Minutes
Devonport to Takapuna Green Routes
Date:
23 August 2016
Time:
10.00am
Venue:
HSBC
Attendees:
Patricia Vasconcelos, (PV) Ina Stenzel (IS), Melissa Clark (MC)
Apologies:
Item
Topic
Update / Actions
Responsible
1
Progress
1.1
Ina has received the tool from MCgney – we can use it although
it is still work in progress
2.2
Agreed using the road widths from GIS is appropriate at this
stage of the design process
2.3
IS & MC had a site visit – discounted route at northern end
eastern side (Hauraki/Ewen/Cliffton) as an alternative to Lake,
not possible due to topography.
2.4
Options around Old lake Rd/Park discussed – check if park is AC
or private. A connection could also be provided to the café/beach
2.5
Investigate Buchanan/Rattray for option for route to avoid
Devonport town centre
2.6
Stanley Ferry link – future project, outside of our scope
2.7
Look at changing priority of Victoria/Abbortsford to allow cycle
priority up the hill.
2.8
Consider saety in parks/lighting when using as alternatives- note
about Ngataranga Park
2.9
Seabreeze – future link to consider
2.10
Change to Regent from Wesley (avoid walkway)
2.11
Liam Winter – Panuku contact re. Takapuna
Next Meeting – 6 September 2016 - 10am - Henderson
Project - Minutes - Meeting Name - Date