12 February 2016 
Mr Ben Ross 
[FYI request #3520 email]
Dear Mr Ross 
Local Government Official Information and Meetings Act 1987 
Manukau Bus Interchange - CAS-182276-S0J1X3 
Thank  you  for  contacting  Auckland  Transport  on  2  January  regarding  the  Manukau  Bus 
Interchange. 
I  have  noticed  through  Auckland  Transport  website  that  the  enabling  works  due  to  start  late 
December,  2015 or  early January,  2016 (according to  the  Tender documents)  have been delayed to 
the following situation: 

Final concept designs released: end of January 
Enabling works: February April 
Main works: May until completion August 2017 (indicative per Auckland Transport in November 
when the concept drawings came out for public submission) 
1.
Are those above dates different to any initial dates for the Manukau Interchange construction
time line as of at the end of November,  2015 when the public submissions on the Interchange
closed?

These dates have not changed since public consultation was carried out in November,  when
the following dates were included in the consultation material.
Enabling works - The enabling works date of Feb - Apr 2016. 
Main Works - Commencement of construction Aug 2016. Completion due August 2017 
2.
If the dates have changed what has caused this recent set of delays?
There have been delays from the initial construction dates.  These are associated with;
Confirmation of the functional brief/requirements for the bus station required as part of the 
consultant firming up design criteria. 
Completion  of concept  design  due  to refinements required  to  ensure  that the consultant 
provided an acceptable design of a functional station. 
3.
What changes are being done to the concept designs that were released to the public in
November and why please?
In accordance of section 1 ?(d) of the LGOIMA, we decline to answer as the information
requested is or will soon been publicly available.
a ucklandtransport.govt. nz