Performance Based Maintenance Contract [Draft]
Page 91
3.
TIMEFRAMES FOR RESPONSE / SCOPING AND COMPLETION
3.1
General
(a)
The relevant categories of Work must be responded to, assessed, Scoped and Completed in
accordance with the timeframes below. The Contractor must program, plan and establish the
processes necessary to carry out the Work with due expedition and without delay and in a
manner sufficient to meet its obligations under this Agreement.
(b)
In this clause 3:
(i)
for URG, references to ‘hours’ are to all hours and are not to be construed as
references to Working Hours; and
(ii)
for all other sub-categories, references to ‘hours’ are to all hours on a business day
and are not to be construed as references to Working Hours.
3.2
Responsive Maintenance
Timeframes for Responsive Maintenance are:
Timeframes
Sub-category
Response/Scoping
Completion
URG
4 hours
12 hours
URS
24 hours
48 hours
GNL
Not applicable
10 business days or such other timeframe as
HNZ may specify in writing acting reasonably
RSC
Scope delivery: 72
15 business days or such other timeframe as
hours or such other
HNZ may specify in writing acting
timeframe as HNZ may
reasonably*
specify acting
reasonably
Estimated completion
date: 48 hours from
HNZ approval of Scope
VSC
Scope delivery: 72
15 business days or such other timeframe as
hours or such other
HNZ may specify in writing acting reasonably
timeframe as HNZ may
*
specify acting
reasonably
Estimated completion
date: 48 hours from
HNZ approval of Scope
Notes:
* denotes timeframes that start on approval of the Scope and acceptance of a date for Completion by
HNZ.
All other timeframes run from the time HNZ releases the Work Order to the Contractor (as shown
conclusively on the time stamp for the Work Order as given by HNZ’s IT Systems).