the Consent Holder shall inform the Consent Authority immediately. 
 
8.  Notwithstanding  Condition  7,  no  lubrication,  cleaning  or  mechanical  repairs  shall  be 
undertaken within the coastal marine area or the bed of the Orowaiti Lagoon. 
 
9.  To  avoid  the  spread  of  Didymo,  no  equipment  shall  be  used  in  the  exercise  of  these 
consents  that  has  been  used  previously  to  undertake  activities  in  the  Buller  River  or  any 
other  water  body  know  to  contain  Didymo,  unless  that  equipment  has  been  thoroughly 
cleaned in accordance with the attached Biosecurity New Zealand document titled “Cleaning 
Methods for Freshwater Activities”. 
 
10.  The Consent Holder shall ensure that any flax plants removed during the exercise of these 
consents  shall,  as  far  as  practicable,  be  replanted  at  their  original  locations  at  the 
completion of the bridge replacement works. 
 
11.  In  the  event  of  any  disturbance  of  Koiwi  Tangata  (human  bones)  or  Taonga  (artefacts, 
including pounamu), the Consent Holder shall: 
 
a) 
Cease any further excavation for a period of at least 24 hours; and 
b) 
Immediately advise the Consent Authority of the disturbance; and 
c) 
Immediately advise the Upoko of the Papatipu Runanga, or the representative, 
of the disturbance; and 
d) 
Immediately  advise  the  Regional  Archaeologist  of  the  New  Zealand  Historic 
Places Trust, except in relation to disturbance of unworked pounamu. 
 
12.  If  the  Consent  Holder  identifies  any  archaeological  remains  or  potential  areas  or  sites  of 
historic  value,  the  Consent  Holder  shall  immediately  notify  the  Consent  Authority  and  the 
Regional Archaeologist of the New Zealand Historic Places Trust. 
 
13.  The  Consent  Holder  shall  pay  to  the  Consent  Authority  such  annual  administration, 
supervision and monitoring fees as are fixed from time to time by the Consent Authority in 
accordance with Section 36 of the Resource Management Act 1991. 
 
TERM 
 
The term of RC07176/8 is for 35 years from the date of issue.  The term of RC07176/9-14 is for 
1 year from the date of issue. 
 

NOTES TO THE CONSENTS 
 
The Consent Holder is advised that the consent does not confer a right of access and the 
Consent Holder should be aware the permission of the legal owner or administering body of the 
bed of the lagoon may also be required. 
REASON  FOR  DECISION  PURSUANT  TO  SECTION  113,  RESOURCE  MANAGEMENT 
ACT 1991 
 
In  making  this  decision  to  grant  the  resource  consents  the  purposes  and  principles  of  the 
Resource Management Act 1991 as set out in Part II of the Act have been achieved along with 
consideration  of  Section  104,  which  requires  an  assessment  of  the  effects  of  the  proposed 
activity. 
 
The  nature  of  the  works  authorised  under  this  decision  are  consistent  with  the  Council’s 
Regional Policy Statement.  Specific objectives and policies in respect of Poutini Ngai Tahu, Soils 
&  Rivers,  Water,  Habitats  &  Landscapes,  Coastal  Environment  and  Network  Utilities  &  are 
contained within Chapter 7 of the Regional Policy Statement (see Table 1). 
 
The occupation of the Coastal Marine Area by the replacement bridge is a discretionary 
activity under Rule 7.5.1.5 of the Regional Coastal Plan. 
 
The  erection  of  the  replacement  bridge  in  the  Coastal  Marine  Area  is  a  discretionary 
activity under Rule 8.5.1.8 of the Regional Coastal Plan. 
 
The  maintenance  of  the  replacement  bridge  within  the  Coastal  Marine  Area  is  a 
permitted activity under Rule 8.5.2.2 of the Regional Coastal Plan. 
 
The  removal  of  the  existing  bridge  from  the  Coastal  Marine  Area  is  a  discretionary 
activity under Rule 8.5.3.2 of the Regional Coastal Plan. 
 
The  removal  of  soil  and  gravels  from  the  lagoon  bed  is  a  discretionary  activity  under 
Rule 9.5.2.4 (alteration) and Rule 9.5.3.7 (disturbance) of the Regional Coastal Plan. 
 
The deposition of material in the bed of the Orowaiti Lagoon in the Coastal Marine Area is a 
discretionary activity under Rule 9.5.4.2 of the Regional Coastal Plan. 
 
The  incidental  discharge  of  sediments  to  the  Orowaiti  Lagoon  (Coastal  Marine  Area)  is  a 
discretionary activity under Rule 10.5.7.2 of the Regional Coastal Plan. 
 
The  use  of  coastal  water  is  a  permitted  activity  under  Rule  11.5.2.1  of  the  Regional 
Coastal Plan. 
 
The  abstraction  of  groundwater/surface  water  from  the  Orowaiti  Lagoon  in  the  Coastal 
Marine Area is a discretionary activity under Rule 11.5.3.2 of the Regional Coastal Plan. 
 
The  earthworks  within  riparian  margins  of  Orowaiti  Lagoon  is  a  discretionary  activity 
under Rule 6.1.6.1 of the Proposed Regional Land and Riverbed Management Plan. 
 
The  vegetation  disturbance  within  riparian  margins  of  Orowaiti  Lagoon  is  a 
discretionary  activity  under  Rule  6.1.6.1  of  the  Proposed  Regional  Land  and  Riverbed 
Management Plan. 
 
The discharge  of dewatering liquid to land (outside riparian margins) is a discretionary 
activity under Rule 28 of the Regional Plan for Discharges to Land.