This is an HTML version of an attachment to the Official Information request 'Watercare - “Letter of Direction" from Waikato Regional Council'.



 
 
 
6 June 2018 
Edward Prince 
Resource Use Group 
Waikato Regional Council 
Private Bag 3038 
Waikato Mail Centre 
Hamilton 3240 
 
 
Dear Edward, 
 
RE: LETTER OF DIRECTION – Waikato WTP Audit 2018 
 
I am writing in response to your Letter of Direction for Waikato Water Treatment Plant (WTP
dated 2 May 2018, covering the period 1 July 2015 to 30 June 2017. Please be advised that 
Watercare  Services  Limited  (Watercare)  takes  its  statutory  responsibilities  very  seriously. 
This  includes  compliance  with  our  Resource  Consents.  While  we  agree  that  a  partial 
compliance status must be addressed, Watercare believes that further discussion is needed 
to clarify, confirm and address the points raised by the Waikato Regional Council (WRC). 
Watercare  has  implemented  a  number  of  improvements  and  actions  to  address  the  partial 
compliance issues with resource consents granted by the WRC. Watercare’s response to the 
issues raised and further information requested by the WRC, are detailed in attached in Tables 
1, 2, 3 and 4. 
Watercare is committed to reducing its impact on the environment and improving the quality 
of water in the Waikato River. Watercare has made concerted efforts to improve operational 
processes  to  ensure  that  controls  are  appropriate  and  implemented,  to  minimise 
environmental impact. Significant work has been undertaken to review operational procedures 
and ensure that these procedures are adhered to at all times.  
An upgrade of the chemical facilities at the Waikato WTP is in the early design phases and 
targets the implementation of additional engineering controls to further reduce risks associated 
with our chemical storage and handling systems. A key requirement of these upgrades is to 
ensure ongoing compliance with our statutory obligations and the mitigation/minimisation of 
potential adverse environmental impacts. 
Watercare would like to propose that a meeting is arranged to clarify points raised by the WRC 
and discuss actions taken/planned. We would also appreciate the opportunity to discuss the 
water abstraction conditions, in particular, the net take and the 7-day rolling average flow at 
Rangiriri.  Nolwenn  Lagadec  will  make  contact  with  you  to  discuss  potential  meeting 
times/locations. 
Please contact me directly if you require any further information or clarification. 
Yours faithfully, 
 
 
Priyan Perera 
Operations Manager – Water Supply  
Watercare Services Limited  

1/7 



 
 
 
Table 1:    Response to the actions listed in the Site compliance report and Letter of Direction 
 
Resource consent 
Condition 
Consent condition 
Action Required 
Status 
Number 
AUTH120246.01.02 

The consent holder shall be responsible for all 
Please ensure that all corrective 
A number of corrective actions have been 
contracted operations relating to the exercise of this  actions identified in the ICAM 
completed. Full details are described in tables 2, 3 
resource consent, and shall ensure contractors are  Investigation Report #9628760 are 
and 4. 
made aware of the conditions of this resource 
implemented to reduce the likelihood 
consent and ensure compliance with those 
of a re-occurrence of this type of 
conditions. 
incident. 
AUTH120246.01.02 

Any discharge to the Waikato River shall comply 
Investigate and take action to improve  Review of the training material has been carried 
with the following limits: 
the quality of the discharged process 
out and all operators retrained. Signage has also 
i) 
pH of the discharge shall be 
backwash to within compliant levels 
been reviewed and improved. Since this time 
between 6 and 9 pH units; 
there have been no further instances of the 
ii) 
total residual chlorine of the 
concentration of soluble aluminium in the 
discharge of less than 0.5 grams per 
discharge exceeded the consented limit.  
cubic metre; 
 
iii) 
suspended solids of the discharge 
The low pH result obtained was due to a failure to 
of less than 50 grams per cubic 
follow maintenance activity procedure. This issue 
metre 
has been addressed. 
iv) 
Total soluble aluminium of the 
 
discharge of less than 5.0 grams per 
cubic metre  
AUTH137722.01.01 

The total combined instantaneous take rate 
Please investigate and take action to 
Consent 137722 was granted in February 2017 
pursuant to this resource consent and resource 
reduce the abstraction rate to within 
providing for a maximum instantaneous flow of 
consent 960089 must not exceed 2,450 litres per 
compliant limits. 
2450 l/s. The maximum flows abstracted from the 
second. 
Waikato River have not exceeded this level.  
 
Watercare believes that this warrants further 
discussion with WRC staff to confirm consent and 
current compliance status. 
AUTH137722.01.01 

Water must not be taken pursuant to this resource  Please explain the reason for the 
Consent 137722 was granted in February 2017 
consent when the Waikato River 7-day rolling 
spikes in take volume during restricted  after the dates of the events raised by the WRC.  
average flow at Rangiriri (Waikato Regional Council  water take conditions around 7 
The graph provided by WRC displays flow rate 
site number 1131.117, map reference NZTM 
December 2015, 21 March 2016, 15 
over a 15 minute period in m3/day as opposed to 
1788389 E 5855059 N), as determined by the 
June 2016 and 26 July 2016 
daily net take. This has been discussed with WRC 
Waikato Regional Council, is less than 328.3 cubic 
and a calculation added to convert flow rate to 
metres per second. 
volume taken over a 15 minute period.  A request 
2/7 



 
 
 
Resource consent 
Condition 
Consent condition 
Action Required 
Status 
Number 
(No # CSR0001254) has been raised with 
Watercare’s ECS team to create a new tag that 
records the net take volume over a 15 minute 
period. This will make the reporting of this 
condition clearer and avoid any confusion in the 
future. Figures 1 displays the daily net take for the 
compliance reporting period and shows that no 
water was taken above the 175,000 m3 limit. 
 
Watercare believes that this warrants further 
discussion with WRC staff to confirm consent and 
current compliance status. 
AUTH960089.01.03 

The maximum rate of abstraction: 
Take action to ensure that discharges  Condition 3 refers to abstraction.  
1) 
Rate of abstraction shall not exceed 2000  remain within compliant limits. 
The maximum abstraction flow rate was exceeded 
litres per second; and  
twice during the reporting period. These 
Net take volume – being the volume taken pursuant 
exceedences were associated with abstraction 
to this resource consent less the volume 
system capacity confirmation testing and should 
discharged into the Waikato River pursuant to 
not reoccur. 
resource consents 120246, 960101 and 960091 
 
shall not exceed 150,000 cubic metres during any 
The WTP was compliant with the total daily 
24 hour period. 
abstraction limit during each occurrence. 
 
 
 
 
 
 
 
 
 
 
 
3/7 



 
 
 
Table 2:    Status update on corrective actions taken following HFA overflow 
 
Recommended Actions following ICAM 
Hierarchy 
investigation 
Responsibility 
Status 
Timeframe 
of Control 
 
High High Alarm to be activated for HFA tanks at Watercare.     
Engineering 
Watercare 
Complete 
 
Complete  
Faulty Tank 1 telemetry gauge to be replaced 
Engineering 
Watercare 
(all chemical tanks display have been 
 
replaced)  
Check materials of construction for compatibility with chemicals in 
Engineering 
Watercare 
Complete 
 
bunds/tanks 
Out of Service vs out of operation - Check HH alarm operation for both 
states (tbc on 20th July 2016.   Ensure that Cold state default start of 
Engineering 
Watercare 
Complete 
 
DNS has HH alarm activated 
Additional risks have been 
In progress- Identified risks in 
identified, with the proposed 
Review Risk Assessment for CoDe functionality with the aim to make 
automating delivery volumes. 
Admin 
IXOM 
system automation. Warrants 
CoDe safe fill functionality mandatory for all fill calculations. 
Label in the field by delivery point 
further risk assessment prior roll-
displays "Safe Fill Level 10,000L=95%" 
out.  
Supplier procedures to be reviewed and measures put in place to 
ensure the following is in place A) Version control    B) Lay out is 
Admin 
IXOM 
Complete 
 
optimised for driver use.    Actions from review to be entered in 
Velocity for implementation 
Period testing to be put in place for high level alarms, bund alarms and 
 
Admin 
Watercare 
Complete 
warning lights 
Ensure procedure updates are provided to Watercare and Transport 
Complete  
Admin 
IXOM 
 
company – an acknowledgment/sign off is required. 
Ensure sign off is documented 
Procedure updated. 
Pre delivery physical sign off of delivery quantity for each tank to be 
Watercare Operators reminded delivery 
implemented at all Watercare sites.   Operator and Driver agree and 
Admin 
Watercare 
supervision is to be direct, in the field, 
 
document tank level before delivery and planned delivery volume in 
as far as practicable. To be included in 
writing.  Watercare procedure to be update to include this step. 
IXOM drivers induction. 
Update Supplier procedure to require check and sign off of initial tank 
level and planned fill level for each tank. In addition, what constitutes 
Admin 
IXOM 
Complete 
 
supervision of the delivery needs be clearly defined. 
 
4/7 



 
 
 
 
Table 3:    Following actions are based on internal discussions, and review of the incident with Waikato Regional Council. 
Additional recommended actions  
Status 
Timeframe 
Notify the Council immediately if an incident occurs, within 5-7 days in writing. This is currently not specified in the 
Acknowledged by Service Delivery and 
 
existing consent, however this is expected practice. New discharge consent will be amended to be more specific. 
notified to Consents team 
Repair equipment in the bund corroded by HFA. 
Complete 
 
Investigate design improvements. Look into minimising single points of failure and ensuring chemicals cannot gravitate 
Complete 
 
to the river. Define scope of work for chemical plant upgrade included in 175MLD upgrade project. 
Update spill procedure (2009). 
Complete. Spill procedure training material 
Ensure consistent with Corporate Incident Management Plan as well as with Health and Safety Emergency Response 
 
also updated. 
Management Plan toolkit. 
Complete.  
Eliminate complacency around bund alarms. As rain enters the bunds, the alarms frequently trigger. 
Incorporated in new chemical area concept 
 
design. 
Modify practices. Wrong practice has been adopted of placing chemical tank in "Out of service" mode, as "Standby" is 
Complete. To be regularly audited. 
 
not an available option. 
Additional recommended actions  
Status 
Timeframe 
Improve communication on faults.  Different operators were aware of different faults and thought some had been fixed. 
Complete 
 
Ensure maintenance takes place in a timely manner.  
Ongoing. To be regularly audited. 
 
 
 
 
 
5/7 



 
 
 
Table 4:    The following actions were identified during the ICAM investigation as potential improvements requiring further investigation: 
Potential improvements to be 
Hierarchy of 
Responsibility / Assigned to  Status 
Timeframe 
further investigated 
Control 
Covered during preliminary HAZOP on 
Consider the installation of a new alarm on the 
Engineering 
Watercare 
15/12/2016. Found not to be an appropriate 
 
overflow pipe.  
mitigation. 
Where tank locations are not clearly 
 
Revised and considered not necessary. 
identified/add Aerial maps of customer 
Admin 
 
IXOM 
Driver is to follow SOP. 
facilities showing the location. 
Watercare to consider including site orientation 
Next driver induction 
Admin 
Watercare 
Induction material reviewed. 
for drivers in Induction program 
booked in May 2018. 
Establish feasibility of separate sensors for 
Covered during preliminary HAZOP on 
Engineering 
Watercare 
 
alarm and telemetry 
15/12/2016.  
Establish feasibility of installing a drop pipes in 
Covered during preliminary HAZOP on 
Engineering 
Watercare 
 
HFA tanks 
15/12/2016.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
6/7 



 
 
 
Waikato WTP - Daily Net Take
200000
180000
160000
140000
120000
100000
80000
60000
40000
20000
0
01-Jul-15 00:00:00
17-Jan-16 00:00:00
04-Aug-16 00:00:00
20-Feb-17 00:00:00
Daily Net Take
150 MLD
175 MLD
 
Figure 1: Waikato WTP - daily net take July 2015 - June 2017 
7/7