PT Funding Review 2016 – Scope paper 
1 December 2016 
 
 
 
Prepared by Helen Chapman 
 
 
 
 
 
 
PT Funding review scope  
PAPER 
Page 1 of 13 
 

Version control 
Date 
Person 
Description 
25 November 2016 
Helen Chapman 
•  First draft 
1 December 2016 
Helen Chapman 
•  Refinements to draft 
12 December 
Tass Larsen 
•  Revision 
 
 
 
 
PT Funding review scope paper 
Page 2 of 13 
 

Contents 
1  Introduction ...............................................................................................................................................4 
2  Problem Definition ....................................................................................................................................4 
2.1 
The transport rating model ..............................................................................................................4 
2.2 
Issues with the current model..........................................................................................................5 
2.3 
The public transport transformation project ....................................................................................6 
3  Objectives ..................................................................................................................................................7 
4  Scope .........................................................................................................................................................7 
4.1 
Scope of the PT Funding Review ...................................................................................................7 
4.2 
Fit with existing Revenue and Finance Policy ................................................................................7 
4.3 
Regional land transport plan ...........................................................................................................8 
4.4 
Regional public transport plan ........................................................................................................9 
5  Methodology .............................................................................................................................................9 
6  Resources ................................................................................................................................................10 
6.1 
Budget ...........................................................................................................................................10 
6.2 
People ............................................................................................................................................10 
Appendix one: Indicative timeline and task breakdown ..............................................................................11 
 
 
 
 
PT Funding review scope paper 
Page 3 of 13 
 

1  Introduction 
This  report  sets  out  the  problem  definition,  objectives  and  scope  for  the  review  of  the 
public  transport  rate  funding.  About  25%  of  the  operational  cost  of  providing  public 
transport  in  the  Wellington  Region  is  raised  through  rates.  Fare  revenue  makes  up 
approximately  55-60%  (reflecting  user  benefits)  and  the  remainder  is  funded  from  road 
users by central government through the National Land Transport Programme (NLTP).  
Public transport funding is used for: 
•  Metlink public transport network funding 
•  rail operations and asset management 
•  bus and ferry operations and asset management 
•  Metlink customer services and information. 
 
The need for a review has been triggered by two key factors: 
•  Concern from council that the current rating approach for transport is difficult to 
understand and therefore hard to explain/defend 
•  The public transport transformation programme is making a number of changes, 
including  new  contracts,  a  new  network  and  a change  to  integrated ticketing  and 
fares.  
This paper sets out the problem definition, identifying why we are undertaking a review 
now.  The  objectives  of  the  review,  the  scope  of  the  review  key  interdependencies and  a 
high level methodology.  
This review is an input into the wider review of the Revenue and financing policy.  The 
key interdependencies are: 
•  The development of the Long Term Plan 2018-2028 
•  The Public transport transformation programme 
•  The regional land transport plan review  
2  Problem Definition 
The  public  transport  funding  policy  methodology  used  to  raise  rate  funding  for  public 
transport  is  lacking  in  transparency,  is  based  on  a  rationale  that  is  poorly  aligned  with 
other strategic documents and does not reflect benefits well. 
2.1  The transport rating model 
GWRC  currently  rates  for  public  transport  using  a  targeted  transport  rate  on  a  basis  of 
cents per dollar of capital value, with a discount for rural proprieties. Cost are apportioned 
to the different city and district council areas in the region using a model that uses census 
journey  to  work  data  to  calculate  a  congestion  benefit,  and  route  based  data  to  allocate 
public  transport  operating  costs  to  intra  district  services  and  inter  district  services.  A 
proportion  of  the  cost  of  inter  district  services  (particularly  rail)  is  allocated  to  the 
Wellington central business district. 
This policy is described in the 2015-2025 LTP as “The transport rate funds GWRC’s net 
expenditure (after deducting fare and Central Government contributions) for the region’s 
public  transport  services,  including  public  transport  operations,  infrastructure  and 
marketing  activities.  This  rate  is  apportioned  principally  on  the  basis  of  a  surrogate 
PT Funding review scope paper 
Page 4 of 13 
 

congestion charge. The transport rate to be recovered from each territorial authority area 
is set on the basis of capital values.”  
The  transport  rate  forms  part  of  the  revenue  and  financing  policy.  It  is  a  requirement 
under  s102  of  the  Local  Government  Act  2002  to  have  a  revenue  and  financing  policy. 
S103 of the Act provides more detail on the policy sets out the possible sources of funding 
councils may use. This work is occurring as an input to a wider review of the revenue and 
financing  policy.  Further  detail  on  the  current  revenue  and  financing  policy  and  the 
review is in section 4.2 of this paper.  
The current transport rating policy has been in place since 2006.  
It is now timely to undertake a full review as: 
•  The current long term plan indicated that the rates funding for public transport be 
reviewed.  
•  The development  of  the  2018-2028  Long  Term  Plan  provides  an  opportunity to 
ensure  any  proposed  changes  are  aligned  with  the  councils  wider  planning  and 
financial management. 
•  The transport rate is the most complex aspect of the revenue and financing policy, 
and accounts for the largest area of council expenditure.  
•  The public transport transformation project is making significant changes that both 
impact upon, and may be impacted by any changes to how the rates component of 
funding is raised.   
2.2  Issues with the current model 
A  number  of  issues  with  the  current  approach  to  setting  the  transport  targeted  rate  have 
been identified.   
•  The  policy  rationale  for  using  a  targeted  transport  rate  as  a  surrogate  for  a 
congestion  charge  is  weak  and  not  well  aligned  with  current  strategic  planning 
documents including the regional land transport plan, and regional public transport 
plan.  
•  The detail of the transport rating approach is hard to explain and the rationale for 
the split between 95% congestion, 5% accessibility is unclear. The 95% of public 
transport  costs  that  are  ascribed  to  congestion  relief  and  concessionary  travel 
doesn’t  align  well  with  the  percentage  of  the  current  or  planned  network  that 
provides  local  or  targeted  services  focused  on  accessibility.  There  is  confusion 
about how the costs ascribed to congestion relief are then allocated to local council 
areas and what service costs are considered intra-district, or inter district.  
•  The current approach does not provide full transparency on cost allocation because 
some  of  the  information  is  commercially  sensitive  under  net  cost  contracts. 
Although  some  of  the  concern  around  a  lack  of  transparency  seems  largely  to 
relate to a lack  of acceptance of the different treatment of inter- and intra-district 
trips, although the difference is clearly set out in the policy.  
•  Because of the funding formula, changes in the allocation of rates between areas 
occur based on changes in census data (journey to work figures), which increases 
the variability in the incidence of rating (others factors are changes in the cost of 
individual services and changing rating valuations).  
•  The  approach  where  costs  are  allocated  to  districts  results  in  the  level  of  rates 
people pay relating more to the costs of providing a service in an area than to the 
service level (benefits). This creates boundary issues (properties on different sides 
of  a  street  can  pay  very  different  transport  rates)  and  contrasts  with  the  network 
PT Funding review scope paper 
Page 5 of 13 
 

wide approach we take to user benefits - i.e. we don’t require individual services 
or services in each geographical area to meet the farebox recovery target of 55%.  
•  Concerns  have  been  raised  about  the  whether  the  amount  paid  by  business 
ratepayers  in  the  Wellington  central  business  district  (approximately  30%)  is 
justified, and if the cost allocation between districts is equitable.  
•  Changes to government funding for off-peak SuperGold card travel may impact on 
the  balance  of  funding  between  fares,  NLTF  funding  and  rates  funding.  The 
change  to  bulk  funding  has  effectively  changed  SuperGold  card  from  a  fare 
substitute to another revenue stream (that is not directly tied to usage).  
2.3  The public transport transformation project 
There is currently a major transformation underway in the provision of public transport in 
Wellington, including new contracts, new routes, and a new integrated fares and ticketing 
(IFT)  system.  This  transition  potentially  impacts  on  both  the  overall  balance  of  funding 
and  the  availability  of  financial  information  used  in  the  model  underlying  the  transport 
rate and necessitates a review.  
2.3.1  New contracting environment 
Once the transition is complete all services will be operated under contract replacing the 
current  split  of  contracted  and  commercial  services.  PTOM  contracts  are  based  on  the 
gross  cost  of  operating  services,  with  fare  revenue  going  to  the  council  to  offset  costs. 
Previously  operators  have  been  paid  the  difference  between  operating  costs  and  fare 
revenue on a net basis. Under this regime, some operator data is unable to be shared with 
the public as it is commercially sensitive. Under PTOM contacts GWRC will have a much 
clearer picture of operating costs on a unit basis (although not for individual routes) and 
fare revenue information will no longer be commercially sensitive.  
A  new  network  is  being  introduced,  making  significant  changes  to  routes.  Routes  will 
form part of operating units. Units are mode specific and contain core, local, and targeted 
services.  The  current  direct  allocation  of  costs  based  on  individual  bus  routes  will  no 
longer be possible. Currently, costs by route have been allocated to intra, or inter districts. 
The  rail  contract  (the  major  component  of  inter-district  services  in  the  rating  model)  is 
managed and structured in such a way that any break down of rail costs by line would be 
arbitrary  and  therefore  contestable.  Rail  feeder  bus  services  have  also  being  considered 
inter  district  but  these  will  now  be  bundled  as  part  of  bus  units,  e.g.  Lower  Hutt. 
Consequentiality if the current funding policy is retained it will be necessary to develop a 
cost allocation model to break down unit costs into costs for specific routes.  
2.3.2  Integrated fares and ticketing 
The  Integrated  Fares and  ticketing  transition  and fares review  will  change  the  way  fares 
are  charged  and  patronage  and  revenue  data  collected.  As  part  of  the  wider  IFT  a 
comprehensive  fare  review  is  currently  underway  to  simplify  the available fare  products 
across the network. Public transport fares are considered to reflect direct user benefits to 
people using public transport. Fare policy considers these benefits along with other factors 
(incentivising  desired  behaviour,  affordability  etc).  The  fare  policy  is  not  currently 
linked to the funding policy. 
Changes  to  fare  products  including  concessions,  the  introduction  of  transfers  and  the 
removal of some operator specific fare products may impact on the overall amount of fare 
revenue,  and  consequentiality  the  amount  that  needs  to  be  raised  through  rates.  The 
cumulative  impact  on  individuals  of  fare  changes  and  rates  funding  changes  should  be 
taken into account as far as possible in this review.. 
PT Funding review scope paper 
Page 6 of 13 
 

A  full  integrated  fares  and  ticketing  system  will  also  be  able  to  provide  accurate  up-to-
date  information  about  boarding/alighting  behaviour.  If  the  current  funding  policy  is 
retained,  once  ticketing  information  is  available  it  may  no  longer  make  sense  to  use 
census journey to work data to inform the congestion component of the rating model.  
3  Objectives 
The review of public transport funding is an input to the wider review of the revenue and 
financing policy, and the overall project objective will be set as part of that process. 
The  working  objective  for  the  public  transport  review  is  to  establish  a  public  transport 
funding policy that is fair, simple and transparent, with a defensible rationale based on the 
distribution of benefits. In doing so, the policy should:  
•  Anticipate new PTOM contracts and allow for future changes in service levels  
•  Consider the possibility of future governance changes (e.g. creation of a CCO and 
boundary changes)  
•  Aim to achieve stability in rating levels for groups of ratepayers (i.e. should not be 
based on factors that are highly variable).  
 
The review must also meet statutory requirements under the Local Government Act 2002.  
4  Scope 
4.1  Scope of the PT Funding Review 
The review of public transport funding is an input to the wider review of the Revenue and 
Financing  Policy.  The  wider  review  will  address  the  general  approach  and  policy 
principles, consistency of approach between activities, and: 
•  links with the Long Term Plan; 
•  the  overall  impact  of  any  allocation  of  liability  for  revenue  on  the  current  and 
future social, economic, environmental and cultural wellbeing of the community; 
•  public consultation.  
 
The Scope of the public transport funding review includes: 
•  The policy rationale for raising rates funding for public transport services 
•  The  economic  benefits  of  public  transport  and  how  they  are  distributed  both 
spatially and to passengers, businesses and community, and other road users 
•  Consideration of options for rates funding, including whether a targeted rate is the 
most appropriate method of rating for public transport, and analysis of how costs 
could be allocated to different areas and classes of ratepayers. 
 
4.2  Fit with existing Revenue and Finance Policy  
Under GWRCs current revenue and financing policy, the following principle would guide 
the review of PT funding:  
PT Funding review scope paper 
Page 7 of 13 
 

Greater Wellington seeks to achieve a rating system that is fair, transparent, and simple, 
provides  flexibility  to  respond  to  future  needs,  reflects  the  principle  of  user  pays,  and 
takes account of ability to pay.  

In addition, GWRC’s approach to rating is to:  
•  Provide GWRC with sufficient income to carry out the range of activities it has 
agreed with the community  
•  Provide a consistent approach to different categories of ratepayer across the region  
•  Ensure that all ratepayers contribute as fairly as possible to fund GWRC services.  
 
The revenue and financing policy also includes wider considerations:  
•  Link  to  community  outcomes:  Each  group  of  activities  contributes  primarily  to 
achieving one or more of these community outcomes (Strong economy, Connected 
community, Resilient community, Healthy environment, Engaged community)  
•  Distribution of benefits: The beneficiaries and type of benefit (individual, group, 
direct, indirect, etc.) of each activity are identified.  
•  Timeframe of benefits: The period in, or over, which the benefits are expected to 
occur  is  identified,  including whether  benefits  from  a  current  activity  will  accrue 
to future generations.  
•  Contributors  to  need  for  activity:  Any  individuals  or  groups  are  identified  who, 
through their action, or inaction, contribute to the need to undertake the activity.  
•  Cost benefit: The costs and benefits, including consequences for transparency and 
accountability, of funding the activity distinctly from other activities.  
•  Equity,  efficiency  and  inter-generational  equity:  The  review  must  consider  the 
overall impact of any allocation of liability for revenue on the current and future 
social, economic, environmental and cultural wellbeing of the community.  
 
The revenue and financing policy is currently being reviewed as part of the development 
of  the  2018-2028  Long  Term  Plan.  This  review  is  being  led  by  Shane  Mercer  (Team 
Leader, Accounting). A project outline is being developed for this work. The revenue and 
financing  policy  review  will  be  signalled  to  council  before  Christmas,  with  the  aim  of 
getting a paper to them in March or April next year. This will be occurring in parallel with 
a high level review of the Financial Strategy, and a review of the Infrastructure policy.  
4.3  Regional land transport plan  
The  Regional  land  transport  plan  (RLTP)  sets  out  the  30  year  vision  for  transport  in 
Wellington.  
To deliver a safe, effective and efficient land transport network that supports the region’s 
economic prosperity in a way that is environmentally and socially sustainable
 
Public  transport  will  provide  an  attractive  option  for  an  increasing  number  of  people, 
particularly  at  peak  times  along  key  commuter  corridors.  Public  transport  trip  times, 
reliability,  cost  and  comfort  will  compete  favourably  with  private  cars  for  a  majority  of 
commuter  trips.  The  public  transport  system  will  effectively  connect  people  with  key 
destinations. All public transport services will have a high level of accessibility, including 
physical access, access to information and simple streamlined ticketing 

A  high  quality  (frequent,  comfortable,  safe,  and  easy  to  use)  and  reliable  peak  period 
public  transport  network  will  provide  an  efficient  method  for  moving  large  numbers  of 
people  at  peak times  (with  associated de-congestion  benefits)  along  corridors  where  the 

PT Funding review scope paper 
Page 8 of 13 
 

transport network is in high demand and capacity is an issue. Continuing to improve off-
peak accessibility will ensure that the public transport network provides a good base level 
of service for community accessibility purposes.’  

The  RLTP  is  the  strategic  document  that  provides  the  rationale  for  why  Greater 
Wellington funds and provides public transport. The current approach to rates funding for 
public transport was developed before the RLTP, and while congestion and accessibility 
are key objectives in both, there is not clear linkage between the RLTP and the targeted 
rate. As part of clarifying the policy rationale for the targeted rate clearer alignment with 
the RLTP will be sought. 
The RLTP will shortly be undergoing a mid-term review, but this will focus primarily on 
activities for inclusion in the National Land Transport Programme and is unlikely to result 
in changes to the vision, objectives and targets.   
4.4  Regional public transport plan 
The Wellington Regional Public Transport Plan 2014 (PT Plan) identifies a dual strategic 
role of the PT network:  
•  To provide peak period congestion relief and access to employment opportunities 
(core routes and some targeted services).  
•  To  provide  community  access  to  services  and  facilities,  particularly  for  people 
who do not have access to a private motor vehicle (local routes and some targeted 
services).  
The  current  service  mix  does  not  link  well  with  the  approach  of  95%  of  benefits  being 
classed as relating to congestion. The review of the policy rationale  will be informed by 
the PT Plan.  
5  Methodology 
The  proposed  methodology  for  the  PT  funding  review  is  set  out  below,  as  thinking 
develops  about  the  approach  for  the  wider  review  of  the  financial  strategy  and  revenue 
and financing policy this may change.  
The main tasks are: 
•  Clarify policy rationale for PT funding  
•  Undertake  an  economic  analysis  of  the  economic  benefits,  and  distribution  of 
benefits    
•  Council and stakeholder engagement on rationale and benefits 
•  Develop long list options 
•  Workshop long list options against policy criteria 
•  Develop short list 
•  Modelling and analysis of short list options 
•  Council and stakeholder engagement on short list options 
 
Tasks  that  form  part  of  the  wider  review  of  the  Revenue  and  Financing  Policy  will 
include: 
•  Proposal for consultation developed  
•  Public consultation 
•  Submissions analysis 
•  Development and adoption of final policy 
PT Funding review scope paper 
Page 9 of 13 
 

 
An  indicative  timeline  and  breakdown  of  tasks  is  attached  as  Appendix  one:  Indicative 
timeline and task breakdown 
6  Resources 
6.1  Budget 
WBS 
$50,000 
Current budget for 2016/17 
562/0110/06 
Legal  
$20,000 
 
Other advice 
$30,000 
possible uses: 
•  economic analysis 
•  communications and marketing  
•  peer review 
 
6.2  People 
Helen Chapman – Policy lead 
Dave Grimmond - Economist  
Shane Mercer – leading the Revenue and Financing policy 
Harriet Shelton/Natasha Hayes – link to RLTP  
Charlotte Vaughan- Finance  
Shirley Long - rating model and financial modelling 
Tass Larsen – peer review/policy  
Andrew Macbeth & David Lewry– link with fares/ticketing work  
Rating expert – may be commissioned as part of revenue and financing policy  
Sam Gain/Linda Going – to commission legal advice if required 
Transport modelling team– Seek input from Nick Sargent on who is best placed to assist 
Communication and Marketing team 
  
PT Funding review scope paper 
Page 10 of 13 
 

















 
 
 
 
Appendix one: Indicative timeline and task breakdown 
 
19-May-17
3-Mar-17
Stakeholder 
16-Dec-16
17-Feb-17
Long list options
engagement
Scope, objectives and
30-Nov-17
Rationale for
31-Mar-17
28-Jun-17
methodology agreed
Approval of policy by council
PT rating clarified
Short list options
Council adopt 
1-Sep-17
developed
consultation proposal
Public consultation complete
17-Feb-17
High level economic
analysis of benefits
1-Jan-17
1-Feb-17
1-Mar-17
1-Apr-17
1-May-17
1-Jun-17
1-Jul-17
1-Aug-17
1-Sep-17
1-Oct-17
1-Nov-17
1-Dec-17
28-Feb-17
1-Jul-17
1-Dec-16
Revenue and Financing
LTP detailed planning 
31-Dec-17
Policy review begins
and budgeting begins
 
 
PT Funding review scope  
PAPER 
Page 11 of 13 
 

 
Task 
Comments 
Deliverable 
Milestone date 
Resources 
Agree  Scope,  objectives   
Paper 
16 December 2016 
PT  Planning,  GM  PT  & 
and methodology 
ELT Wayne to confirm 
Clarify  policy  rationale  Use  information  in  RLTP  and  Paper 
17 February 2017 
PT Planning 
for PT funding  
PT  plan  to  clarify  policy 
rationale and refine as necessary 
Develop  policy  criteria  for 
assessing rating approach  
High 
level 
economic  Undertake initial analysis of key  Paper 
17 February 2017 
Strategic Planning, 
analysis of benefits 
benefits  of  PT,  and  distribution 
of  benefits  spatially  and  to 
different  groups  (e.g.  PT  Users, 
businesses, 
the 
wider 
community) 
Long 
list 
options  Long list of possible approaches  Paper 
3 March 2017 
PT Planning, Finance, 
identified 
to rating for PT developed 
strategic planning, legal 
(to confirm LG (rating) 
Act requirements 
Engage  with  council  and   
Workshop 
March/April 
PT Planning 
stakeholders about policy 
rationale  and  economic 
benefits 
Workshop 
long 
list   
Workshop 
Complete  17  March  PT Planning, Wider PT 
options  against  policy 
2017 
group, Finance, Strategic 
criteria 
Planning, Regional 
Transport Planning 
Develop  short  list  of   
Paper 
17 March 2017 
PT Planning 
rating approaches 
PT Funding review scope paper 
Page 12 of 13 
 

Undertake modelling and   
Model 
outputs,  Complete  19  May  Regional Transport 
analysis  of  short  list 
summary 
paper.  2017 
Planning (Transport 
options 
Possible 
model), Finance. 
development 
of 
Possible peer review. 
economic model 
Engage  with  council  and   
Workshop 
19 May 2017 
PT Planning, Finance,  
stakeholders on short list 
Develop  proposal  for  Through the wider R & F policy  Paper  &  council   TBC 
Finance, PT Planning, 
public consultation 
review.  
resolution 
Communications & 
marketing 
Public consultation 
Through the  wider R & F policy  Consultation 
 TBC 
Finance,  PT  Planning, 
review 
document 
Communications 

marketing 
Submissions analysis 
 
Paper 
 TBC 
PT Planning 
Finalisation of policy 
 
Paper 
 TBC 
PT  Planning,  Finance, 
Strategic Planning, Legal 
Adoption 
of 
rating  Through the wider R & F policy  Council resolution 
 TBC 
PT  Planning,  Finance, 
approach by council 
review 
Democratic services 
Implementation 
 
 
 
Finance 
 
 
PT Funding review scope paper 
Page 13 of 13