This is an HTML version of an attachment to the Official Information request 'Request for correspondence and reports on the New timetable for Johnsonville train line'.



 
 
 
 
 
 
Tranz Metro Communications 
 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
Customer Communications review for the 
Johnsonville Line 
 
1. Purpose 
The purpose of this document is  

  
 
 
M:\National Passenger\Planning and Performance\... 
 



 
Slippery track conditions are the most common reason for disruptions on the Johnsonville Line, 
particularly during the winter months. The grade of 1 in 36 on the steepest part of the line makes 
the Johnsonville Line one of the steepest commuter lines in Australasia. When dew or overnight 
frost settles on the tracks, this causes adhesion issues for the trains, which means that services 
often struggle to keep up to the current timetable. 
 
The fact that the Johnsonville Line is predominantly single line track compounds delays to 
services, meaning that any small delay has a knock on effect, especially during the peak travel 
periods. These small delays haven’t been factored into the current timetable 
 
There are other factors that contribute to disruptions on the Johnsonville Line, such as operational 
reasons, points and signal faults, land slips and mechanical faults just to name a few. 
The key numbers: 
 

•  Between April and July, there were 58 days of service disruptions on the Johnsonville 
Line.  
 
•  Of those 58 days, slippery track conditions accounted for 34 days. 
 
•  The YTD on time performance of the Johnsonville Line is currently sitting at 84 per cent. 
 

  
 
 
M:\National Passenger\Planning and Performance\... 
 



 
4. Proposal 
To try and minimise the effect that delays have on the on time performance of the Johnsonville 
Line, KiwiRail and Greater Wellington Regional Council trialled a new morning and afternoon peak 
timetable last October that proved successful. The hope now is to have this timetable 
implemented as soon as practicable, taking into account the roster changes and associated notice 
periods, plus the availability of additional rolling stock. 
 
Attached is a copy of the proposed new timetable for the Johnsonville Line. The main features 
are: 
 
•  Morning Peak - An increase in journey time from 21 minutes to 23 minutes for services 
travelling from Johnsonville to Wellington. Services from Wellington to Johnsonville will 
now be scheduled to take 28 minutes. (the additional time is designed to allow recovery in 
the timetable on services with lower patronage) 
 
•  Evening Peak - The timetable will reverse in the afternoon. Services from Wellington to 
Johnsonville taking 23 minutes and services from Johnsonville to Wellington taking 28 
minutes. 
 
•  Providing more regularity for passengers travelling during peak travel periods, with 
services departing every 15 minutes from Johnsonville during morning peak, and every 15 
minutes from Wellington during afternoon peak. 
 
•  An extra Friday night service (9.32pm), which would bring the Johnsonville Line into line 
with both the Kapiti Line and Hutt Valley Line in terms of Friday night service coverage. 
 
•  To run this timetable we require a minimum of eight two car Matangi trains, which would 
run as four, 4-car Matangi services. It is preferable that Matangi Mark 2 trains that have 
wheel dampeners are used. 
 
The graphic below displays the service pattern based on a 15 minute departure timetable 
for the Morning Peak from 7.00am until 8.00am. 
 
 

  
 
 
M:\National Passenger\Planning and Performance\... 
 



 
5. Timeframe 
Rolling stock and staffing 
 
We have a proposed implantation date of Sunday 25 October. Below is a schedule of key dates  
 
 
for tasks to be completed or implemented by our Operations and Service Support Team. 
 
Operations tasks 
Start date 
Lead in 
Completion date 
time 
 
 
 
 
Have the time table 
Monday, 3 August 
1 weeks 
Friday, 7 August 
agreed with GWRC  
 
 
 
 
 
Start writing new roster 
Monday, 10 August 
3 weeks 
Friday, 28 August 
 
 
 
 
 
Consultation with roster 
Monday, 31 August 
2 weeks 
Sunday, 13 September 
representatives 
 
 
 
 
Consultation with staff 
Sunday, 13 September 
6 weeks 
Saturday, 24 October 
 
 
 
 
 
Implementation of new 
Sunday, 25 October 
N/A 
N/A 
timetable 
 
 
 
Tasks to be done in parallel with time table introduction 
Operations tasks 
Start date 
Lead in 
Completion date 
time 
 
 
 
 
New berthing/rolling stock 
Thursday, 1 October 
2 weeks 
Wednesday, 14 October 
arrangements 
 
 
 
Communications 
If we were to implement the new timetable on Sunday, October 25, KiwiRail would require a 
minimum of four weeks to ensure that passengers are informed of the timetable change (Monday, 
28 September). A further three weeks would be required from the implementation date to make 
changes to both OMS and VIX Horizon, so that the Real Time Information system is able to track 
services operating to the new timetable. 
 
 
5. Costs 
Whilst this proposal offers additional services, adding to customer satisfaction and potential 
patronage growth, the costs of implementation are expected to be small. From the initial 
assessment of the proposed timetable there are minimal impacts on staff numbers and the 
additional vehicle km should not translate to extra maintenance costs due to the time based 
maintenance limits prescribed by the Unit Maintenance Plan.  
 
 

  
 
 
M:\National Passenger\Planning and Performance\... 
 



 
6. Conclusion 
 
It is expected that with a more realistic timetable, delays to services on the Johnsonville Line will 
be minimised and our passengers will see improvement in the reliability of services. The new 
timetable should alleviate the pressure that small delays cause to services and eliminate the 
knock on effect that they have. 
 
The different journey times, depending on the time and direction of the service, prioritises the 
majority of passengers travelling during the peak travel periods, which makes this timetable 
commuter friendly. 
 
Providing Johnsonville Line passengers with services that depart on a clock face timetable will 
create better certainty for passengers and falls into line with other commuter rail systems 
throughout the world.  
 
 
 
 
 
 
 
 
 
 

  
 
 
M:\National Passenger\Planning and Performance\...