Systems Replacement Project 
RFP# 22871: Student Management System 
Evaluation Team Short-Listing 
Recommendations 
Prepared by: 
Project Administrator 
Approved by 
Chair SMS Evaluation Panel 
Prepared for: 
Chair Business Evaluation Team 
Process: 
To record the process and 
Evaluation Team recommendations 
Date: 
4 November 2008 
Version: 
Version 1.4 
Status: 
Final 
 



The approximate value of the LMS tender is 
 

5.  RFP Responses 
Responses to the RFP were due by 4pm 15 September 2008 and were opened by the 
Systems  Replacement Project  Manager in the  presence  of a  Probity Auditor from 
Ernst  and  Young 
 
  on  18  September  2008.  Two  hard  copies  of 
responses  were  received;  one  from  Integrated  Tertiary  Software  and  the  other  from 
, which was not compliant with the required RFP process. 
6.  Management of Non Compliant Response 
After the completion of the inventory of responses and prior to the commencement 
of  the  evaluation  process  a  decision  was  made,  by  the  Chief  Executive,  that  non-
compliant responses to the three RFPs would only be considered if a determination 
was  made  by  the  Evaluation  Teams  that  the  compliant  responses  had  failed  to 
adequately meet the evaluation criteria. 
7.  Action Register 
Date 
Action 
12 August 2008 
RFP released on GETS 
15 September 
Closing date for proposal submissions 
18 September 
Responses opened by Systems Replacement Project Manager, in the 
presence of the Probity Auditor from Ernst and Young. 
18 September 
Inventory of responses prepared 
Week 
Précis of responses prepared and distributed to Evaluation Team 
commencing 22 
Members along with copies of the evaluation sheets, Evaluation 
September 
Guidelines and copies of responses relevant to the SMS Evaluation 
Team. 
23 September to  Members of the SMS Evaluation Team individual y score and rank 
16 October 
responses. 
17 October 
Meeting of SMS Evaluation Team meet to discuss individual scores 
and rankings, to determine aggregate scores and rankings and to 
prepare a shortlist of vendors for presentation/proof of concept 
before the TCS Selection Panel. 
21 October 
Minutes of 17 October meeting circulated amongst members of the 
Evaluation Team. 
30 October 
Second meeting of SMS Evaluation Team. 
 Confidential 
26/05/2009 
Page 3 of 18 

 
30 October 
Revised score sheet correcting the aggregate numerator circulated to 
members of the Project Team for review. 
31 October 
Draft Minutes circulated for comment. 
 
8.  Conflict of Interest 
Conflict  of  Interest  Declarations  were  completed  by  all  members  of  the  SMS 
Functional  Evaluation  Team,  the  Systems  Replacement  Project  Manager  and  the 
Project Administrator  prior to the  Evaluation  Team  meeting  on  17  October  2008. 
Prior to the commencement  of  the  meeting  of  30  October  a  probity check list  was 
provided to all members. The self check probity check list asked members whether 
they  had  been  contacted  by  any  of  the  vendors;  whether  they  had  discussed  the 
responses with anyone other than Team Members and whether as a result of their 
review  of  the  responses  they  had  identified  any  conflicts  of  interest.  Any  positive 
responses to these  questions  were  to  be reported  to the  Chair.  No  declarations 
were made. 
9.  Evaluation Process 
The  evaluation  process  was  conducted  in  accordance  with  ‘Systems  Replacement 
Project  Stage  2  Processes:  Evaluation  Guidelines,  
Systems  Replacement  Project 
Stage  2  Processes:  Procurement  Plan’
  and  the  RFP  rules  relating  to  non  compliant 
responses which are set out on page 15 in Section 4.2.2 of the RFP document. This 
section  states  that  ‘any  non-conforming  proposal,  including,  without  limit,  any  late 
proposal,  may  be  excluded  from  or  accepted  for  consideration  by  TCS  at  its  sole 
discretion
’. 
At  the  evaluation  meeting  of  17  October  the  responses  from 
  and 
Integrated  Tertiary  Solutions  Ltd  (I.T.S.)  were  discussed.  As  some  members  of  the 
Evaluation  Team  had  not  had  the  opportunity  of  reviewing  the  responses  and 
completing  their  individual  assessments  it  was  not  possible  to  complete  the 
assessment process at this meeting. The SMS Evaluation Team did however agree 
that in view of the non compliant response from 
 and the approaching end 
of  year  that  there  was  sufficient  information  in  the  response  from  Integrated  Tertiary 
Solutions  Ltd  to  recommend  to  the  Business  Evaluation  Team  that  an  immediate 
invitation to I.T.S. to present their proposal to the Selection Team be issued. 
It was further agreed that it would be necessary to schedule a further meeting of the 
Functional  Evaluation  Team  before  this  presentation  to  agree  aggregate  scores.  This 
meeting was held on 30 October 2008. 
 Confidential 
26/05/2009 
Page 4 of 18 

Subsequent to the meeting of 17 October probity advice was received from Ernst 
and Young that an assessment process should be completed prior to the issue of the 
invitation to Integrated Tertiary Solutions Ltd to determine whether the response 
was  of sufficient merit to warrant an invitation to present their proposal and proof  of 
concept. 
10. Summary 
Attached to this report are the Minutes of the 17 October meeting, Minutes of the 
30 October meeting, a list of issues/questions to be put to I.T.S. at the presentation, 
a copy of the probity self check list, and a copy of the aggregate score sheets. 
The evaluation process requires that the common and specific criterions be assessed 
against a maximum score, which ranges between 10 and 95. The individual ratings 
for  each  criterion  would  then  be  aggregated  and  summed  to  determine  the 
aggregate  score for  each response.  One  of the ten  score  sheet  responses included  a 
qualitative  assessment  (based  on  an  earlier  draft  of  the  Evaluation  Guidelines) 
against  the  ‘specific’  criterion  rather  than  a  numeric  assessment;  this  response  was 
translated in to a numeric value to enable a uniform methodology to be applied. The 
translation process was consistent with the translation process used for aggregation 
of the similarly assessed scores for the OTLE RFP. 
The individual scores were aggregated and from a possible score of 630 the proposal 
from I.T.S. Ltd was assessed as 416.6  out of a maximum of 630. 
 
 and 
 
  felt  that  they  did  not  have  sufficient  technical  knowledge  to 
evaluate  the  technical  and  general  user  requirements.  As  the  maximum  possible 
score for these two categories is 100 the non-scoring has the effect of distorting the 
overall aggregate score. If the scores for these two members are not included in the 
aggregate assessment the modified score would be 482.9 out of 630. 
Recommendations 
The SMS Functional Evaluation Team recommends to the Business Evaluation Team 
that it 
1.  Agrees  that  Integrated  Tertiary  Systems  Ltd  be  invited  to  present  their 
proposal  to  TCS  selection  staff  and  that  the  issues/further  questions 
identified  by  the  Evaluation  Team  be  put  to the  vendors  by  the  Selection 
Staff; 
2.  Notes the comments set out in the Minutes of the Meetings of 17 and 30 
October 2008; 
3.  Notes that Integrated Tertiary Systems received an aggregate score of 416.6 
or of an adjusted 482.9 out of a possible maximum score of 630; and 
  Confidential 
26/05/2009 
Page 5 of 18 

4. Agrees that a letter be prepared to 
 advising that their response was 
not compliant  and in terms  of the RFP rules  was not considered by the  SMS 
Evaluation Team. 
Name: 
 
 
Position: Chair SMS Evaluation Team 
Date: 2 November 2008 
  Confidential 
26/05/2009 
Page 6 of 18 

Notes from SMS Functional Evaluation Team Meeting 
Date: 17 October 2008 
Time: 10:00 – 11:00 
Venue: Tawa Room, Hobson Street 
Members Present: 
 
 (Chair), 
 

 

 

 

 

 

 

 

 

 

 
 
Apologies: 
 

 
 
Absent: 
 
 
Observers: 
 

 

 
 (Probity Advisor, Ernst and 
Young) 
Notes 
1.  There are two responses to the RFP, one from ITS which is compliant with the 
tender requirements and the other from 
 which is not compliant. The 
objective of the meeting was to decide whether to invite I.T.S. to provide a 
presentation/proof of concept and whether to exclude 

2.  Noted that one member had not read the responses and that other members 
felt that more time was necessary to read and digest the information before 
assigning scores. 
3.  At the request of a Panel Member the term “open source” used in the 
 response was explained. 
4.  Noted that some members felt that it was hard to numerical y rate the 
responses without observing the software in operation. 
5.  Noted that TCS had looked at I.T.S’s product previously (2007) but had not 
proceeded to purchase. Members of the previous Evaluation Panel were not 
advised as to why, leading to concern that the present evaluation might be 
destined for a similar fate. It is believed that the earlier procurement was 
halted over process concerns, rather than any identified short-coming of the 
product itself. 
6.  Noted that the evaluators should focus on system functionality not technical 
aspects of the vendor’s response. 
7.  Noted concerns around the provision of ongoing support from I.T.S. given that 
they are based in South Africa. 
8.  Noted that 
 
 
   
 
 
 has been identified 
by the vendors as a reference site. There is a protocol to be observed, but it 
  Confidential 
26/05/2009 
Page 7 of 18 

should be possible to pose such questions as the last (concerning vendor 
responsiveness) to them. Additionally, the Evaluation Team could expect to be 
offered a demonstration of the 
 system later in the process, assuming it 
proceeds that far. 
9.  Noted that the response from I.T.S. provides no quantification of ‘speed of 
use’. The Project Manager noted that this was not uncommon in responses 
from vendors because of the number of variables. Noted that information on 
operational performance can be gauged from that available at comparable 
reference sites (having a similar size and IT infrastructure). Noted also that 
performance cannot be permitted to erode over time (e.g. under increased 
load). 
10.  Noted the view that I.T.S. does not seem to understand the range of functions 
of TCS, especially with respect to measures of assessment and the transfer of 
data with NZQA. (References to assessment in the proposal are largely framed 
in the paradigms and vocabulary of the tertiary sector.) Some concern whether 
they could make the necessary adaptations. 
11.  Noted the need to ensure that all required functionality is explicitly identified 
and  addressed.  Whereas  some  functions  may  be  forthcoming  from  the  other 
system being considered (the OTLE), this cannot be taken for granted. 
12.  Noted concern about the quality of some data to be migrated to the new 
system and the need to give some thought about the transfer of this data. 
Experience with the implementation of ākona was referenced as an example 
where the conversion process went wel  but the quality of the imported data, 
particular that concerned with rubrics, was poor. Noted that this issue exists 
irrespective of any choice of SMS. 
13.  Noted that I.T.S. may not understand the difference between the types of 
students enrolled with TCS. Noted issues around their proposals for the 
allocation of incoming work which does not mention work coming in 
electronically or the need to refer all work to the responsible teacher. Noted 
that this was an area identified by ITS in 2007 as requiring particular attention. 
14.  Noted concern that technical specifications for end-user software could cause 
difficulties for students and external school staff whose technology may be 
older than that at TCS (e.g. the requirement to support the SSL security 
protocol). Noted that the requirements for external users appear to be 
relatively low (e.g. Internet Explorer v4.0) and that IRG can provide expert 
advice to the panel. 
15.  Noted the need to clarify whether the ITS system can deal with students 
working on multiple levels over multiple years and the need to avoid 
reentering enrollment data each year. 
16.  Noted the need to clarify how easily the ITS system can be adapted to cope 
with future changes. 
  Confidential 
26/05/2009 
Page 8 of 18 

17.  Noted the need to clarify the interface with Navision. 
Where to from here? 
18.  Agreed, in view of the approaching end of year hiatus to invite I.T.S. to present 
their proposal to the Selection Team. 
19.  Agreed that it would be necessary to schedule a further meeting of the 
Functional Evaluation Team before the I.T.S. presentation to agree aggregate 
scores and decide whether or not the 
 proposal should be advanced. 
20.  Agreed that further questions for the next meeting be referred to 
 
 
for consolidation. 
21.  Agreed that the Minutes be circulated. 
  Confidential 
26/05/2009 
Page 9 of 18 


Notes from SMS Functional Evaluation Team Meeting 
Date: 30 October 2008 
Time: 3.00 to 4.00 
Venue: Tawa Room, Hobson Street 
Members Present: 
 
  Chair), 
 
 
 

 

 

 
 , 
 

 
 
Apologies: 
 

 

 
 , 
 
 
Absent: 
 

 

 
 
Observers: 
 

 

 
 (Probity Advisor, Ernst and 
Young) 
Prior to the  commencement  of the  meeting  a  probity check list  was  distributed 
which  asked  attendees  to  disclose  whether  they  had  been  contacted  by  any  of  the 
vendors, whether they had discussed their individual assessments with anyone other 
than a fellow Panel Member, and whether as a result of the review of the responses 
they had become aware of any conflicts of interest. Any positive answers were to be 
referred to the Chair of the Evaluation Team. No declarations were made. 
Copies of the Minutes of the 17 October meeting and a copy of the aggregate score 
sheet was tabled. The score sheet shows an aggregate score of 417 out of a possible 
of 630. It was noted that there was some distortion to the scoring as two members 
of the Evaluation Team had been unable to assess two technical criteria categories 
which had a combined possible maximum score of 100. If these scores were omitted 
the aggregate score increases from 417 to 483 out of a possible 630. 
The Chair summed up the purpose of the meeting, which was to discuss and agree 
the aggregate scoring and to make  a  decision  on  whether ITS  should  be invited to 
present their proposal and demonstrate their product to a TCS Selection Team. 
There was  a general discussion on whether the Evaluation Team felt comfortable 
with the aggregate score as a true reflection of the earlier discussion which focused 
on qualitative factors and whether the Team had confidence in ITS, and if not should 
TCS go back to the market to identify other vendors and other solutions. It was: 
  Noted that there was some variation between individuals scores and that there 
were some issues around the aggregate numerator, especially in those technical 
criteria where some members of the Evaluation Team had entered a zero score 
to reflect that they felt unable to assess that particular criteria. 
  Confidential 
26/05/2009 
Page 10 of 18 










  Agreed to review the aggregate spreadsheet so that the aggregates for each 
category of criteria reflected the number of scores. 
Agreed that TCS should first invite ITS to present their proposal. 
  Agreed  that  the  Chair  will  review  the  information  sent  to  the  SMS  RFP 
respondents  to  identify  any  gaps  and  will  arrange  to  provide  any  necessary 
additional or clarifying information. 
  Noted that while ITS has previously responded to TCS tenders and already has 
some knowledge of the School and its operations, there is still concern to ensure 
that  they  have  sufficient  information  about  TCS  business  processes  and 
methodologies to present properly. 
  Agreed that, in view of the above, that ITS should have access to Evaluation 
Team  Members  and  other  appropriate  TCS  staff  prior  to  the  presentation  in 
order  to  fully  inform  themselves  of  the  TCS  ways  of  working  and  special 
requirements. 
  Agreed that TCS staff prepare a range of scenarios which reflect the wide range 
of business undertaken by the School, that these scenarios be referred to 
 
 by 14 November 2008, for collating. 
  Noted that 
 
 is available to assist Evaluation Team members prepare 
the scenarios. 
  Noted  that  questions,  issues  and  scenarios  will  be  referred  to  ITS  prior  to  the 
presentation,  and  that ITS  be  offered  detailed  briefing  on  matters raised  by the 
Evaluation Team, so that their presentation can be more fully informed. 
  A number of such areas were identified in the meeting, and will be included. 
They included: 
1.  assessments 
2.  allocation of work to teaching staff 
3.  conduct of the project alongside BAU, and how cut-over of the new 
system will be managed 
4.  clarification of the meaning of certain risks identified in the response 
document, particularly that relating to the School’s ‘culture’ 
  Agreed  Noted  that 
 
  and 
 
  will  brief  members  of  the 
Evaluation Team who were unable to attend the meeting on the outcomes and 
the need to prepare scenarios. 
 
Confidential 
26/05/2009 
Page 11 of 18 



  Agreed  that  ITS  be  asked  to  provide  historic  issues  lists  for  one  or  two 
comparable  clients,  (a)  as  they  stood  immediately  upon  going  live  with  the 
application, and (b) following a reasonable period (in the order of a year), to 
help determine the effectiveness of the System, its implementation and whether 
any additional unforeseen capital investment was required to remedy the issues. 
  Noted that the ideal timeline would be to have all issues clarified by ITS and ITS 
having presented  before the  Christmas  break, to enable the commencement of 
work as early as possible in 2009. 
Questions for I.T.S. at Presentation 
1.  Is data (like a teacher in-putting marks and ordering work) transferred in real 
time and permanently stored or is it batch transferred later? Not doing it in real 
time has the potential to lose data when something goes wrong and teachers are 
left not knowing whether something has actually been ordered or not. 
2.  Have any of the ITS systems been hacked into? 
3.  Can names of actual students be found from a ‘sounds like’ search function? 
This is useful when trying to decipher student or supervisor messages from an 
answer phone! 
4.  Can cohorts be automatically updated if that is a chosen parameter? E.g. Can 
a cohort of SC150 Ful  time Maori students be kept as a cohort if those criteria are 
used to create the cohort in the first place or is it only a manual cohort like ākona? 
5.  What are the organisational culture risks referred to in the RFP response and 
how do they see these impacting on the roll out of the new system? 
  Confidential 
26/05/2009 
Page 12 of 18 

Probity Checklist (Self-Check) 
Action 
Yes 
No 
Have you read all of the vendor’s responses to the RFP? 
 
 
(If no, please advise the Chair of the Evaluation Panel) 
Have you read The Evaluation Guidelines? 
 
 
(If no, please advise the Chair of the Evaluation Panel) 
Have you completed your individual assessment of each response? 
 
 
(If no, please advise the Chair of the Evaluation Panel) 
Have any of the vendors contacted you? 
 
 
(If yes provide details below and copy to Chair of Evaluation Panel) 
Have you discussed the responses with anyone other than other 
 
 
Panel Members? 
(If yes provide details below and copy to Chair of Evaluation Panel) 
Have you discussed your individual assessments with anyone other 
 
 
than Panel Members? 
(If yes provide details below and copy to Chair of Evaluation Panel) 
As a result of your review and assessment of the responses are you 
 
 
now aware of any potential conflict of interest? 
If yes provide details below and copy to Chair of Evaluation Panel)
(
 
Notes: 
 
Name: 
Date: 30 October 2008 
 Confidential 
26/05/2009 
Page 13 of 18 

Summary of RFP Responses 
Respondent 
Response 
Aggregate 
Presentation 
Contract Price 
Comments 
(Address & contact details) 
Compliant 
Score 
Recommended 
Integrated Tertiary Software (Pty) Ltd 
Yes 
Between 
 and 
483 
Yes 
The Integrated Tertiary Software (ITS) solution includes 
Head Office: PO Box 25168, 
 Million for the 
functionality  to  support  student,  financial,  human 
Monument Park, 0105, South Africa 
high  level  phases  of  the 
resources, 
payrol  and  library  management  business 
Tel: 00 27 12 4255600 
project  depending  upon 
Web: www its co za 
licensing  model  options. 
processes. 
While modular, the system is claimed to be 
Email: [email address] 
These costs do not 
fully  integrated.  ITS  will  integrate  the  solution  with 
 
include the cost of TCS 
other  TCS  software.  One  of  the  core  strengths  is  the 
backfilling and third 
management  of  assessments,  linking  distributed  staff 
party costs which will 
resources  to  students,  bar  coded  resource  handling  and 
bring the total to 
 or 
more. 
distribution  of  study  material  through  the  warehousing 
function. 
The  delivery  model  that  forms  the  basis  for  this 
proposal  (though  not  necessarily  their  ideal  delivery 
model)  is  based  in  the  system  being  installed  on 
servers  of  TCS  (and  based  at  TCS).  ITS  offers 
three  Licensing  models  and  TCS  can  opt  for  any 
one  of  the models.  Pricing for  all  three models  has 
been  provided.  ITS  can  also  supply  all  the  required 
Oracle  Database  products  to  host  the  system.  A 
hosted  solution  cannot  be  provided  at  this  stage. 
ITS  has  entered  into  discussions  with 
 
 
  regarding  the  hosting  of  the  ITS 
Integrator  system  for TCS.  This  option  will  be  more 
cost effective and that this should, although pricing 
  Confidential 
26/05/2009 
Page 14 of 18 

 
Respondent 
Response 
Aggregate 
Presentation 
Contract Price 
Comments 
(Address & contact details) 
Compliant 
Score 
Recommended 
 
 
 
 
 
has not been provided be seriously considered by 
TCS. 
ITS  has  recently  implemented  a  Student  Management 
Systems  at 
 
 
 
 
 
 
 
 
 
 
 
     
 
 
  ITS  systems  have  also  been  
implemented  with  over  40  tertiary  institutions  in  12 
countries. 
 
 
 
 
No 
   
 

No 
This  proposal  is  not  compliant  with  the  RFP  process, 
 
 
 
 
which 
  have  acknowledged  in  their  response 
 
 
 
 
document. 
 state that they decided to submit a 
non-compliant  response  to  stimulate  discussion. 
  does  not  have  an  out-of  the-box  system  but  is 
interested  in  conducting  an  evaluation  of  open  source 
Student  Management  Systems  and  to  then  develop  a 
strategy  to  extend  one  of  these  or  create  a  new  open 
source  package.  This  evaluation  would  cost  around 
$20,000. 
  Confidential 
26/05/2009 
Page 15 of 18