Old Mangere Bridge - Strategy Review
1
Introduction
WSP Opus were approached by the Auckland Motorway Association (AMA) to provide a “Senior
Engineer’s Review” on the asset condition and suitability of the current strategy for maintaining and
managing Old Mangere Bridge (OMB) in Auckland. Following a start-up meeting on the 29th March
with Jennifer Hart from the AMA; we were tasked with providing a high-level review to determine
whether the current “Holding Strategy” for the bridge is appropriate considering the demolition and
reconstruction has been pushed back due to East West Link project review and light rail. This report
seeks to review the currently available information and the current risk-management strategy and
to suggest possible solutions, with safety of users and maintainers paramount.
From our understanding, the proposed and imminent reconstruction of OMB was part of the wider
East-West connection project which is no longer a funding priority for the Government. The current
holding strategy for OMB was based on the knowledge that the bridge would be decommissioned in
a very short space of time (1-2 years). This strategy was essentially a “managed decline” until the
replacement could be procured, the risks of which, although significant, were mitigated partly by the
short time-scale and temporary measures put in place such as fencing off the weaker/most
deteriorated parts of the structure, regular inspections and monitoring.
2 Background
OMB was constructed circa 1914 and consists of 17 simply supported reinforced concrete spans
varying in length between 11.43 & 15.24m and measuring 243m in total. Until 1985, the bridge
formed the main road link between the city of Auckland and the airport; whereupon it was replaced
by the current motorway bridge and downgraded to a pedestrian and cycleway bridge due to its
deteriorating condition. OMB has arguably reached the end of its useful life due to its current
condition. Despite its location in an exposed marine environment and being constructed from
comparatively understrength materials (for contemporary standards), OMB has managed to survive
for over 100 years. OMB is still in service as a cycle / pedestrian bridge and benefits from monthly
special inspections and a cloud-point 3D survey to check for any sudden change in its condition. In
2016, a live load assessment concluded that large areas of the bridge could not safely support a
reduced crowd loading event of 3 kPa. This reduced loading is based on engineering judgement at
the time and is typically reserved for structures which are deemed to be lightly loaded. However, the
Bridge Manual specifies a crowd loading of 5kPa in clause 3.4.14. There have a been a number of
crowd loading events on OMB in the past 8 years and this remains a significant risk.
There is an alternative cycling and walking route across the Mangere Inlet via the motorway bridge.
On the west side of the westernmost span, is a dedicated, cantilevered access route with a raised
footway and textured cycleway.
It is understood that the AMA has commenced separate work assessing the adequacy of this facility
in the event that the OMB needs to be closed.
2
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
3 Observations from a site visit on 19th April 2018
On 19th April 2018, Engineers from WSP Opus inspected the bridge by boat at low tide with particular
attention paid to the soffit and visible substructure. A walkover of the structure and the most likely
cycle path diversion was also undertaken. Observations from the site visit are noted as follows:
Impact damage on Column IS60 / Pier 15. Evident damage from a collision by a water-borne vehicle
has caused significant damage to the edge girder haunches on the Western side of the bridge. The
concrete haunches are contorted and cracked with exposed rebar visible. Repairs include a localised
concrete encasing in the transition zone to the tapered section. At first glance, it is hard to see how
this helps the damaged section. The concrete thickening would appear to want to attract load to this
region of the structure in addition to the dead load from the additional concrete. Meanwhile the load
transfer to column IS60 is compromised due to the distortion of the haunches. The area immediately
above this is closed off to the public so any dead load failure in this region is unlikely to endanger
life.
Photo 1 – Pier 15 (Column IS60) impact damage and repairs
Pier 7, Column IS28: On the Span 8 side there is severe loss of section on the outer girder in the shear
zone haunch. The exposed bottom steel is buckled and the stirrups have corroded away leaving a
rough concrete surface with approximately 300mm loss of section. The full width of Span 8 is open
to the public which could pose a risk should crowd loading ensue.
3
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
Photo 2 – Pier 7 (Column IS28) loss of concrete and exposed, buckled reinforcing bars
Spans 3, 4, 5 & 6 exhibit sufficient loss of concrete to reveal two layers of steel reinforcing bars on
the soffit of some of the internal girders. Stirrups are also corroded through in the zones of maximum
shear.
Photo 3 – Beam soffit – Span 5
4
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
Photo 4 – Beam soffits – Span 3
A concrete overslab has been added to the structure presumably to strengthen the deck. It is assumed
that the new slab has been tied in to the existing deck slab to allow some composite action which will
be beneficial to the strength of the bridge despite adding considerable additional self-weight.
NB 1: During the inspection, a motorised scooter was observed crossing the bridge despite the
signage.
Photo 5 – Bridge signage
NB 2: During our inspection, fishing was observed taking place away from the bridge at the
southwestern end of the bridge at low tide.
5
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
4 Review of strategy
Since the closure of the bridge to vehicular traffic, Asset Managers for OMB have spent a great deal
of time and expense assessing the condition and attempting to prolong the life of the bridge. The
condition has consistently been assessed as poor and there is common concern expressed amongst
Inspectors, Assessors and Asset Engineers that the structure is potentially unsafe. This situation has
been tolerated to some extent due to the imminent replacement of the structure and with the
implementation of short term mitigations and strengthening works. Now that situation has changed
it is important to review the current status and condition of the bridge with a renewed vigour and an
eye firmly on the safe operation of a key bridge asset over the medium to long term.
The existing holding strategy is based on an ongoing restricted operation of the bridge in conjunction
with real time monitoring using an array of 100 tiltmeters running along both sides of the deck. The
restricted operation has been achieved through fencing off some of the worst affected areas of the
structure to reduce live loading effects and additional signage. In addition, dive inspections have
concluded that the substructure below the water line is in fair condition.
The risk strategy matrix below in Figure 1 shows as red, the items where action needs to be taken to
ensure the safety of the public. The orange areas also require action within a year. This matrix was
used to assess the risk to OMB in 2016 including mitigations and residual risk scores as shown in
Figure 2. This risk assessment has been updated with additional scoring based on the bridge not
being replaced for at least 10 years.
Figure 1 – Risk Strategy Matrix
6
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
Risk Assessment carried out in 2016
(2016) Over 1-2 year period
(2018) 1-10 year period
Risk Score
Severity
Likelihood
Risk
Severity Likelihood
Risk
Number
Risk
Specific Details
Mitigation Measures
(Before
Status & Further Mitigation
(Residual)
(Residual)
Score
(10+ years) (10+ years)
Score
Mitigation)
Following the numberical assessment it has shown
Collapse of the structure due to
Install fencing that restricts pedestrian
Further restriction / new
1
a number of elements do not have adequate factors
20
5
3
15
5
4
20
loading
access to the substandard elements
fencing
of safety to support crowd loading
Collapse of the structure due to
The quarterly inspections have noted cracking and
Install steel collars and bracing to
Real-time monitoring &
2
20
5
3
15
5
4
20
condition
deterioration of structural members
hold/strengthening substandard members
continuing inspections
The central carriageway section of the bridge still
Monitor the structure through quarterly
Collapse of the structure in remaining remains open including the full central 4 spans as inspection and real time monitoring which
Real-time monitoring &
3
15
1
2
2
5
3
15
open section
they have a factor of safety greater than 1 and
will capture any significant deterioration of
continuing inspections
better condition factors
the structure
Install signs warning people not to enter
Large sections of concrete have the potential to fall the worst spans. Warning signs paced in the
No change
4
Falling debris on boat users
off the structure and hit boat users underneath
spans less likely to have falling debris
12
4
2
8
4
2
8
The piles under the water have not been inspected
Inspection has taken place and
Hidden detail such as under water of which could be hiding more significate conditional
condition is fair
5
behind delaminated concrete
deterioration.
Carry out underwater inspection
20
5
2
10
5
1
5
Continue with quarterly inspection. Once
the real time monitoring is set up this can
Load testing to calbrate
Assumed section loss and section
An assumption had to be made on the loss of
monitor ongoing deterioration and
1
2
2
5
2
10
monitoring
sizes used in the assessment are not
section and some of the section sizes due to the
progress failure to allow enough time to
6
conservative
extensive deterioration
evacuated the structure
15
By restriction access to the worst areas, and
Risk of structural failure can be
a strigent monitoring regime the risks can
managed but not eliminated.
If the structure were to fail and collapse there
Reputional risk to the Agency
be managed. If the structres RTM levels get
15
5
2
10
Risks from tides, flood,
5
4
20
would be reputional risk to the agency
triggers or further significant deterioration
deterioration and overload are
the structre will have to be closed
significant over 10 year period.
7
If the structure deteriorates further that
affects the safe usage of the bridge it will
Structure will almost certainly
have to be closed down. If this were to
If the structure has to be closed before the new
need to be closed within 10
Reputional risk to the Agency
occur the underslung walkway under the
15
5
3
15
3
5
15
structure can be constructed
years. The alternative walkway
mainline bridge could be utiliised but
remains sub-optimal
would need to be upgraded at a cost and
8
will not accommodate people fishing.
Effective public relations and
9
Community Relations
Backlash form the community
Keep the community infomed
8
4
2
8
media campaign
2
2
4
Figure 2 – Risk Strategy Matrix for Old Mangere Bridge 2016 & 2018
7
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
One of the key mitigations for the current holding strategy is an implemented system of effective
real-time monitoring. Unfortunately, this hasn’t been functioning recently due to some installation
difficulties, although a small amount of data was recorded at first. The monitoring is proposed to be
reinstalled in the near future with equipment and expertise provided by WSP Opus Research Labs
in Petone. This monitoring will allow for an alarm system to alert the On-call Engineer. Assuming
the monitoring can be used for advising of a potential collapse scenario, the key issues to be solved
and agreed upon are:
Calibrating the alarm triggers to differentiate between an in-service dynamic loading event and
an overload event or displacement due to structural failure.
Rationalising length of time between an event occurring and alerting users of the bridge to
evacuate if required.
Strengthening work has been carried out near the span supports to reduce the likelihood of a sudden
catastrophic failure. Steel clamps and braces were installed as holding measures in the event of a
dead load failure. These mitigations are designed to be a last resort and should not be relied upon
during a crowd overload event. To reduce this likelihood of the risk, the deck area could be better
protected and further restricted to pedestrians / crowds.
Three-dimensional surveying is currently being carried out on an ad-hoc basis and the results are
compared against a baseline for changes in the deck level. This cloud point data is a very useful tool
for monitoring alignment changes over time. We believe that surveying either by total station or 3D
scanning should be continued at 3-monthly intervals whilst the bridge remains open.
The bridge beams have been externally post-tensioned which is providing a much-needed boost to
flexural capacity especially considering that the section loss is so severe in many areas. This is fine
whilst the post-tensioning remains functional. A small risk remains that a failure may occur at an
anchoring point due to the condition of the concrete, leading to an abrupt change in load path which
could initiate a structural failure.
Regular inspections by boat are ongoing to look specifically at existing problem areas such as the
bridge strike area and the worst corrosion. Whilst these provide important qualitative photographic
and journaled reference information, they may not necessarily advise of an imminent failure which
could arise from a hidden critical element. Also, there is the risk that the inspector will become
desensitised to the inherent risk of a bridge in this condition.
The worst parts of the structure have been fenced off to reduce the live loading demand, particularly
on the edge girders. This fencing, although effective in normal daily situations is however not
impregnable. Should an emergency occur on the bridge it would be quite easy for people to access
the weak and dangerous parts of the structure. In addition, the unlocked gate could provide very easy
access for crowds during an incident. Ideally the fencing and gates should be reviewed and upgraded
as soon as possible. Consideration should also be given to fencing off more of the structure (see
recommendations).
Closure of the bridge has been considered previously but not implemented due to pressure from
stakeholders who use it for leisure and commuting by walking and cycling. Work to assess the
alternative route is the subject of a separate report.
8
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
Fishing could continue at the southern end of the bridge as was observed during our site visit. Closure
would clearly be an advantage by eliminating the risk to the public but the disadvantage around
stakeholder relations remains. From our experience, this option would be highly likely in a similarly
high-profile area in the UK where risk to the public would be the paramount consideration and the
public would expect such a response. This also aligns with the new focus areas within the NZ
Transport Agency Statement of Intent, in particular the effort to “Keep People Safe”.
A partial demolition where the riskier sections of the bridge could be dismantled has been considered
but ruled out due to the unknown consequences of residual stresses in the structure. This option
would have been beneficial if only to remove dead load and to prevent accidental loading of the
weakened parts of the structure. This is particularly so due to the retrofit post tensioning and it would
not be advisable to remove any of the structure until decommissioning begins.
5 Recommendations
There are clearly risks to the public with Old Mangere Bridge remaining open which can either
mitigated through the measures outlined below or eliminated through a permanent bridge closure.
Having been to site and having reviewed all available documentation on the current condition of Old
Mangere Bridge including the latest assessment reports; it is clear to us that the structure is not
currently fit for purpose and is continuing to deteriorate and weaken as more of the reinforcement
becomes exposed. It is hard to justify keeping the bridge open to the public for much longer without
urgent strengthening work taking place. Indeed, from a UK perspective, it is considered likely that a
well-used bridge in this condition would be closed immediately to eliminate the potential risk to the
public. In addition, the assumptions made in the 2016 assessment may have underestimated the
degree of corrosion in the reinforcement and the exact combined effect of post tensioning with
exposed longitudinal reinforcement, failed stirrups and spalling concrete.
Assuming that OMB will not be replaced for the next 10 years, our recommendations for a revised
strategy are based around an updated and phased strategy. This strategy seeks to put in place a
structured approach to managing the risk and protecting the users and stakeholders of the bridge.
This strategy should be reviewed on a regular basis to ensure that it remains appropriate and is
outlined as follows:
1. We would recommend initially load testing the bridge with operational monitoring in
place. The phased approach would depend on the outcome of this. Assuming a structural
failure does not occur, the monitoring information can be used to set trigger and alert
levels for future events. We would suggest keeping the bridge open as it is for the first 12
months with monitoring and upgrades to the fencing including providing an adequate
locking system. Fencing should also be reconfigured to restrict access to the edges of Span
8 due to the condition of the concrete edge girder at Pier 7.
2. After one year and assuming no further significant deterioration has been noted, we
would recommend narrowing the useable portion of the bridge to the minimum footpath
and cycleway standards along the full span. This could be implemented fully or in sections
dependent on condition. This will reduce the live load demand from recreational users.
Fishing can still be carried out from the approaches to the bridge as was evident during
our inspection (even at low tide). This strategy could potentially remain in place until year
4 with functioning real-time monitoring, scheduled 3D surveying and regular inspections.
9
| 15 November 2018
WSP Opus
Old Mangere Bridge - Strategy Review
3. Proceed with upgrade works to the alternative cycling and walking route along the
motorway bridge so that it is available in the event of the closure of OMB.
4. After 4 years, it is possible that OMB will need to be closed if it has not been already.
Although it is difficult to predict the situation this far in the future, we anticipate that
the effect of storms and high tides combined with continued deterioration will have
increased the risk profile of the structure substantially beyond the current situation.
5. Cyclists and pedestrians to be rerouted over the motorway bridge until a replacement
structure for OMB is procured and built.
Looking at the first point in more detail, we recommend repairing the faults to the monitoring system
and instigating the real time monitoring as soon as possible. In advance of testing, using the media
the public should be kept informed of this critical safety work to keep the bridge open. Once the
monitoring equipment has been tested, the bridge should be temporarily closed to the public and a
load test should be conducted using water tanks that can be easily filled to achieve the desired load
case and easily drained with minimal risk of harm. The critical spans should firstly be loaded to 3kPa
to check for effects and then to 5kPa whilst monitoring continues and with safe observations by boat.
The outcomes of the testing can be used to calibrate the monitoring system for when the bridge
reopens to the public. If any structural damage should occur during testing, then the outcome of the
test will be that the bridge is no longer safe for use and should be closed immediately and an
alternative route should be devised as per point 3 above.
We believe this phased strategy will help to keep the bridge open in the short term and transition
through to permanent closure using evidence-based engineering judgement. Keeping the public
informed through a multimedia approach and the strategy of introducing safety measures by
degrees, will provide a useful means of managing the expectations of stakeholders throughout until
the inevitable closure of OMB. This approach will also help to put across the message to the public
that everything is being done to try to keep the bridge open, but that the safety of members of the
public is ultimately the principal consideration.
10
| 15 November 2018
WSP Opus