This is an HTML version of an attachment to the Official Information request 'Request for ATs CCFAS2 Project Information'.



 
 
 
 
 
Auckland Transport 
 
 

 
 
 

Auckland light rail peer review - 
 
Part B: options and assessment  
 
 

(Draft 2) 
 
 
 
 
 
 

21 July 2015 
 
N207/Rep/1553 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Ian Wallis Associates Ltd 
[email address] 

link to page 3 link to page 4 link to page 11 Ian Wal is Associates Ltd 
Contents 
1.  INTRODUCTION ............................................................................................................................... 3 
2.  OPTIONS AND ASSESSMENT - PEER REVIEW .................................................................................. 4 
ANNEX A: Study Objectives ................................................................................................................... 11 
 
 
 
IWA/N207/Rep/1553 
21 July 2015 


Ian Wal is Associates Ltd 
1.  INTRODUCTION 
This paper has been prepared for Auckland Transport by consultants Ian Wallis Associates (IWA), as 
part of a peer review of AT’s proposals for a light rail network for Auckland. 
The paper is one of three papers prepared by IWA for this peer review. 
This paper (B) is concerned with options and their assessment.  Specifically it addresses the following 
aspect of the peer review task: 
 “…the reliability of the options analysis results against the achievement of the 
study objectives, including whether there are further viable options that could be 
considered and appropriateness of the MCA for the purpose used – to identify the 
broad strategic option for further development.” 
For conciseness, our review of this aspect is provided in tabular form, within the following sections: 
•  A:  Project Purpose and Objectives 
•  B:  Problem Definition 
•  C:  Range of Options Considered 
•  D:  Selection of ‘Short’ List Options 
•  E:  Framework for Option Assessment 
•  F:  Assessment Objectives and Criteria 
•  G:  Assessment Scoring Methodology 
•  H:  Assessment Scoring Application 
•  I:  Approach to Assessment Weightings (and Sensitivity Tests) 
•  J:  Summary of Option Assessment Findings. 
The other two papers in this peer review set cover the fol owing aspects of the AT proposals: 
Paper A:  Robustness of the deficiency analysis.  This paper focuses on demand and capacity analyses 
regarding the maximum number of buses that can practically and reliably be accommodated on main 
routes in the isthmus and city centre. 
Paper C: Cost estimates.  This paper reviews the estimates of LRT infrastructure costs, vehicle capital 
costs and operating costs for the LRT proposals relative to the costs for the bus-based base case. 
 
 
IWA/N207/Rep/1553 
21 July 2015 


link to page 4 link to page 4 Ian Wal is Associates Ltd 
2.  OPTIONS AND ASSESSMENT - PEER REVIEW 
Summary of AT Work Undertaken 
Peer Review Comments 
A.  Project Purpose and Objectives 
 
We were advised by ATthat the purpose for this  • We note the ‘two-pronged’ nature of this purpose 
(CCFAS2) project has been defined as fol ows: 
statement, ie focusing on: (i) providing an effective 
Provide an effective transport solution for those 
transport solution for inner Auckland that supports 
parts of inner Auckland and the City Centre that 
growth requirements; and (i ) maintaining the 
cannot be served by the heavy rail network, with 
amenity of the city centre streets, in particular in the 
CRL; that supports growth requirements in a way 
light of the prospect of an increased  number of 
that maintains or enhances the quality and capacity 
buses on these  streets to cater for future public 
of the City Centre streets; and thereby resolve the 
transport demand. 
outstanding issues identified in CCFAS including the  • Taken at face value, these objectives/sub-objectives 
impact of a high number of buses on urban 
are consistent  with the ‘two-pronged’ (‘balanced’) 
amenity.” 
statement of project purpose: objective 1 focuses on 
economic development; objectives 2 and 3 on 
AT also advised that six objectives had been set for 
transport system accessibility and efficiency 
the project, in summary as fol ows (full  in/around the city centre; objective 4 on 
objectives/sub-objectives set out in Annex A): 
sustainability and environmental impacts of the 
1.  Significantly contribute to lifting and shaping 
transport system; objective 5 on city ‘liveability’, 
Auckland’s economic growth 
including restraining transport costs and congestion 
2.  Improve the efficiency and resilience of the 
levels; and objective 6 on  implementability and 
transport network of inner Auckland and the 
‘stageability’. 
City Centre. 
• However, we note that, in interpreting these 
3.  Improved transport access into and around 
objectives, the further advice from AT indicates a 
the City Centre to address current problems 
somewhat different balance between the objectives 
and for a rapidly growing Auckland. 
– focusing primarily on city ‘liveability’ and amenity 
4.  Provide a sustainable transport solution that 
of the city central area. 
minimises environmental impacts. 
• This direction wil  clearly have implications for the 
5.  Contribute positively to a liveable, vibrant and 
option assessment framework and criteria (as 
safe city. 
discussed in a later section). 
6.  Optimise the potential to implement a feasible 
solution. 
In relation to the stated project purpose and 
objectives, we were further advised by AT2  as 
fol ows: 
You wil  see the emphasis given (in the project 
purpose)  to urban amenity.  In this context I can 
confirm that achievement of objectives 4 and 5 is 
given particular weighty in accordance with the 
guidance of the AT executive.  Objective 1 should 
also be understood to have an amenity dimension – 
we understand that enhanced economic activity in 
the City Centre is not seen as likely to occur unless 
the aesthetical qualities improve.” 
 
B.  Problem Definition 
 
The  definition of the problem that this project is  •  We note that the ‘problem definition’ as outlined 
intended to address is essential y summarised in the 
in the Jacobs’ Deficiency Analysis paper is entirely 
based on a ‘do minimum’ transport scenario  for 
year 2046: this Do Min case includes CRL and the 
                                                           
1  Email John Al ard to Ian Wallis, 20 July 2015. 
2  Ibid. 
IWA/N207/Rep/1553 
21 July 2015 


link to page 5 link to page 5 link to page 5 Ian Wal is Associates Ltd 
CCFAS2 ‘Deficiency Analysis’ paper prepared by the 
new bus network, but otherwise minimal changes 
AT Project Team3
to the existing PT system.  Its estimation of future 
That  paper focuses on the transport issues and 
bus service levels is based on continuing to use 
problems expected to occur in the southern 
‘standard’ size buses (c. 50 passenger capacity) in 
corridor and the central area over the period to 
the corridors of interest, despite the use of much 
2046.  Its analyses are based primarily on transport 
larger capacity vehicles elsewhere in AKL.  Thus it 
model ing using the APT model. Its findings on these 
paints a ‘worst case’ picture of the number of 
issues and problems are summarised as fol ows: 
buses in future –  which, prima facie, could be 
“In summary, the deficiency analysis for CCFAS2 has 
substantial y  improved upon by use  of  a smal er 
highlighted that capacity on public transport bus 
number of larger (eg double-decker) buses.  Its 
services is likely to be a real issue, particularly as 
results need to be interpreted in that light. 
they near the City Centre and then within the City 
Centre itself.  The problem of delivering sufficient 
capacity is already evident by 2026 on some services 
and corridors and by 2046, nearly twice the number 
of buses currently operating would be required to 
meet the demand for travel by bus.  The central 
isthmus is the main area where issues are evident as 
services entering the City Centre at Symonds Street 
struggle to cope with demand and Symonds Street 
itself wil  struggle to cope with the required bus 
volumes beyond the very early 2020s.” 
In regard to issues relating to the amenity of the City 
Centre area as affected by transport, a separate 
report was prepared, focusing on the ‘amenity 
capacity’  of central area streets in terms of bus 
volumes.4 
Arguably, a more balanced summary of the 
problems is provided in a recent AT document5
•  Increasing congestion in the City Centre is 
reducing urban amenity and liveability. 
•  Constrained access to the City Centre wil  
limit economic growth and reduce the 
region’s productivity. 
•  Inefficient use of city centre street space 
wil  restrict accessibility, mobility and the 
city’s economic competiveness. 
C.  Range of Options Considered 
 
The main outcome of the long list review workshop  •  We have  reviewed the paper summarising the 
[10 Oct 14, AT34] was the selection of five suburban 
findings from the long list workshop and have no 
routes for further assessment (Dominion, Manukau, 
issues with selection of these five suburban 
Sandringham, Mt Eden, Remuera Roads). A variety 
routes/corridors and options for their extension 
of city centre streets/ corridors  were also  in/through the CBD. We note that these options are 
nominated as providing potential routes for  described in various places as 'Long list options', 
operation of the suburban services in/through the 
although arguably at that stage they were no more 
CBD. 
than specifications of potential corridors/roads to 
be used  rather than future network or service 
options. 
 
                                                           
3 CCFAS2 – Deficiency Analysis (ref ZB01598), Jacobs for AT, 9 January 2015. 
4 Built Environment and Amenity Technical Paper (draft), Jasmax for AT, November 2014. [IWA 65] 
5 LRT Technical Advisor RoI (ref 303-15-791-PS), AT, July 2015. 
IWA/N207/Rep/1553 
21 July 2015 


Ian Wal is Associates Ltd 
D.  Selection of ‘Short’ List Options 
 
Fol owing the long list review work (as above), AT  • While a multitude of 'short' list options could be 
prepared a Short List Summary Paper [13 Feb 15, AT 
defined, consistent with the outcomes from the long 
61.1]. This paper “developed a short list of 10 
list review workshop above  [AT 34], we consider 
network options that would enable a range of 
that the 10 short list options defined are likely to 
combinations of modes to be evaluated”. Of these 
have covered the range of more promising options 
10 options, five are focused on LRT (involving 
(recognising that the options might be further 
different combinations of the five suburban  refined in the subsequent stages of the study).  
corridors identified earlier), two involve  bus on-
• However, we note that we have not identified any 
street (using double-decker buses), one  involves 
written material that explains and justifies the 
BRT (predominantly on-street), one involves  a 
selection of these 10 options from the wide range of 
combination of heavy rail and bus, and one a 
possibilities: this short list assessment is a significant 
combination of heavy rail and LRT. The five LRT 
step in the overal  study and should be appropriately 
options al  involve different combinations of the five 
documented. We also note that while five LRT-based 
suburban corridors identified earlier, and al  would 
options were included in the short list, only one of 
run into the CBD via Queen and/or Symonds 
these options was 'mirrored' by a corresponding 
Streets. 
BRT-based option - whereas there appears to be no 
reason why the other four LRT options were not 
similarly 'mirrored'. 
• We further note that, in the specification/discussion 
of the options, the aspect of bus capacity gets only 
brief mention.  Our understanding is that: the Do 
Min option is based on ‘standard’ size buses; options 
1, 2 and 3 involve double-decker buses; other 
options (including the BRT option 7) most likely 
involve standard size buses (although this is 
unclear).  Given the demand forecasts for 2046, we 
would have expected that the main bus routes in al  
options would be operated by double-decker buses. 
E.  Framework for Option Assessment 
 
A multi-criteria analysis (MCA) approach was taken  • We support in principle the use of the multi-criteria 
to the comparative assessment (evaluation) of the 
analysis (MCA) framework for the study’s 
10 ‘short list’ options.  This involved [refer AT27, 23 
comparative assessment of options  against the 
Dec 14]: 
range of objectives. However, we have considerable 
•  Specification of objectives (8). 
concerns relating to some of the details of 
•  Specification of criteria relating to each  application of this framework,  as noted in the 
objective (over 50 criteria in total, within the 
fol owing sections. 
8 objectives). 
• We note that the MCA application in this case is 
•  For each criterion, specification of an  more ambitious and complex than most such 
appropriate measure and the data source for 
applications, in terms of having: 
this measure. 
o  A relatively large number of objectives (8) 
•  Specification and then application of a relative 
o  A relatively large number of criteria (> 50), 
rating scale (2, 1, 0, -1,  -2) for rating the 
many of which significantly overlap (hence may 
performance of each option against each 
result in double-counting) and some of which 
criterion. 
contradict others. 
•  Selection and application of weightings for 
o  A relatively large number of options (10) to be 
each objective and the criterion within the 
compared 
objectives, and hence derivation of the  • We have been unable to identify any statement as 
weighted sum score for each option under 
to the role of the MCA, potentially as part of a wider 
each set of weights. 
assessment of the most promising options – which 
•  Drawing conclusions from these results on the 
would be expected to include a business case 
relative performance of the options, and the 
analysis,  including an economic appraisal.  By 
sensitivity of the performance results to a 
default,  the impression is given that the MCA 
range of weighting assumptions. 
assessment comprises the  total  assessment of 
IWA/N207/Rep/1553 
21 July 2015 


link to page 7 Ian Wal is Associates Ltd 
options, rather than only a component of a wider 
assessment process. 
F.  Assessment Objectives and Criteria 
 
The assessment (evaluation) framework has eight  • The eight objectives used in the assessment differ 
‘objectives’. Six of these relate to ‘benefits’ -  of 
from the six study objectives defined earlier (refer 
which three relate directly to transport (city centre 
Annex A).  One reason is that an additional objective 
access, city centre mobility, regional movement), 
(cost) has been included for assessment purposes, 
two to environment and one to economic  but was not included in the original objectives.  . 
performance.  The seventh objective relates to  • Apart from that, there is only a broad 
implementation and the eighth to cost aspects. 
correspondence (no more) between the other seven 
 
assessment objectives and the six project objectives. 
 
Further, there is no clear correspondence between 
 
the assessment criteria and  the project sub-
objectives. We cannot see any good reason for these 
 
differences, particularly at the top (objective) level, 
 
and have not identified any documentation to 
 
explain the reasons. 
 
• Further, we note that the eight assessment 
 
‘objectives’ are not couched in ‘objective terms’, but 
 
are merely topic heading in the spreadsheet 
 
analyses. 
• We note that, of the eight  objectives, seven are 
 
essential y measuring ‘benefits’ (to transport users, 
 
the community, the environment, etc) while only 
 
one is measuring ‘costs’ (to the public sector). 
Within the eight objectives, over 50 assessment  • The > 50 criteria is a relatively large number for such 
criteria are specified.  For each objective, a 
assessments, and tends to give rise to issues of 
corresponding measure is defined along with the 
double (or triple) counting and interpretation. For 
data source to be used in measuring performance. 
example, criteria 1.02, 1.04 and 1.07 appear in part 
to double-count similar effects, and in part to point 
in contradictory directions. We have not attempted 
to review/critique every individual criterion and its 
associated measures. 
G.  Assessment Scoring Methodology 
 
The assessment scoring is set out in two main  • The ‘Do Minimum’ should be defined somewhere 
spreadsheets [AT27, Evaluation framework v O9, 
(we have not sighted any definition).  We are unclear 
sheets ‘Assessment’ and ‘Scored version’].  It 
whether  the Do Min is a realistic option over the 
involved ranking (rating?) performance against 
longer-term (eg 2046): if not, we suggest it should 
each criterion on a relative scale, comparing every 
be replaced,  as the assessment base case, by a 
option against the Do Minimum case. The rating 
minimum cost variant that would be realistic 
scale used was +2, +1, 0, -1, -2, using only integer 
(maybe this is option 1?)
scores and where the Do Minimum was scored 0  • We have seen no statement as to the ‘assessment 
(zero) in al  cases. 
year’ adopted but assume it is 2046, representing a 
medium/long term year for which model estimates 
are available and by which the full scheme is 
assumed to have been implemented. 
• The 5-point assessment scale is relatively crude for 
a project of this type: a 7-point scale may be worth 
consideration. 
• Where quantitative assessments are possible/ 
available against criteria, it would be helpful to 
include these in the assessment. Then, as required, 
they can be also expressed in terms of points 
                                                           
6  AT advises that option 1 is being used as the ‘base case’ for economic assessment purposes in work currently in progress. 
IWA/N207/Rep/1553 
21 July 2015 


Ian Wal is Associates Ltd 
(usual y assuming a linear relationship between the 
quantified estimates and the corresponding point 
scores). This wil  give more confidence that relative 
performance figures (e.g. out of the transport 
model) are being reflected consistently in the rating 
scores. 
• The above point is considered especial y important 
in the case of the cost objective. It is not readily 
apparent to people examining the results that the 
total cost range between the options is very 
substantial, probably in the order of $2.0 bil ion (PV 
terms) over the economic life of the project. This 
significant amount (of similar order to the total costs 
of CRL)  tends to get lost in the way that the 
assessment results are presented. 
H.  Assessment Scoring Application 
 
Each option was assessed against each criterion on  • We have not attempted to review the awarded 
the 5-point scale (relative to Do Min = 0).  The Excel 
scores in any detail.  However, we do have some 
worksheet [AT27, Assessment] sets out the scores 
reservations from the limited checks made (noting 
awarded with a brief comment as to the basis for 
that no two parties are ever likely to agree 
them. 
completely on the relative merits of options against 
al  criteria). 
• To review the assessment findings on the relative 
merits of BRT v LRT, we specifical y compared option 
5 (ful  LRT network) and option 7 (ful  BRT network). 
A view quite often expressed is that anything an LRT 
solution can achieve, an equivalent BRT option can 
also achieve, but at significantly lower total costs 
(capital and operating, in PV terms). This review 
found that, according to the assessment results, 
option 7 performs substantial y worse than option 5 
against most objectives (1, 2, 4, 6 and 8).    In 
‘unweighted’ terms (al  objectives weighted equal y, 
and al  criteria within any objective weighted 
equal y) option 7 performs no better than option 1 
(double decker buses, on-street operation).  We find 
these relative results somewhat unlikely, which 
raises more general concerns about the assessment 
scoring and weightings applied (refer fol owing 
section). 
• We also note that, under the base assessment (all 
objectives given equal weighting), the 10 options fal  
into two groups: options 1, 2, 3 and 7, with weighted 
sum scores in the range -0.6 to 0.7; and the other six 
options, with weighted sum scores considerably 
higher, in the range 1.7 to 2.8.  We observe that al  
six high-scoring options are focused on LRT mode; 
whereas the four lower-scoring options are focused 
on bus mode (with one including a limited heavy rail 
extension, Mt Roskil  Spur).  The conclusion that may 
well be taken from this scoring is that, for the area 
under study, LRT-based PT is very considerably 
superior to bus-based PT services on the assumption 
that al  objectives are equal y weighted.  This result 
is somewhat surprising in our view. 
IWA/N207/Rep/1553 
21 July 2015 


Ian Wal is Associates Ltd 
I.  Approach to Assessment  Weightings  (and 
 
Sensitivity Tests) 
Our understanding is that the ‘base’ assessment (A)  • The results we have inspected [AT27, v9: Scored 
results give equal weight to each objective (ie a one-
version] appear to be identical for equal and 
point score difference between options is given the 
unequal criteria weightings (ie assessment (B) is 
same weight across all objectives); and also equal 
identical to (A), (D) identical to (C).   This suggests 
weight to al  criteria within any objective. 
that the unequal criteria weightings have not been 
Sensitivity tests have also been undertaken on the 
applied in practice. 
weighting of objectives and criteria, adopting: 
• The main changes in objective weightings for (C) and 
 
(B) Equal objective weighting, unequal criterion 
(D) compare with (A) and (B) are that two objectives 
weighting 
(Environment, Cost) are down-weighted (to 5% 
 
(C) Unequal objective weighting, equal criterion 
each), while three objectives (city centre access, city 
weighting 
centre mobility, economic performance) are up-
weighted (to 20% each).  However, we note that this 
 
(D) Unequal objective weighting, unequal  re-weighting of objectives has resulted in very little 
criterion weighting. 
change in the relative rankings of the ten options. 
• It was noted in the first section of this table that AT’s 
intention was to give particular weight to the project 
objective 4 (‘a sustainable transport solution that 
minimises environmental impacts’) and objective 5 
(‘significantly contribute to lifting and shaping 
Auckland’s economic growth’).  In our 
interpretation, project objective 4 best corresponds 
to assessment objective ‘Environment’ and 
objective 5 to ‘Built Environment’.  But, in the 
sensitivity testing for objective weightings, 
‘Environment’  has been sharply down-weighted 
(from 12.5% to 5.0%)  and ‘Built environment’ has 
been marginal y down-weighted (from 12.5% to 
10.0%).  Our conclusion is that the current sensitivity 
tests do not reflect the relative importance of the 
various project objectives as advised by AT 
management. 
• We have a substantial concern about the relative 
weightings adopted between 'benefit' objectives 
and criteria and 'cost' objectives and criteria (refer 
item F above). The current base objective 
weightings (A) result in a weighting for 'benefit' 
objectives against cost objectives of 87.5%: 12.5%; 
while the reweighted objectives result in a ratio of 
95%: 5%. 
• We note that, for a project of this nature, 
conventional economic evaluation typical y shows a 
broad comparability between the magnitude of 
benefits and the magnitude of costs (i.e. a BCR ratio 
in the order of 1.0). This would suggest that, from a 
socio-economic perspective, the appropriate 
balance between benefit objectives (in total) and 
cost objectives would be expected to be in the order 
of 50%: 50%. It would be of interest to examine the 
results of sensitivity tests on these lines. 
• Indicatively, we note that the cost range between 
the 10 options is likely to be in the order of $2 bil ion 
(capital and operating, PV terms,  over the project 
life). This cost range would equate to a difference of 
two rating points (-2 compared with 0) on the cost 
IWA/N207/Rep/1553 
21 July 2015 


Ian Wal is Associates Ltd 
objective, i.e. around $1.0 bil ion per one rating 
point difference. We suggest that some thought be 
given to the 'value' (in wil ingness-to-pay terms) that 
society might reasonably give to a score difference 
of one rating point on each of the seven 'benefit' 
objectives. If this value is considered to be 
significantly lower than $1 bil ion, then this benefit 
objective should, logical y, be given lower weighting 
than the cost objective; or vice versa if the value is 
considered to be higher. It would also be worth 
considering a similar question for al  the 'benefit' 
objectives combined: the logic of weighting al  
objectives equal y, as has been done at present, is 
that a one point higher rating across al  of the 
benefit categories would be worth in the order of 
seven times the $1.0 bil ion per point cost advantage 
on the cost objective. 
• We suggest that the treatment of the cost objective 
in the MCA evaluation needs re-consideration, with 
a choice between: 
(i)  re-assessing the weighting to be given to the cost 
objective, in the light of the above comments; or 
(i ) not attempting to include the cost objective in 
the MCA, but addressing the costs v benefits 
trade-off separately (eg in the economic case 
assessment).   
The present approach is a very unsatisfactory solution. 
J.  Summary of Option Assessment Findings 
 
The MCA findings indicate (based on the objectives,  • In regard to point (i), while ‘real-world’ experience 
criteria and scoring system used): 
indicates some advantages for LRT-based solutions 
(i)   a  strong superiority for al   the LRT-based 
over bus-based solutions in similar situations, it 
options over the bus-based options. They also 
would general y suggest a closer balance between 
indicate a similarly strong superiority for the 
the two types of solutions than is indicated by the 
LRT-based option 5 over the BRT-based option 
MCA results. 
7:  apart from the mode/technology involved,  • In regard to point (i ), we find that the sensitivity 
these two options are very similar in terms of 
tests undertaken are not consistent with the advice 
route, network, services, etc. 
provided by AT management on the relative 
(i ) The ordering of options is very insensitive to the 
priorities of the various objectives. 
different criterion weightings tested. 
• In regard to point (i i), we find that the attempt to 
(i i) The ordering of options is very insensitive to 
include the cost objective in a framework otherwise 
major changes in their relative costs. 
including only ‘benefit’ objectives has not been 
 
successful or helpful.  We suggest that further 
consideration needs to be given to this, with one 
option being to exclude costs from the MCA 
assessment and to address cost v benefit trade-offs 
elsewhere (eg in the economic case). 
 
 
 
IWA/N207/Rep/1553 
21 July 2015 
10 



Ian Wal is Associates Ltd 
ANNEX A: Study Objectives 
(Source: Light Rail for Auckland: Potential Peer Review – Terms of Reference). 
 
 
 
 
 
IWA/N207/Rep/1553 
21 July 2015 
11 

Document Outline