Report 
For 
Peer Review of Draft Capex 
Estimate 
David Creegan 
Director - Infrastructure 
 
Turner & Townsend 
Level 14 
55 Clarence Street 
Sydney 
NSW 2000 
 
 
t: +61 (0)2 8245 0000 
e: [email address] 
w: turnerandtownsend.com 
 
 
 
 
 
 
 
 
City Centre Future Access Study 2 
Auckland Transport – Commercial in Confidence 
23 December 2014 
 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Contents 

Executive Summary 


Brief and methodology 

2.1 
Scope 

2.2 
Basis of Review 

2.3 
Turner & Townsend capability 

2.4 
Benchmarking 

2.5 
Exclusions 

2.6 
Information Received 


Cost estimate summaries 

3.1 
Option 4 

3.2 
Option 9a 
12 

Cost reviews 
16 
4.1 
Overall cost 
16 
4.2 
Direct construction costs 
17 
4.3 
Indirect construction costs 
20 
4.4 
Risk & contingency 
24 
Appendix 1 
 
Appendix 2 
 
Appendix 3 
 
Appendix 4 
 
 
 
 
 
Rev 
Originator 
Approved 
Date 

David Creegan 
Darren Munton 
05-Dec-14 

Leigh Doran 
David Creegan 
23-Dec-14 
 
 
 
 
© Turner & Townsend Infrastructure. All rights reserved December 14. This document is expressly provided 
to  and  solely  for  the  use  of  Auckland  Transport  and  must  not  be  quoted  from,  referred  to,  used  by  or 
distributed to any other party without the prior consent of Turner & Townsend Infrastructure who accept 
no liability of whatsoever nature for any use by any other party. 
F:\SYD\INFRASTRUCTURE\SY20981 - AUCKLAND TRANSPORT LR PEER REVIEW\2000 COSTPLAN\2200 COST PLANS\2210 PRELIMINARY PEER REVIEW\ISSUED 
141223\AT CCFAS2 PEER REVIEW R1 141223.DOCX 
 
mak i ng   the  di ff er en c e  


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 

Executive Summary 
During the previous three months Auckland Transport together with their 
commissioned consultants, have prepared various options with outline designs and 
draft cost estimates for Auckland’s City Centre Future Access Study 2 (CCFAS2), 
including a new light rail system (Option 4) and a combination of a modified heavy 
rail network and a new light rail system (Option 9a). 
Turner & Townsend have been commissioned by Auckland Transport to undertake an 
independent peer review of the draft estimate of capital expenditure. 
Turner & Townsend have undertaken the independent review which indicates that, 
including the light rail vehicles, we consider the Option 4 should be in the order of 
$3,673m versus the draft estimate of $1,945m and Option 9a $1,865m versus the 
draft estimate of $1,240m. 
From information received, Turner & Townsend have identified Option 4 to consist of 
33.64km of light rail running, 54 Light Rail Vehicles, 35 substations and 43 light rail 
stops. 
Turner & Townsend have similarly identified Option 9a to have a light rail alignment 
length of 13.24km, a heavy rail alignment length of 3.86km, 22 Light Rail Vehicles, 9 
heavy rail Electric Multiple Units, 15 substations, 2 heavy rail stations and 17 light 
rail stops.  
At Appendix 1 and 2 there are indicative cost summaries that capture the findings of 
this report and presents an alternative overall cost that Turner & Townsend consider 
to be a more likely scenario than the current draft estimate. 
Direct construction costs 
Direct construction costs include the costs a main contractor would incur for labour, 
plant / equipment, materials and other sub-contract costs. 
The direct construction costs within the draft estimate have been estimated at 
$655m for Option 4 and $405m for Option 9a, compared to this review of $1,127m 
for and $569m respectively. 
The primary drivers for the overall differential in both options are existing utilities 
modifications, road and footpath works, traction power and the allowances for 
various rail systems. 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Indirect construction costs 
Indirect construction costs include the costs a main contractor would incur in 
preparing final designs, providing project insurances and security bonds and 
preliminaries which include the core site management team, site supervision, 
temporary site facilities of compounds, lay-down areas and offices, consumables, 
temporary utilities, traffic management and the like. The other indirect construction 
costs are main contractor’s corporate overhead and profit margin. 
The indirect cost elements also show significant divergence between the draft 
estimate and this review. The principle reason for the difference is that Turner & 
Townsend have assessed the allowances for the above items at a higher percentage 
given the type and quantity of works, the requirements for the proposed light rail 
‘wire free’ technology and our experience of previous and current light rail systems 
and significant infrastructure programmes internationally. 
The indirect construction costs within the draft estimate have been estimated at 
$212m for Option 4 and $131m for Option 9a. This compares with this review of 
$669m and $281m respectively. 
Project / client costs 
Project / client costs include the costs that the owner will incur in the development, 
delivery and commissioning of the project including the teams responsible for 
development management, project management, commercial and schedule 
management, business and local community communications, stakeholder 
management, environment management, the Project Board, the Environmental 
Impact Statement and legal costs. Other costs include external engagements that 
cover planning, engineering and architectural design, programme, project and cost 
management, health and safety and other independent and specialist advisers. 
This review suggests that the client costs are increased from the draft estimate 
assumption of $80m for Option 4 and $49m for Option 9a to $195m and $98m 
respectively which still places the project towards the lower end of expected ranges 
of light rail, heavy rail and infrastructure projects globally. 
Risk and contingency 
The design and engineering evidence that we have reviewed indicates that the 
CCFAS2 is at an early stage of development and therefore the scope of work must be 
considered very flexible and hence subject to a great deal of uncertainty and risk. 
The draft estimate contains a P50 risk allowance of 20%. 
This review suggests that a more appropriate risk and contingency allowance in the 
order of 30% should be considered for adoption at this stage with the expectation 
that this will reduce as the definition of scope increases and agreements are reached 
with government agencies, utility providers, contractors and advisors. 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Conclusion 
The design and construction of new light rail systems in New Zealand and Australia 
requires a high percentage of imported skills, expertise and equipment. Turner & 
Townsend’s research and experience of planning for light rail systems in Australia, 
including wire free technology in Sydney, indicates that the draft estimate for 
Auckland is overly optimistic and set at too low a level. It is recommended that the 
current draft estimate is reviewed in more detail and supported by more evidence 
based data. 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 

Brief and methodology 
2.1 
Scope 
Review the capital cost estimates and undertake benchmarking including indirect 
construction cost elements, client costs and risk and contingency and comment on 
their appropriateness. 
Review the appropriateness of the rates and allowances made in the estimate with 
commentary on elements that appear to be outside of expected ranges. A detailed 
re-measure or verification of the quantities not part of the scope of services. 
2.2 
Basis of Review 
The basis of the review is of the estimates supplied by Auckland Transport, in 
conjunction with supplied route images and Turner & Townsend industry benchmarks 
from works of a similar nature. 
2.3 
Turner & Townsend capability 
Turner & Townsend have provided cost planning and risk management services in 
support of numerous Business Cases for major infrastructure projects in Australia 
including the North West Rail Link (Sydney), Sydney CBD (Central Business District) 
and South East Light Rail and Wynyard Walk pedestrian link (Sydney). Other 
business cases that we have supported include Brisbane’s Cross River Rail and the 
Gold Coast Light Rail project. 
We are on the Australian Government’s Department of Infrastructure and Regional 
Development’s panel of Infrastructure Advisory Services, providing base cost 
estimate and contingency review services. 
Through our global network of 87 offices we have access to light rail, heavy rail and 
other infrastructure project data that is based on robust information that can be 
trusted. We are currently working closely with rail owners / operators in Australia, 
the UK, Europe, Middle East and Africa and have most recently brought our 
experience of Edinburgh Trams to Sydney in support of the AUD$1,600m investment 
in an extended light rail system. 
This experience gives us in-depth knowledge of the issues involved with setting 
appropriate budgets for significant infrastructure investments funded by government 
or a combination of public and private entities. 
 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
2.4 
Benchmarking 
Using our experience and knowledge of light rail and other infrastructure projects we 
have benchmarked the allowances for overhead and profit, risk and contingency and 
project leadership and management costs against other comparable projects whilst 
appreciating that there will be specific project issues and other impacts of delivering 
a new light rail system through Auckland’s city centre. 
Other similar light rail systems that we have detailed access to include, but not 
limited to, Sydney Light Rail (Australia), Newcastle (Australia), Perth light rail 
(Australia), Edinburgh Trams (UK), Nottingham Express (UK), Stagecoach Supertram 
(Sheffield, UK) and Dublin Luas (Ireland). Our rolling stock database includes over 
65 orders covering 17 countries and spanning over 10 years. 
The methodology for reviewing the capital costs for the key elements of the project 
followed the principles below; 
Property acquisition - A review of the estimated property acquisition costs is not 
included as part of the scope of this review so we have retained the values as given 
in the draft estimate. 
Existing utilities – An overall rate per kilometre was calculated and compared to 
other similar projects in addition to an assessment of what the utilities cost 
represented as a percentage of the light rail infrastructure and systems total cost. It 
is recognised that each project has specific issues and there are examples where 
expenditure on this scope of work has been minimal. 
Trackform – Specific consideration given to the light rail steel track required and 
the cost implications of curved track requirements. An overall rate per metre for the 
trackform was derived from other similar projects and compared to the draft 
estimate. 
Rail alignment (structures) -A rate per metre for elevated structures was 
compared to other similar structures. 
Stops – Allowances per stop were based on similar stops on the Sydney light rail 
project and other light rail projects globally. 
Precincts – The road works and footpath works between stops were considered 
overall and assessed against the typical percentage these works usually form as part 
of the overall scope. 
Bulk and traction power - Unit rates for supply and installation were applied to the 
elemental quantities of substations, overhead wiring, small power and lighting from 
our internal cost database.  
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Rail systems – Benchmarked rates from our internal cost database for supply and 
installation of communications and security systems, tram and traffic control 
signalling, combined services route, passenger information systems and ticketing 
systems were applied to the alignment length. 
Depot and stabling – Rates per facility/building, including fitout, and an operations 
control centre were compared to other similar projects on a total cost and a cost per 
light rail vehicle basis. 
Contractor’s indirect costs - The specific project requirement for preliminaries 
including the core management and site based teams, temporary construction 
facilities such as construction sites, office buildings and lay down areas, insurances, 
traffic management and main contractor’s design costs were analysed as 
percentages of total direct construction cost and benchmarked against comparable 
projects. 
Project / owner’s costs - Requirements for external appointments and internal 
Department of Transport costs calculated as a percentage of total construction costs 
and benchmarked against comparable projects. 
Rolling stock – The unit rate was compared to our database of light rail vehicle 
orders allowing for the addition of wire free technology which is assumed to include 
some form of on-board energy storage system. 
Risk and contingency - Based on the information available upon which the 
estimate has been prepared, together with the assumptions made, direct costs, 
indirect costs, engineering, procurement and management, the adequacy of the total 
risk allowance as a percentage of the total cost was assessed and benchmarked 
against comparable projects. 
2.5 
Exclusions 
The following items are excluded from this review; 
 
Escalation – all costs are assumed to be 4th Quarter 2014 and there is no 
provision for escalation over the period from 1st Quarter 2015 to 
commencement of revenue services. 
 
Land and property – this cost category includes land acquisitions, relocations, 
alterations / refurbishments / demolitions and legal and other fees. The costs 
contained in the draft estimate  
 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
2.6 
Information Received 
The following reference documents were received from Auckland Transport and were 
used to form the basis of our review: 
 
CCFAS2 Draft Estimate estimate-2.12.2014 (WT Partnership) 
 
Operational costing of LRT/bus options 4, 6, 8 and 9, 21 November 2014 
(MRCagney) 
 
Route images – Option 4 (pdf file) and Option 9A (jpg file) 
 
CCFAS2 LRT Staging Plan 21 Nov D (URS, 42127353-SK017-D.dwg, 10/11/14) 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 

Cost estimate summaries 
3.1 
Option 4 
The latest draft estimate at a P50 confidence level for the CCFAS2 project is 
$1,614m plus light rail vehicles of $331m, giving a total of $1,945m as set out 
below; 
 
All costs $m 
 
Total $ 
Total $m per 
km 
 

Land & Property 
  
282.3 
8.4 

Investigation & Reporting 
  
29.9 
0.9 

Developed Design & D&C Monitoring 
  
49.8 
1.5 

Design & Construct contract 
  
  
0.0 
4.01 
Track (34 km alignment) 
  
352.1 
10.5 
4.02 
Power (inc. 35 Nr substations) 
  
76.2 
2.3 
4.03 
Systems 
  
20.1 
0.6 
4.04 
Statutory Undertakers  Equipment 
  
63.7 
1.9 
4.05 
Highway Costs 
  
13.9 
0.4 
4.06 
Stops (43 Nr) 
 
54.9 
1.6 
4.07 
Support Facilities 
  
74.4 
2.2 
4.08 
Design 
  
26.2 
0.8 
4.09   Programme & Project Management 
  
185.9 
5.5 
 
Subtotal 
  
867.5 
25.8 
4.10 
Off site overhead and Profit 
 
130.1 
3.9 
 
Total D&C 
  
997.6 
29.7 

Contingency P50 
19% 
254 
7.6 

Subtotal @4Q14 prices 
  
1,613.6 
48.0 

Rolling Stock 
54 Nr 
331.0 
9.8 

Total Costs @4Q14 Prices 
  
1,944.7 
57.8 
Table 1- Draft estimate as presented 
 
 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
In order to compare the CCFAS2 project with other similar light rail systems we have 
analysed the draft estimate and re-ordered some of the line items to reach a 
standard elemental format as set out below; 
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
 
Direct construction costs 
 
 
 

Track (34 km alignment) 
53.8% 
352.1 
10.5 

Power (inc. 35 Nr substations) 
11.6% 
76.2 
2.3 

Systems 
3.1% 
20.1 
0.6 

Utilities 
9.7% 
63.7 
1.9 

Roadworks 
2.1% 
13.9 
0.4 

Stops (43 Nr) 
8.4% 
54.9 
1.6 

Depot & Stabling Facility 
11.4% 
74.4 
2.2 

Direct construction costs 
100.0% 
655.4 
19.5 

Preliminaries 
23.9% 
156.4 
4.6 
10 
Traffic management 
4.5% 
29.5 
0.9 
12 
Contractor’s design 
4.0% 
26.2 
0.8 
13  Indirect construction costs 
 
212.1 
6.3 
14  Total construction costs 
 
867.5 
25.8 
15 
Contractor’s OH&P 
15.0% 
130.1 
3.9 
16  Total contractor’s costs 
 
997.6 
29.7 
15 
Rolling stock (LRVs) 
54 Nr 
331.02 
9.8 
16  Subtotal 
 
1,328.6 
39.5 
 
Planning & Development 
2.3% 
29.9 
0.9 
 
Client Design 
2.3% 
29.9 
0.9 
 
Client Costs 
1.5% 
20.0 
0.6 
 
Owners management costs total 
6.1% 
79.8 
2.4 
 
Subtotal 
 
1,408.4 
41.9 
 
Property acquisitions 
 
282.3 
8.4 
 
Subtotal 
 
1,690.7 
50.3 
Risk and contingency 
 
254.0 
7.6 
 
19% excluding LRVs 
15% including LRVs 
33  Subtotal 
 
1,944.7 
57.8 
Table 2 – Draft estimate in standardised cost breakdown structure 
 
  mak i ng   the  di ff er en c e  



Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
In reviewing the data presented we have found several anomalies in formulas used 
to arrive at the current estimate based on the information provided. We have 
assessed that the accurate representation of the provided information is as follows. 
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
 
Direct construction costs 
 
 
 

Track (34 km alignment) 
53.8% 
352.1 
10.5 

Power (inc. 35 Nr substations) 
11.6% 
76.2 
2.3 

Systems 
3.0% 
19.8 
0.6 

Utilities 
9.7% 
63.7 
1.9 

Roadworks 
2.1% 
13.9 
0.4 

Stops (43 Nr) 
8.4% 
54.9 
1.6 

Depot & Stabling Facility 
11.4% 
74.4 
2.2 

Direct construction costs 
100.0% 
655.0 
19.5 

Preliminaries 
23.9% 
156.4 
4.6 
10 
Traffic management 
4.5% 
29.5 
0.9 
12 
Contractor’s design 
4.0% 
26.2 
0.8 
13  Indirect construction costs 
 
212.1 
6.3 
14  Total construction costs 
 
867.1 
25.8 
15 
Contractor’s OH&P 
15.0% 
130.1 
3.9 
16  Total contractor’s costs 
 
997.2 
29.6 
15 
Rolling stock 
54 Nr 
331.02 
9.8 
16  Subtotal 
 
1,328.2 
39.5 
 
Planning & Development 
2.3% 
29.9 
0.9 
 
Client Design 
2.3% 
29.9 
0.9 
 
Client Costs 
1.5% 
20.0 
0.6 
 
Owners management costs total 
6.0% 
79.8 
2.4 
 
Subtotal 
 
1,408.0 
41.9 
 
Property acquisitions 
 
282.3 
8.4 
 
Subtotal 
 
1,690.3 
50.3 
Risk and contingency 
 
275.6 
8.2 
 
20% excluding LRVs 
16% including LRVs 
33  Subtotal 
 
1,965.9 
58.4 
Table 3 – Draft estimate with corrections 
 
  mak i ng   the  di ff er en c e  
10 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
In reviewing each element we would recommend various adjustments to the overall 
costs as summarised in the table below. Total cost increases from $1,945m to 
$3,673, an increase of some 89%;  
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
 
Direct construction costs 
 
 
 

Track (34 km alignment) 
18.8% 
211.5 
6.3 

Power (inc. 35 Nr substations) 
25.3% 
285.6 
8.5 

Systems 
8.1% 
90.8 
2.7 

Utilities 
29.0% 
326.8 
9.7 

Roadworks 
4.2% 
47.5 
1.4 

Stops (43 Nr) 
5.3% 
59.4 
1.8 

Depot & Stabling Facility 
9.4% 
105.8 
3.1 

Direct construction costs 
100.0% 
1,127.4 
33.5 

Preliminaries 
36.8% 
414.9 
12.3 
10 
Traffic management 
4.5% 
50.7 
1.5 
12 
Contractor’s design 
18.0% 
202.9 
6.0 
13  Indirect construction costs 
 
668.5 
19.9 
14  Total construction costs 
 
1,795.9 
53.4 
15 
Contractor’s OH&P 
15.0% 
269.4 
8.0 
16  Total contractor’s costs 
 
2,065.3 
61.4 
15 
Rolling stock 
54 Nr 
368.3 
10.9 
16  Subtotal 
 
2,433.6 
72.4 
 
Planning & Development 
1.7% 
41.4 
1.2 
 
Client Design 
2.5% 
60.8 
1.8 
 
Client Costs 
3.8% 
92.5 
2.8 
 
Owners management costs total 
8.0% 
194.7 
5.8 
 
Subtotal 
 
2,628.3 
78.1 
 
Property acquisitions 
 
282.3 
8.4 
 
Subtotal 
 
2,910.6 
86.5 
 
Risk and contingency 
30.0% 
762.7 
22.7 
33  Subtotal 
 
3,673.3 
109.2 
Table 4 – Revised estimate based on peer review 
 
 
  mak i ng   the  di ff er en c e  
11 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
3.2 
Option 9a 
 
The latest draft estimate at a P50 confidence level for the CCFAS2 project is 
$1,033m plus light rail vehicles of $135m and heavy rail of $72m, giving a total of 
$1,240m as set out below; 
 
All costs $m 
 
Total $ 
Total $m per 
km 
 

Land & Property 
 
192.7 
11.3 

Investigation & Reporting 
 
18.5 
1.1 

Developed Design & D&C Monitoring 
 
30.8 
1.8 

Design & Construct contract 
 
 
 
4.01 
Track (LR 13 km, HR 4 km alignment) 
 
218.8 
12.8 
4.02 
Power (inc. 15 substations, LR only) 
 
30.2 
1.8 
4.03 
Systems 
 
7.7 
0.5 
4.04 
Statutory Undertakers  Equipment 
 
30.3 
1.8 
4.05 
Highway Costs 
 
6.5 
0.4 
4.06 
Stops (17 Nr LR, 2 Nr HR) 
 
38.3 
2.2 
4.07 
Support Facilities 
 
73.3 
4.3 
4.08 
Design 
 
16.2 
0.9 
4.09   Programme & Project Management 
 
114.9 
6.7 
 
Subtotal 
 
536.2 
31.4 
4.10 
Off site overhead and Profit 
 
80.4 
4.7 
 
Total D&C 
 
616.6 
36.1 

Contingency P50 
20% 
174.0 
10.2 

Subtotal @4Q14 prices 
  
1,032.6 
60.4 
7.01 
Rolling Stock – Light rail 
22 Nr 
134.9 
7.9 
7.02 
Rolling Stock – Heavy rail 
9 Nr 
72.0 
4.2 

Total Costs @4Q14 Prices 
  
1,239.5 
72.5 
Table 5- Draft estimate as presented (LR = Light Rail, HR = Heavy Rail) 
 
 
 
 
 
  mak i ng   the  di ff er en c e  
12 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
In order to compare the CCFAS2 project with other similar light rail systems we have 
analysed the draft estimate and re-ordered some of the line items to reach a 
standard elemental format as set out below; 
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
Direct construction costs 
 
 
 

Track (LR 13 km, HR 4 km alignment) 
54% 
218.8 
12.8 

Power (inc. 15 substations, LR only) 
8% 
30.2 
1.8 

Systems 
2% 
7.7 
0.5 

Utilities 
8% 
30.3 
1.8 

Roadworks 
2% 
6.5 
0.4 

Stops (17 Nr LR, 2 Nr HR) 
10% 
38.3 
2.2 

Depot & Stabling Facility 
18% 
73.3 
4.3 

Direct construction costs 
100% 
405.1 
23.7 

Preliminaries 
24% 
96.7 
5.7 
10 
Traffic management 
5% 
18.2 
1.1 
12 
Contractor’s design 
4% 
16.2 
0.9 
13  Indirect construction costs 
 
131.1 
7.7 
14  Total construction costs 
 
536.2 
31.4 
15 
Contractor’s OH&P 
9% 
80.4 
4.7 
16  Total contractor’s costs 
 
616.6 
36.1 
15 
Rolling stock (LRVs) 
22 Nr 
134.9 
7.9 
16 
Rolling stock (AM Class EMUs) 
9 Nr 
72.0 
4.2 
17  Subtotal 
 
823.5 
48.2 
 
Planning & Development 
3% 
18.5 
1.1 
 
Client Design 
3% 
18.5 
1.1 
 
Client Costs 
2% 
12.3 
0.7 
 
Owners management costs total 
7% 
49.3 
2.9 
 
Subtotal 
 
872.8 
51.0 
 
Property acquisitions 
 
192.7 
11.3 
 
Subtotal 
 
1,065.5 
62.3 
Risk and contingency 
 
20% excluding Rolling Stock 
 
174.0 
10.2 
16% including Rolling Stock 
33  Subtotal 
 
1,239.5 
72.5 
Table 6 – Draft estimate in standardised cost breakdown structure (LR = Light Rail, HR = Heavy Rail) 
 
  mak i ng   the  di ff er en c e  
13 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
In reviewing the data presented we have found several anomalies in formulas used 
to arrive at the current estimate based on the information provided. We have 
assessed that the accurate representation of the provided information is as follows. 
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
Direct construction costs 
 
 
 

Track (LR 13 km, HR 4 km alignment) 
54% 
218.8 
12.8 

Power (inc. 15 substations, LR only) 
8% 
30.2 
1.8 

Systems 
2% 
7.7 
0.5 

Utilities 
8% 
30.3 
1.8 

Roadworks 
2% 
6.5 
0.4 

Stops (17 Nr LR, 2 Nr HR) 
10% 
38.3 
2.2 

Depot & Stabling Facility 
18% 
73.3 
4.3 

Direct construction costs 
100% 
405.1 
23.7 

Preliminaries 
24% 
96.7 
5.7 
10 
Traffic management 
5% 
18.2 
1.1 
12 
Contractor’s design 
4% 
16.2 
0.9 
13  Indirect construction costs 
 
131.1 
7.7 
14  Total construction costs 
 
536.2 
31.4 
15 
Contractor’s OH&P 
15% 
80.4 
4.7 
16  Total contractor’s costs 
 
616.6 
36.1 
15 
Rolling stock (LRVs) 
22 Nr 
134.9 
7.9 
16 
Rolling stock (AM Class EMUs) 
9 Nr 
72.0 
4.2 
17  Subtotal 
 
823.5 
48.2 
 
Planning & Development 
3% 
18.5 
1.1 
 
Client Design 
3% 
18.5 
1.1 
 
Client Costs 
2% 
12.3 
0.7 
 
Owners management costs total 
7% 
49.3 
2.9 
 
Subtotal 
 
872.8 
51.0 
 
Property acquisitions 
 
199.8 
11.7 
 
Subtotal 
 
1,072.6 
62.7 
Risk and contingency 
 
20% excluding Rolling Stock 
 
174.0 
10.2 
16% including Rolling Stock 
33  Subtotal 
 
1,246.6 
72.9 
Table 7 – Draft estimate with corrections (LR = Light Rail, HR = Heavy Rail) 
 
  mak i ng   the  di ff er en c e  
14 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
 
In reviewing each element we would recommend various adjustments to the overall 
costs as summarised in the table below. Total cost increases from $1,240m to 
$1,865m, an increase of some 50%;  
 
All costs $m 
 
Total $m 
Total $m per 
km 
 
Direct construction costs 
 
 
 

Track (LR 13 km, HR 4 km alignment) 
31.0% 
176.4 
5.2 

Power (inc. 15 substations, LR only) 
18.8% 
107.3 
3.2 

Systems 
1.4% 
7.7 
0.2 

Utilities 
22.6% 
128.6 
3.8 

Roadworks 
1.1% 
6.5 
0.2 

Stops (17 Nr LR, 2 Nr HR) 
6.7% 
38.3 
1.1 

Depot & Stabling Facility 
18.4% 
104.6 
3.1 

Direct construction costs 
100.0% 
569.4 
16.8 

Preliminaries 
29.9% 
170.1 
5.1 
10 
Traffic management 
4.5% 
25.6 
0.8 
12 
Contractor’s design 
15.0% 
85.4 
2.5 
13  Indirect construction costs 
 
281.1 
8.4 
14  Total construction costs 
 
850.5 
25.2 
15 
Contractor’s OH&P 
15.0% 
127.6 
3.8 
16  Total contractor’s costs 
 
978.1 
29.0 
15 
Rolling stock (LRVs) 
22 Nr 
134.9 
4.0 
16 
Rolling stock (AM Class EMUs) 
9 Nr 
72 
2.1 
17  Subtotal 
 
1,185.0 
33.0 
18 
Planning & Development 
2.1% 
24.5 
0.7 
19 
Client Design 
2.5% 
29.3 
0.9 
20 
Client Costs 
3.7% 
44.0 
1.3 
21  Owners management costs total 
8.3% 
97.8 
2.9 
22  Subtotal 
 
1,282.8 
31.9 
23 
Property acquisitions 
 
199.8 
5.9 
24  Subtotal 
 
1,482.6 
37.8 
25 
Risk and contingency 
25.8% 
382.8 
11.4 
36  Subtotal 
 
1,865.4 
49.2 
Table 8 – Revised estimate based on peer review (LR = Light Rail, HR = Heavy Rail) 
 
 
  mak i ng   the  di ff er en c e  
15 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 

Cost reviews 
4.1 
Overall cost 
To be able to use international light rail projects as comparators for Auckland the 
data set has to include projects that are similar in nature and extent. It is very 
difficult and not relevant to compare Auckland’s planned 34 km network, or even 
shorter initial stages, with simple short extensions to existing light rail networks. 
The design and construction of light rail systems in New Zealand and Australia 
requires a high percentage of imported skills, expertise and equipment. Turner & 
Townsend’s research and experience of planning for light rail systems in Australia, 
including wire free technology in Sydney, indicates that a cost of some NZD$60m per 
km for Auckland is overly optimistic and set at too low a level. 
A selection of relevant projects is given in the graph below, which can be 
supplemented with further similar projects from our global database. 
Total cost (NZD) per km
CCFAS2 Draft Estimate
CCFAS2 Peer Review
LR - FR - 03
LR - FR - 02
LR - FR - 01
LR - Aus - 06
LR - Aus - 05
LR - IRL - 03
LR - IRL - 02
LR - IRL - 01
LR - USA - 02
LR - USA - 01
LR - UK - 03
LR - UK - 01
$0 m
$50 m
$100 m
$150 m
$200 m
Graph 1 – Overall cost of light rail projects per route alignment km  
(LR = Light Rail, HR = Heavy Rail) 
 
  mak i ng   the  di ff er en c e  
16 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.2 
Direct construction costs 
In the time available it was not possible to consider individual unit rates in detail or 
verify the quantities used. The major cost components were assessed at a high level 
either at a total cost per route alignment, such as trackform, overhead wiring, road 
works and the like or at a facility level such as the depot and stabling or in some 
case a slightly more detailed level such as number of substations, stops and the like. 
4.2.1 
Trackform 
Option 4 has an alignment length of 33.6 km and Option 9a 17.1 km (13.2 km of 
light rail and 3.9 km of heavy rail). The trackform and storm water drainage appears 
to be set at a high level of pricing and there are opportunities to reduce this cost 
component, as shown in the table below; 
 
Draft Estimate 
Revised Estimate  Difference $m/km 
$m/km 
$m/km 
Option 4 
10.5 
6.3 
(4.2) 
Option 9a 
12.8 
5.2 
(7.6) 
Table 4.2.1 – Trackform per alignment km 
Some detailed observations for the trackform are; 
 
Track - there is a cost within the draft estimate for "Make good asphalt carriage 
way adjacent to slab" with a cost of $500/m. We would normally include this cost 
within the Roadworks budget.  
 
Track - the formwork rate of $120/m appears high. We would normally expect to 
see circa $15-$20/m, especially when it is re-usable.  
 
Track - our benchmarked data would be circa $4,200/m - $4,900/m for 
trackwork. The draft estimate has $6,270 plus the rail boot which is included 
within the drainage. This appears high.  
 
Drainage - the draft estimate includes the rail boot within the drainage heading 
and this would normally be within the track component. This equates to 
$2,616/m versus an expected range of $350-$500/m, leaving $573/m for 
drainage (based on the Dominion road option). This appears high as $250-
$300/m would be the expected range for drainage. 
 
 
 
 
  mak i ng   the  di ff er en c e  
17 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.2.2 
Bulk and traction power 
When considering the bulk and traction power requirements it would appear that the 
pricing of the feeders, substations and transformers reflect smaller sizes and 
capacities than those required for a light rail system which results in a shortfall of 
cost in this area. 
The draft estimate contains 43 light rail substations for Option 4 and 15 for Option 
9a, with heavy rail substations excluded. As a minimum we would advocate using a 
cost of $2.3m per traction substation.  
Additional notes and observations are given at Appendix 4. 
4.2.3 
Light rail systems 
Contained within the systems heading there needs to be provision for small power 
and lighting, combined services route, communications systems, security systems, 
passenger information system, road traffic and LRV signalling and ticketing systems. 
The allowances made for rail systems are largely one line items and do not appear to 
contain any detail, especially when compared to the detail in other areas such as the 
depot facility building. It is clear that this area of the draft estimate is understated 
and requires more work to better reflect the scope of works required to deliver a 
wire free light rail system. 
4.2.4 
Existing utilities 
The costs of existing utilities modifications are significantly lower as a proportion of 
the overall light rail infrastructure cost when compared to other international 
projects. It is recognised that Auckland city centre may have very few below and 
above ground utilities that require protection, relocation or diversion and the project 
team will have a deeper understanding of this position. However, this is an area of 
high risk for all light rail projects in our experience. 
If indeed the corridors are largely utility free then the costs could be considerably 
lower when compared to other light rail projects. 
4.2.5 
Stops 
Option 4 contains a total of 43 new light rail stops and Option 9a a combination of 17 
new light rail stops and 2 new heavy rail platforms. 
The average cost per stop in the draft estimate equates to $1.3m which is 
reasonable when compared to other similar light rail systems that have a variety of 
city centre and suburban stop locations. 
 
 
 
  mak i ng   the  di ff er en c e  
18 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.2.6 
Light rail depot and stabling 
Specific site conditions such as ground conditions, topography, sensitive noise 
receptors and the like can dictate a wide range of cost for depots and stabling 
facilities, as can the total fleet size with increased economies of scale for larger 
fleets. With the requirement for a temporary depot there will be some duplication of 
infrastructure which lead to some cost inefficiencies. The benchmark data indicates 
that the draft estimate is at the lower end of expectations so our suggested 
allowance is above the current assumption. 
The draft estimate equates to $1.4m per LRV and our revised estimate contains 
$2.0m per LRV. 
4.2.7 
Rolling stock 
The light rail vehicles are priced competitively but current market intelligence 
suggests that the unit price does not properly reflect the desire for wire free 
technology and we would recommend a unit price of at least $6.8m per vehicle, 
versus the draft estimate of $6.1m. 
We do not possess detailed knowledge of the Auckland Transport AM Class Electric 
Multiple Unit rolling stock pricing and have therefore assumed that the draft estimate 
of $8.0m per three car train is appropriate.  
 
 
  mak i ng   the  di ff er en c e  
19 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.3 
Indirect construction costs 
The following subsections summarise the findings and differences between the 
current estimate and the review undertaken by Turner & Townsend for the indirect 
construction cost elements. 
4.3.1 
Preliminaries 
Preliminaries comprise the management resources and temporary facilities needed to 
deliver the permanent works. They vary with the method and circumstances of the 
project and are very dependent upon the duration of the construction durations. 
Typically preliminaries include the core project and site management teams, 
stakeholder and community relations, the site compounds and offices and traffic 
management activities and staff. 
Preliminaries in the draft estimate at 28% are set at the lower end of what might be 
expected for a light rail system but may reflect what might be possible in New 
Zealand with lower people costs. However, it must be stressed that there will be 
requirements for light rail experts to be temporarily relocated to Auckland to 
undertake some of the specialised work associated with the management, 
installation and commissioning of a complex wire free light rail system into an 
established urban environment. Although people costs are generally lower in New 
Zealand there will still be a requirement for overseas staff to be deployed for the 
construction phase with the associated additional expense 
We have assessed that the preliminaries should be set at a level of 35% or greater 
In recommending an appropriate allowance (as a percentage of total direct 
construction costs) for preliminaries we considered various other light and heavy rail 
projects. The projects have been anonymised to retain client confidentiality. 
Graph 1 plots the preliminaries percentages. The data set shows that there is 
considerable variability in the preliminaries percentages, 29% to 71%, among these 
projects which can be explained to a considerable extent by the fact that 
preliminaries vary considerably with the works method, circumstances and 
complexity of the project. 
The heavy rail projects have been completed under either an Alliance delivery model 
or on a design and construct basis, with the Alliance projects tending to have higher 
preliminaries cost. 
 
 
 
  mak i ng   the  di ff er en c e  
20 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
 
Preliminaries & Traffic Management as a % of Direct Costs
 
CCFAS2 - Draft
Estimate Opt 4
 
CCFAS2 - Peer
Review
 
HR - AUS - 01
 
HR - AUS - 02
 
HR - AUS - 03
 
HR - AUS - 07
 
HR - AUS - 08
 
HR - AUS - 09
 
HR - AUS - 10
 
HR - AUS - 12
 
LR - AUS - 01
 
LR - AUS - 02
 
LR - AUS - 03
 
LR - AUS - 04
 
 
LR - UK - 01
 
LR - UK - 02
 
LR - UK - 03
 
LR - UK - 04
 
0%
10%
20%
30%
40%
50%
60%
70%
80%
 
Graph 2 - Preliminaries as percentage of direct construction costs in NSW and internationally  
(HR = Heavy Rail, LR = Light Rail) 
 
 
 
  mak i ng   the  di ff er en c e  
21 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.3.2 
Contractor’s design 
The contractor’s design allowance is in addition to any design undertaken by 
professional engineering companies engaged by Auckland Transport. The allowance 
includes the cost of detail design, construction support and any detail design 
required in conjunction with the utilities providers. 
The light rail systems design will form a considerable proportion of the total design 
effort, with expertise from outside of New Zealand. The requirements for a 100% 
wire free system will drive additional cost into both the client and contractor's design 
totals. 
The draft estimate contains a provision of 4% which, in Turner & Townsend’s 
experience of light rail projects in Australia and globally, would represent exceptional 
performance. To better reflect the complex design associated with a light rail project 
that relies heavily of specialist rail systems experts that are not resident in New 
Zealand we would suggest a percentage of at least 18%.  
Graph 2 plots the design percentages of 15 rail projects to demonstrate typical 
design proportion ranges. 
 
 
 
  mak i ng   the  di ff er en c e  
22 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Contractor Design as a % of Direct Costs
CCFAS2 - Draft Estimate Opt 4
CCFAS2 - Peer Review
HR - AUS - 01
HR - AUS - 02
HR - AUS - 03
HR - AUS - 05
HR - AUS - 07
HR - AUS - 08
HR - AUS - 10
HR - AUS - 15
LR - AUS - 01
LR - AUS - 02
LR - AUS - 03
LR - AUS - 04
LR - UK - 01
LR - UK - 05
LR - USA - 01
0%
5%
10%
15%
20%
25%
30%
Graph 3 - Design allowances for previous project  
(HR = Heavy Rail, LR = Light Rail)  
 
 
 
 
  mak i ng   the  di ff er en c e  
23 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
4.4 
Risk & contingency 
A P50 risk and contingency allowance of 20% for the project (excluding LRVs) must 
cover uncertainties in scope, quantities, unit rates and other risk events. Turner & 
Townsend consider this percentage as too low at this stage of the project 
development and scope definition.  
A more realistic level would be in the order of 30%, based upon Turner & Townsend 
recent experience of major engineering projects in Australia and internationally. 
It is worth taking into consideration the Australian Government’s Dept. of 
Infrastructure and Regional Development guidance (Best Practice Cost Estimation) 
that a risk allowance could be up to 40% for road projects and 70% for rail projects, 
when at Project Scoping stage. We consider that the Auckland CCFAS2 project may 
have just reached Project Scoping stage. 
Similarly, New South Wales Roads & Maritime Services guidance ranges from 40% to 
70% and a study by the UK Dept. of Transport into optimism bias suggests a range 
of 45% to 60% and above for projects in the early stages of development. 
Risk and contingency allowances
CCFAS2 - Draft Estimate
CCFAS2 - Peer Review
UK Dept. of Transport Low
UK Dept. of Transport High
Indicatice NSW Roads Low
Indicatice NSW Roads High
Best Practice Cost Estimating - Road Low
Best Practice Cost Estimating - Road High
Best Practice Cost Estimating - Rail Low
Best Practice Cost Estimating - Rail High
0% 10% 20% 30% 40% 50% 60% 70% 80%
Graph 4 – Typical risk and contingency allowances at early stage of project development 
 
  mak i ng   the  di ff er en c e  
24 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
 
Appendix 1 
Option 4 cost summaries 
 
  mak i ng   the  di ff er en c e  


Peer review of Auckland Light Rail Cost Estimate
4/12/2014
Option 4 Summary 

Element
Item description
Draft Estimate 
T&T Peer review Price 
Comments
2.12.2014 Price 
NZ$ (inflated 0%)
NZ$
 33,636m 
 33,636m 
Length
1. Land and Property
           282,312,093                282,312,093 
2. Investigation and Reporting
             29,877,147                  41,127,703 
Percentage based calculation
3. Developed design reporting including D&C Contract               49,795,251                154,228,888 
Draft Estimate 2.12.2014 has a total 5%. T&T have increased to 
monitoring
7.5%.
4. Detailed design and Construction
           867,513,286             1,788,161,011 
Split of the total is No1-6
1.Track
            352,137,531                 211,499,179 
Bridges and support structures & Portals or underpasses costs have 
been left as per the Draft Estimate 2.12.2014, as T&T have no 
drawings to price. The track has been reduced $58m and drainage 
by $82m based on market knowledge.
2. Power
              76,178,920                 350,989,324 
Power supply has been excluded, so the estimate is like for like. 
Substations and underground power was under-priced. $78m 
increase in substations and $131m increase in underground power.
3. Systems
              20,126,578                   90,783,564 
Draft Estimate 2.12.2014 was under-priced. 
2.Statutory undertakers                63,717,800                 326,807,376 
Draft Estimate 2.12.2014 was under-priced. 
Equipment
3.Highway costs
              13,906,015                   47,460,647 
T&T have used the Draft Estimate 2.12.2014 price for cycleway.
Draft Estimate 2.12.2014 price for highway seems very low. T&T 
believe the works outside of the corridor have not been allowed for.
4. Stops
              54,892,860                   54,892,860 
Stops price has been pro-rated from benchmarked data.  
The Draft Estimate 2.12.2014 bus interchange price has been used 
by T&T.
5.Support Facilities
              74,410,308                 105,785,855 
T&T have used the administration building/Control centre & 
Temporary depot cost within the comparison.
6. Design
              26,214,802                 202,115,530 
Draft Estimate 2.12.2014 had 4%. T&T benchmarked data and 
market knowledge highlights the design is severely under-priced. 15-
20% would be more comfortable. T&T have allowed 18% for this 
comparison exercise.
6.Programme and 
            185,928,472                 463,181,424 
The Draft Estimate 2.12.2014 has preliminaries at 22%. T&T have 
Project Management
increased to 30% based on market knowledge.
check
                            -                    65,354,748 
Off site Overheads and Profit @ 15%
           130,126,992                268,224,152 
risk
           253,962,477                760,216,155 
WT Risk @ 20.27% . T&T Risk @ 30%.  
1.0795 exchange rate used
Total expected cost
          1,613,587,246               3,294,270,002 
CCFAS2 Draft Estimate estimate-2.12.2014 LPD rev c
Summary 34km

DRAFT COMERCIAL IN CONFIDENCE
Light Rail 
2.12.2014
a
b
c
d
e
f
 Convert Sydney 
price to Auckland 
 Convert Aus $  prices.  (Assumed 
 T&T expected 
 Stage 1 Queen 
 Stage 2 
 Stage 4 Mt Eden  
 Temporary 
 Stage 2 
 Stage 5 Customs 
 Stage 5 New 
to NZ $ 
increase of 0%, 
Auckland price X 
Level 4 Cost 
Street ( Fort to 
Dominion Road 
 Stage 3 
Road (including 
 Additional 
 % of total 
 T&T expected 
Level 1-Project Stage
level 1 Cost Asset
Level3 Cost Sub Asset
Depot Including 
 Stage 1 Total 
Stoddard & 
 Stage 2 total 
 Stages 1-3 
Street To New 
Market to 
 Total 
 $ / m 
(1:1.0795) 
having looked 
route length    = col e 
Activity
Ian Mkinnan 
Ian McKinnon to  
Sandringham Road 
upper Symonds 
Stabling 
expected $ 
Aus $/m 
rail link 
Depot) 
Market 
Onehunga 
(XE.com 
through the WT BoQ 
X 33,636 (Total 
Drive ) 
Mt Roskill) 
Street) 
03.12.14) 
the rates look inline 
length) 
with expectations of 
Sydney 
Length
                     2,081                           832                       2,913                     5,220                     1,800                     7,020                         5,000                       14,933                         5,715                         4,988                     8,000 
                   33,636 
1. Land and Property
1. Land and Property
1. Land Acquisitions
$                       -
 
30,939,515
$         
744,957
$              
31,684,472
$         
21,625,058
$             
53,309,530
$             
28,146,646
$             
112,245,335
$           
$       25,739,757
 
$    10,000,000
 
229,441,268
$         
$            6,821
 
14.22%
$              229,441,268
 
1a.Bus Terminus land
2,700,000
$           
2,700,000
$           
2,700,000
$               
5,400,000
$               
2,700,000
$               
8,100,000
$             
$               241
 
0.50%
$                  8,100,000
 
1b Depot land
1,500,000
$             
1,500,000
$             
32,290,000
$         
32,290,000
$         
33,790,000
$             
33,790,000
$           
$            1,005
 
2.09%
$                33,790,000
 
2.Relocations
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
3. Alterations /Refurbishments/ 
Demolitions
2,554,200
$           
2,554,200
$           
2,554,200
$               
$      3,000,000
 
5,554,200
$             
$               165
 
0.34%
$                  5,554,200
 
4. Legal and other Fees
2% $                       -
 
30,000
$                  
30,000
$                  
672,790
$              
660,699
$              
1,333,489
$           
486,501
$                  
1,849,990
$               
616,933
$                  
2,244,907
$               
$            514,795
 
$         200,000
 
5,426,625
$             
$               161
 
0.34%
$                  5,426,625
 
Sub Total Land and Property
$                       -
 
1,530,000
$             
1,530,000
$             
34,312,305
$         
36,249,856
$         
70,562,161
$         
24,811,559
$             
96,903,720
$             
31,463,579
$             
114,490,242
$           
$       26,254,552
 
$    13,200,000
 
282,312,093
$         
$              282,312,093
 
2. Investigation and 
1.Planning
1.Route development costs
Reporting
2. Consultation
2.Approvals
1.Designations costs
$               890
 
1.85%
2%
3%
2,867,833
$             
1,448,458
$             
4,316,291
$             
4,460,760
$           
3,344,172
$           
7,804,932
$           
3,783,785
$               
15,905,008
$             
4,427,524
$               
4,169,055
$               
5,375,560
$          
52,061
$           
29,929,208
$           
41,127,703
$                 
2. Legigslive approvals costs
3.Funding
1.Outline business case
2. Full business case
Sub Total Investigation and Reporting
2,867,833
$             
1,448,458
$             
4,316,291
$             
4,460,760
$           
3,344,172
$           
7,804,932
$           
3,783,785
$               
15,905,008
$             
4,427,524
$               
4,169,055
$               
$         5,375,560
 
29,877,147
$           
$                41,127,703
 
3. Developed design 
1.Preliminary Design
reporting including D&C  2.Reference Design
$               890
 
1.85%
3%
3%
2,867,833
$             
1,448,458
$             
4,316,291
$             
4,460,760
$           
3,344,172
$           
7,804,932
$           
3,783,785
$               
15,905,008
$             
4,427,524
$               
4,169,055
$               
5,375,560
$          
52,061
$           
29,929,208
$           
61,691,555
$                 
Contract monitoring
3. Detailed Design
4. Procurement
5.Programme and 
1.Internal management costs
0.5%
477,972
$                
241,410
$                
719,382
$                
743,460
$              
557,362
$              
1,300,822
$           
630,631
$                  
2,650,835
$               
737,921
$                  
694,843
$                  
$            895,927
 
$             8,677
 
4,988,203
$             
$               148
 
0.31%
2.5% $                51,409,629
 
Project Management
2.External management support
0.5%
477,972
$                
241,410
$                
719,382
$                
743,460
$              
557,362
$              
1,300,822
$           
630,631
$                  
2,650,835
$               
737,921
$                  
694,843
$                  
$            895,927
 
$             8,677
 
4,988,203
$             
$               148
 
0.31%
1% $                20,563,852
 
3.D&C Contract Monitoring
0.5%
477,972
$                
241,410
$                
719,382
$                
743,460
$              
557,362
$              
1,300,822
$           
630,631
$                  
2,650,835
$               
737,921
$                  
694,843
$                  
$            895,927
 
$             8,677
 
4,988,203
$             
$               148
 
0.31%
0.5% $                10,281,926
 
4.Stakeholder& Publicity
0.50%
477,972
$                
241,410
$                
719,382
$                
743,460
$              
557,362
$              
1,300,822
$           
630,631
$                  
2,650,835
$               
737,921
$                  
694,843
$                  
$            895,927
 
$             8,677
 
4,988,203
$             
$               148
 
0.31%
0.5% $                10,281,926
 
Sub Total Developed design and D&C monitoring
4,779,721
$             
2,414,098
$             
7,193,819
$             
7,434,600
$           
5,573,620
$           
13,008,220
$         
6,306,309
$               
26,508,348
$             
7,379,208
$               
6,948,427
$               
$         8,959,268
 
49,795,251
$           
$            1,480
 
$               - 
$              154,228,888
 
4. Detailed design and 
1.Track
1.Trackbed and rail
14,324,450
$           
5,307,940
$             
19,632,390
$           
33,066,420
$         
10,833,120
$         
43,899,540
$         
31,592,000
$             
95,123,930
$             
36,045,480
$             
31,520,210
$             
$       48,147,200
 
210,836,820
$         
$            6,268
 
13.07% $              4,200
 
$              4,534
 
$                        4,534
 
$              152,505,624
 
Construction
2.Bridges and support structures
500,000
$                
N/A
500,000
$                
10,000,000
$         
N/A
10,000,000
$         
5,000,000
$               
15,500,000
$             
5,000,000
$               
11,000,000
$             
N/A
31,500,000
$           
$               936
 
1.95%
$                31,500,000
 
3.Portals or underpasses
18,411,835
$           
N/A
18,411,835
$           
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
18,411,835
$           
$               547
 
1.14%
18,411,835
$                 
4.Public realm
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
5. Public Art
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
6. Track drainage & attenuation
5,733,096
$             
2,292,862
$             
8,025,958
$             
16,645,770
$         
1,424,850
$           
18,070,620
$         
13,772,500
$             
39,869,078
$             
15,743,790
$             
13,740,008
$             
$       22,036,000
 
91,388,876
$           
$            2,717
 
5.66% $                 250
 
$                 270
 
$                           270
 
$                  9,081,720
 
2. Power
1.Supply
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
2.Sub-Stations
610,000
$                
305,000
$                
915,000
$                
1,220,000
$           
610,000
$              
1,830,000
$           
1,220,000
$               
3,965,000
$               
1,220,000
$               
2,745,000
$               
$         2,745,000
 
10,675,000
$           
$               317
 
0.66% $     82,600,000
 
$     89,166,700
 
$               89,166,700
 
$                89,166,700
 
3. OLE
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Excluded
Excluded
4. Underground
4,329,320
$             
1,581,040
$             
5,910,360
$             
10,478,400
$         
3,396,000
$           
13,874,400
$         
9,650,000
$               
29,434,760
$             
11,029,800
$             
9,929,360
$               
$       15,110,000
 
65,503,920
$           
$            1,947
 
4.06% $              5,411
 
$              5,841
 
$                        5,841
 
$              196,467,876
 
3. Systems
1. Signalling
1,820,000
$             
15,000
$                  
1,835,000
$             
2,110,000
$           
492,001
$              
2,602,001
$           
2,140,000
$               
6,577,001
$               
2,435,000
$               
3,375,000
$               
$         1,530,000
 
13,917,001
$           
$               414
 
0.86% $              1,500
 
$              1,619
 
$                        1,619
 
$                54,456,684
 
2. Telecoms
395,629
$                
274,800
$                
670,429
$                
897,428
$              
317,001
$              
1,214,429
$           
912,567
$                  
2,797,425
$               
1,043,057
$               
925,666
$                  
$         1,443,429
 
6,209,577
$             
$               185
 
0.38% $              1,000
 
$              1,080
 
$                        1,080
 
$                36,326,880
 
2.Statutory undertakers 1.D
  
iversions
5,764,200
$             
2,228,300
$             
7,992,500
$             
9,642,200
$           
1,128,000
$           
10,770,200
$         
9,324,950
$               
28,087,650
$             
8,966,700
$               
10,360,150
$             
$       16,303,300
 
63,717,800
$           
$            1,894
 
3.95% $              9,000
 
$              9,716
 
$                        9,716
 
$              326,807,376
 
Equipment
2.Upgrades
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
3.Highway costs
1.Highway changes
854,800
$                
$                       -
 
854,800
$                
1,233,000
$           
27,500
$                
1,260,500
$           
130,000
$                  
2,245,300
$               
1,300,000
$               
2,487,000
$               
$            339,000
 
6,371,300
$             
$               189
 
0.39% $              1,100
 
$              1,187
 
$                        1,187
 
$                39,925,932
 
2. Bus Facilities
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
3. Cycle facilities
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
2,314,575.00
$          
2,020,140
$               
3,200,000
$          
7,534,715
$             
7,534,715
$                   
4. Stops
1. Civil Works
$            1,415
 
2.95% $              2,000
 
$              2,159
 
$                        2,159
 
$                47,599,860
 
10,054,590
$           
1,442,120
$             
11,496,710
$           
9,954,560
$           
9,954,560
$           
6,681,800
$               
28,133,070
$             
9,421,590
$               
3,188,680
$               
6,856,520
$          
47,599,860
$           
2. Shelters and furniture
N/A
3. Bus Interchange
$               217
 
0.45% ?
7,293,000
$                   
2,431,000
$           
2,431,000
$           
2,431,000
$               
4,862,000
$               
2,431,000
$               
Not Required
Not Required
7,293,000
$             
5.Support Facilities
1. Administration building/Control 
centre
N/A
1,000,000
$             
1,000,000
$             
N/A
Part of depot
N/A
N/A
N/A
N/A
N/A
N/A
1,000,000
$             
$                 30
 
0.06%
1,000,000
$                   
2.Control centre
Excluded
2,000,000
$             
Excluded
Excluded
5,000,000
$           
5,000,000
$           
Excluded
5,000,000
$               
Excluded
Excluded
Excluded
7,000,000
$             
$               208
 
0.43%
$                  8,500,000
 
3.Maintenance sheds
N/A
N/A
N/A
N/A
N/A
N/A
$            1,974
 
4.12%
-
$                              
4.Storage sheds
N/A
15,270,308
$           
15,270,308
$           
N/A
50,000,000
$         
50,000,000
$         
N/A
65,270,308
$             
N/A
N/A
N/A
1,140,000
$      
66,410,308
$           
73,993,096
$      
$     79,875,547
 
$               79,875,547
 
$                96,285,855
 
5. Storage Yards
N/A
N/A
N/A
N/A
N/A
N/A
6. Design
1. Detailed design
3,780,612
$             
6,836,290
$           
13,931,095
$             
$               779
 
1.62%
2.MSQA
4%
2,511,917
$             
1,268,695
$             
-
$                       
3,907,151
$           
2,929,139
$           
-
$                     
3,314,193
$               
-
$                         
3,878,040
$               
3,651,649
$               
4,708,418
$          
45,600
$           
26,214,802
$           
18%
202,115,530
$               
6.Programme and 
1.Temporary traffic Management
4.50%
2,825,906
$             
1,427,282
$             
4,253,188
$             
4,395,545
$           
3,295,281
$           
7,690,826
$           
3,728,467
$               
15,672,481
$             
4,362,795
$               
4,108,105
$               
$         5,296,970
 
$           51,300
 
29,491,651
$           
$               877
 
1.83%
4.5%
$                50,528,883
 
Project Management
2.Preliminaries and General
22%
14,989,863
$           
7,570,936
$             
22,560,799
$           
23,315,924
$         
17,479,636
$         
40,795,560
$         
19,777,445
$             
83,133,804
$             
23,142,202
$             
21,791,213
$             
$       28,097,484
 
$         272,118
 
156,436,821
$         
$            4,651
 
9.69%
30%
$              412,652,541
 
Sub Total Base D&C
83,125,606
$           
41,984,283
$           
125,109,889
$         
129,297,398
$       
96,932,528
$         
226,229,926
$       
109,674,922
$           
461,014,737
$           
128,334,029
$           
120,842,181
$           
$     155,813,321
 
$      1,509,018
 
867,513,286
$         
$          25,791
 
53.76%
$           1,788,161,011
 
Off site Overheads and Profit
15%
12,468,841
$           
6,297,642
$             
18,766,483
$           
19,394,610
$         
14,539,879
$         
33,934,489
$         
16,451,238
$             
69,152,210
$             
19,250,104
$             
18,126,327
$             
$       23,371,998
 
$         226,353
 
130,126,992
$         
$            3,869
 
8.06%
$              268,224,152
 
Sub Total D&C
95,594,447
$           
48,281,925
$           
143,876,372
$         
148,692,008
$       
111,472,407
$       
260,164,415
$       
126,126,160
$           
530,166,947
$           
147,584,133
$           
138,968,508
$           
$     179,185,319
 
$      1,735,371
 
997,640,278
$         
$          29,660
 
$                   1
 
$           2,056,385,163
 
Total excluding Risk
103,242,001
$         
53,674,481
$           
156,916,482
$         
194,899,673
$       
156,640,055
$       
351,539,728
$       
161,027,813
$           
669,484,023
$           
190,854,444
$           
264,576,232
$           
$     219,774,699
 
$    14,935,371
 
1,359,624,769
$      
$          40,422
 
$                   1
 
$           2,534,053,847
 
Contingency (P50)
Estimating Risk
4.27%
4,408,433
$             
2,291,900
$             
6,700,334
$             
8,322,216
$           
6,688,530
$           
15,010,746
$         
6,875,888
$               
28,586,968
$             
8,149,485
$               
11,297,405
$             
$         9,384,380
 
$         637,740
 
58,000,000
$           
$            1,724
 
3.59%
10%
$              253,405,385
 
Scope Risk
6.00%
6,194,520
$             
3,220,469
$             
9,414,989
$             
11,693,980
$         
9,398,403
$           
21,092,384
$         
9,661,669
$               
40,169,042
$             
11,451,267
$             
15,874,574
$             
$       13,186,482
 
$         896,122
 
60,000,000
$           
$            1,784
 
3.72%
10%
$              253,405,385
 
Specific Risk
10%
10,324,200
$           
5,367,448
$             
15,691,648
$           
19,489,967
$         
15,664,006
$         
35,153,973
$         
16,102,781
$             
66,948,402
$             
19,085,444
$             
26,457,623
$             
$       21,977,470
 
$      1,493,537
 
135,962,477
$         
$            4,042
 
$               - 
10%
$              253,405,385
 
Sub Total Contingency
20,927,153
$           
10,879,817
$           
31,806,971
$           
39,506,163
$         
31,750,939
$         
71,257,103
$         
32,640,338
$             
135,704,412
$           
38,686,196
$             
53,629,602
$             
$       44,548,332
 
$      3,027,399
 
253,962,477
$         
$            7,550
 
$               - 
$              760,216,155
 
Total expected cost
124,169,154
$         
64,554,298
$           
188,723,453
$         
234,405,836
$       
188,390,994
$       
422,796,831
$       
193,668,151
$           
805,188,435
$           
229,540,640
$           
318,205,834
$           
$     264,323,031
 
$    17,962,770
 
1,613,587,246
$      
$          47,972
 
$     3
  ,294,270,002
Post per m
59,668
$                  
77,589
$                  
64,787
$                  
44,905
$                
104,662
$              
60,227
$                
38,734
$                    
53,920
$                    
40,165
$                    
63,794
$                    
$              33,040
 
47,972
$                  
Contingency (P95)
Estimating Risk
Scope Risk
91%
Specific Risk
Sub Total P95
Total Funding Risk Cost
CCFAS2 Draft Estimate estimate-2.12.2014 LPD rev c
Final Summary @ 0% Syd 2 Auc


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Appendix 2 
Option 9a cost summaries 
 
  mak i ng   the  di ff er en c e  


Peer review of Auckland Light Rail Cost Estimate
5/12/2014
Summary  HR & LR
Element
Item description
Draft Estimate 
T&T Peer review Price 
Comments
2.12.2014 Price 
NZ$ (inflated 0%)
NZ$
                    17,099                          17,099  Length
1. Land and Property
           192,681,194                199,821,194 
Draft Estimate 2.12.2014 has an error in calculations. $7m.
2. Investigation and Reporting
             17,995,062                  24,455,672 
Percentage based calculation
3. Developed design reporting including D&C Contract               29,991,770                  73,367,015 
Draft Estimate 2.12.2014 has a total 5%. T&T have increased to 
monitoring
7.5%.
4. Detailed design and Construction
           521,595,966                850,632,056 
Split of the total is No1-6
1.Track
            207,841,052                 176,391,909 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used and adjusted in line with T&T's 
benchmarked data. T&T reduced by $31m
2. Power
             30,196,080                 107,328,999 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used and adjusted in line with T&T's 
benchmarked data. Added an additional $52m for the power and an 
additional $25 for the substations
3. Systems
               7,669,021                     7,669,021 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used. The initial view is the estimate 
is low, although the benchmarked data is not readily available to 
change the Draft Estimate 2.12.2014.
2.Statutory undertakers                30,272,600                 128,630,124 
Insufficient time to fully analyse the costs, therefore the Draft 
Equipment
Estimate 2.12.2014 has been used. An additional $98m has been 
added to the utilities estimate.
3.Highway costs
               6,514,830                     6,514,830 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used. The initial view is the estimate 
is low, although the benchmarked data is not readily available to 
change the Draft Estimate 2.12.2014.
4. Stops
             38,280,052                   38,280,052 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used. The initial view is the estimate 
is low, although the benchmarked data is not readily available to 
change the Draft Estimate 2.12.2014.
5.Support Facilities
             73,270,308                 104,645,855 
Insufficient time to fully analyse the costs, therefore the Draft 
Estimate 2.12.2014 has been used. The initial view is the estimate 
is low, therefore an additional $30m has been added to the to 
depot.
6. Design
             15,761,758                   85,419,119 
Draft Estimate 2.12.2014 had 4%. T&T benchmarked data and 
market knowledge highlights the design is severely under-priced. 
T&T have allowed 15%.
6.Programme and 
            111,790,265                 195,752,147 
The Draft Estimate 2.12.2014 has preliminaries at 22%. T&T have 
Project Management
increased to 25%.
check
                          -                                  -   
Off site Overheads and Profit @ 15%
            78,239,394                127,594,808 
risk
          170,370,037                382,761,225 
WT Risk @ 20.27% . T&T Risk @ 30%.  
1.0795 exchange rate used
Total expected cost
         1,010,873,423               1,658,631,970 
CCFAS2 Draft Estimate estimate-2.12.2014 LPD rev c
Summary HR& LR

Heavy rail and light rails
#REF!
DRAFT COMMERCIAL IN CONFIDANCE
 excludes heavy rail with park and 
ride and final depot 

LR
HR
a

b
c
d
e
f
 Convert Sydney 
price to Auckland 
 Convert Aus $  prices.  (Assumed 
 Stage 1A Queen 
 Temporary 
to NZ $ 
increase of 0%, 
 T&T expected 
 Queen Street to     New Market to 
 % of total 
 T&T expected 
Level 1-Project Stage
level 1 Cost Asset
Level3 Cost Sub Asset
Street ( Fort to Ian 
Depot Including 
 Final Depot 
 Total 
 $ / m 
 $ / m 
(1:1.0795) 
having looked 
Auckland price X 
Newmarket 
Onehunga 
expected $ 
Aus $/m 
Mkinnan Drive ) 
rail link 
(XE.com 
through the WT 
route length   
03.12.14) 
BoQ the rates look 
Heavy Rail with Park 
inline with 
Level 4 Cost Activity
and Ride
expectations of 
Length
                            2,081                            832                           2,326                      8,000 
                      13,239 
1. Land and Property
1. Land and Property
1. Land Acquisitions
$                  7,
  000,000
$          110,
 
264,033
$       33,
 
933,216
$       30,
 
000,000
$          181,
 
197,249
$                  3,
  109
$         47,
 
405
$              181,
  
197,249
2.Relocations
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
3. Alterations /Refurbishments/ 
Demolitions
$       15,
 
000,000
$            15,
 
000,000
$                      -
  
$               -
 
$                15,
  
000,000
4. Legal and other Fees
2% $                      140,
 
000
$                           - 
$                      -
  
$              2,
  205,281
$            678,
  
664
$            600,
  
000
$             3,
  623,945
$                       62
 
$              948
 
$                  3,
  623,945
Sub Total Land and Property
$                           - 
$                      -
  
$          112,
 
469,314
$       34,
 
611,880
$       45,
 
600,000
$          192,
 
681,194
$                  3,
  172
$         48,
 
353
$              199,
  
821,194
2. Investigation and 
1.Planning
1.Route development costs
$                     888
 
$              820
 
Reporting
2. Consultation
$                      -
  
$               -
 
$                            - 
2.Approvals
1.Designations costs
$                      -
  
$               -
 
2.5% $                24,
  
455,672
3%
$                  3,
  885,023
$                2,
  867,833
$           1,
  448,458
$             1,
  906,467
$         5,
   375,560
$         2,
   511,721
$           17,
  
995,062
2. Legigslive approvals costs
$                      -
  
$               -
 
$                            - 
3.Funding
1.Outline business case
$                      -
  
$               -
 
$                            - 
2. Full business case
$                      -
  
$               -
 
$                            - 
Sub Total Investigation and Reporting
$                   3,
  885,023
$                 2,
  867,833
$            1,
  448,458
$              1,
  906,467
$         5,
   375,560
$         2,
  511,721
$            17,
 
995,062
$                     888
 
$              820
 
$                24,
  
455,672
3. Developed design 
1.Preliminary Design
$                     888
 
$              820
 
reporting including D&C 
2.Reference Design
$                      -
  
$               -
 
3% $                29,
  
346,806
3%
$                  3,
  885,023
$                2,
  867,833
$           1,
  448,458
$             1,
  906,467
$         5,
   375,560
$         2,
   511,721
$           17,
  
995,062
Contract monitoring
3. Detailed Design
$                      -
  
$               -
 
4. Procurement
$                      -
  
$               -
 
5.Programme and 
1.Internal management costs
0.5%
$                      647,
 
504
$                    477,
 
972
$               241,
 
410
$                 317,
 
744
$            895,
  
927
$            418,
  
620
$             2,
  999,177
$                     148
 
$              137
 
2.5% $                24,
  
455,672
Project Management
2.External management support
0.5%
$                      647,
 
504
$                    477,
 
972
$               241,
 
410
$                 317,
 
744
$            895,
  
927
$            418,
  
620
$             2,
  999,177
$                     148
 
$              137
 
1% $                  9,
  782,269
3.D&C Contract Monitoring
0.5%
$                      647,
 
504
$                    477,
 
972
$               241,
 
410
$                 317,
 
744
$            895,
  
927
$            418,
  
620
$             2,
  999,177
$                     148
 
$              137
 
0.5% $                  4,
  891,134
4.Stakeholder& Publicity
0.50%
$                      647,
 
504
$                    477,
 
972
$               241,
 
410
$                 317,
 
744
$            895,
  
927
$            418,
  
620
$             2,
  999,177
$                     148
 
$              137
 
0.5% $                  4,
  891,134
Sub Total Developed design and D&C monitoring
$                   6,
  475,039
$                 4,
  779,721
$            2,
  414,098
$              3,
  177,443
$         8,
   959,268
$         4,
  186,201
$            29,
 
991,770
$                  1,
  480
$           1,
  366
$                73,
  
367,015
4. Detailed design and 
1.Track
1.Trackbed and rail
$               14,
  
324,450
$            5,
  307,940
$            14,
 
899,240
$       48,
 
147,200
$          151,
 
449,143
$                  6,
  211
$           6,
  406
$              120,
  
000,000
Construction
2.Bridges and support structures
$                    500,
 
000
N/A
$                        -
  
N/A
$                500,
 
000
$                     500,
 
000
3.Portals or underpasses
$               18,
  
411,835
N/A
N/A
N/A
$            18,
 
411,835
$                18,
  
411,835
$                68,
 
770,313
4.Public realm
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
5. Public Art
Excluded
Excluded
Excluded
Excluded
Excluded
Excluded
6. Track drainage & attenuation
$                 5,
  733,096
$            2,
  292,862
$              7,
  418,116
$       22,
 
036,000
$            37,
 
480,074
$                  2,
  755
$           3,
  189
$                37,
  
480,074
2. Power
1.Supply
Excluded
Excluded
Excluded
Excluded
$                        -
 
$                            - 
2.Sub-Stations
$                    610,
 
000
$               305,
 
000
$                 915,
 
000
$         2,
   745,000
$             4,
  575,000
$                     335
 
$              393
 
$                30,
  
000,000
3. OLE
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
4. Underground
$                 4,
  329,320
$            1,
  581,040
$              4,
  600,720
$       15,
 
110,000
$            25,
 
621,080
$                  1,
  926
$           1,
  978
$              5,
   411
$             5,
  841
$                       5,
   841
$                77,
  
328,999
3. Systems
1. Signalling
$                 1,
  820,000
$                 15,
 
000
$              1,
  760,000
$         1,
   530,000
$             5,
  125,000
$                     308
 
$              757
 
$                  5,
  125,000
2. Telecoms
$                    395,
 
629
$               274,
 
800
$                 430,
 
163
$         1,
   443,429
$             2,
  544,021
$                     194
 
$              185
 
$                  2,
  544,021
2.Statutory 
1.Diversions
$                 5,
  764,200
$            2,
  228,300
$              5,
  976,800
$       16,
 
303,300
$            30,
 
272,600
$                  2,
  226
$           2,
  570
$              9,
   000
$             9,
  716
$                       9,
   716
$              128,
  
630,124
undertakers  
2.Upgrades
Excluded
Excluded
Excluded
Excluded
$                        -
 
$                            - 
3.Highway costs
1.Highway changes
$                    854,
 
800
$                      -
  
$              1,
  179,000
$            339,
  
000
$             2,
  372,800
$                     109
 
$              507
 
$                  2,
  372,800
2. Bus Facilities
Excluded
Excluded
Excluded
Excluded
$                       - 
$                            - 
3. Cycle facilities
Excluded
Excluded
$                942,
 
030
$         3,
   200,000
$             4,
   142,030
$              405
 
$                  4,
  142,030
4. Stops
1. Civil Works
 $                   9,008,342 
$                  1,
  682
$           1,
  559
$                30,
  
987,052
$               10,
  
054,590
$           1,
  442,120
$             3,
  625,480
$         6,
   856,520
$           30,
  
987,052
2. Shelters and furniture
$                      -
  
$               -
 
$                            - 
3. Bus Interchange
$                      -
  
$               -
 
$                  7,
  293,000
$             7,
   293,000
 $                   7,293,000 
$                      -
  
$               -
 
$                            - 
5.Support Facilities
1. Administration building/Control 
centre
N/A
$           1,
  000,000
N/A
N/A
$             1,
   000,000
$                  1,
  000,000
2.Control centre
Excluded
$           2,
  000,000
Excluded
Excluded
$         5,
   000,000
$             7,
   000,000
$                  8,
  500,000
Excluded
3.Maintenance sheds
N/A
N/A
N/A
4.Storage sheds
N/A
$         15,
 
270,308
N/A
N/A
$           65,
  
270,308
$     73,
  
993,096
$     79,
 
875,547
$              79,
 
875,547
$                95,
  
145,855
5. Storage Yards
N/A
Excluded
Excluded
$       50,
  
000,000
$                            - 
6. Design
1. Detailed design
$                     778
 
$              718
 
2.MSQA
4%
$                  3,
  402,866
$                2,
  511,917
$           1,
  268,695
$             1,
  669,862
$         4,
   708,418
$         2,
   200,000
$           15,
  
761,758
$                      -
  
$               -
 
15% $                85,
  
419,119
6.Programme and 
1.Temporary traffic Management
4.50%
$                   3,
  828,224
$                 2,
  825,906
$            1,
  427,282
$              1,
  878,595
$         5,
   296,970
$         2,
  475,000
$            17,
 
731,977
$                     875
 
$              808
 
4.5% $                25,
  
625,736
Project Management
22%
2.Preliminaries and General
$                 20,
 
306,604
$               14,
  
989,863
$            7,
  570,936
$              9,
  964,901
$       28,
 
097,484
$       13,
 
128,500
$            94,
 
058,288
$                  4,
  642
$           4,
  284
25% $              170,
  
126,411
Sub Total Base D&C
$               112,
  
609,349
$               83,
  
125,606
$          41,
 
984,283
$            55,
 
259,907
$     155,
 
813,321
$       72,
 
803,500
$          521,
 
595,966
$                 25,
 
742
$         23,
 
757
$              850,
  
632,056
Off site Overheads and 
15%
$                 16,
 
891,402
$               12,
  
468,841
$            6,
  297,642
$              8,
  288,986
$       23,
 
371,998
$       10,
 
920,525
$            78,
 
239,394
$                  3,
  861
$           3,
  564
$              127,
  
594,808
Sub Total D&C
$               129,
  
500,751
$               95,
  
594,447
$          48,
 
281,925
$            63,
 
548,893
$     179,
 
185,319
$       83,
 
724,025
$          599,
 
835,360
$                 29,
 
603
$         27,
 
321
$              978,
  
226,864
Total
$               139,
  
860,813
$             103,
  
242,001
$          52,
 
144,481
$          181,
 
102,117
$     228,
 
132,027
$     136,
 
021,947
$          840,
 
503,386
$                 35,
 
143
$         77,
 
860
$           1,
  275,870,745
Contingency (P50)
Estimating Risk
4.27%
$                   5,
  972,057
$                 4,
  408,433
$            2,
  226,569
$              7,
  733,060
$         9,
   741,238
$         5,
  808,137
$            35,
 
889,494
$                  1,
  501
$           3,
  325
10% $              127,
  
587,075
Scope Risk
6.00%
$                   8,
  391,649
$                 6,
  194,520
$            3,
  128,669
$            10,
 
866,127
$       13,
 
687,922
$         8,
  161,317
$            50,
 
430,204
$                  2,
  109
$           4,
  672
10% $              127,
  
587,075
Specific Risk
10%
$                 13,
 
986,081
$               10,
  
324,200
$            5,
  214,448
$            18,
 
110,212
$       22,
 
813,203
$       13,
 
602,195
$            84,
 
050,339
$                  3,
  514
$           7,
  786
10% $              127,
  
587,075
Sub Total Contingency
$                 28,
 
349,787
$               20,
  
927,153
$          10,
 
569,686
$            36,
 
709,399
$       46,
 
242,363
$       27,
 
571,649
$          170,
 
370,037
$              382,
  
761,225
Total D&C expected cost
$               168,
  
210,600
$             124,
  
169,154
$          62,
 
714,167
$          217,
 
811,516
$     274,
 
374,390
$     163,
 
593,596
$   1
  ,010,873,423
1,658,631,970
$      
Post per m
$                      59,
 
668
$                 75,
 
378
$                   93,
 
642
$              34,
  
297
$                  76,
 
356
$                     125,
 
284
Contingency (P95)
Estimating Risk
Scope Risk
Specific Risk
Sub Total P95
CCFAS2 Draft Estimate estimate-2.12.2014 LPD rev c
HR & LR


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Appendix 3 
Query and response summary 
 
  mak i ng   the  di ff er en c e  


Queries / Observations  
Issue: 1 

Tel: 02 8245 0000       
Fax: 02 8245 0099 
Level 14, 55 Clarence Street Sydney 2000   
From: 
David Creegan 
To: 
Auckland Transport 
Date: 
03.12.14 
Copy: 
 
Project: 
City Centre Future Access 
Job  Ref: 
 
Study 2 (CCFAS2) 
 
Nr 
Query 
Response (04-Dec-14) 

Power supply– Why has this been excluded from 
Upgrade of  Transpower’s grid only has been 
the estimate? 
excluded 

How many substations are allowed for? 
One Substation has been allowed  every 1.5km of 
route as advised by Arup , (Queen street 2 no, 
Post response note:  
Dominion Road 4 no, Stoddard 2 no, Sandringham 
4 no, Mt Eden, 4 no, Quay to new market 3 no, 
From our analysis of the draft estimate it would 
Newmarket to Onehunga 4 no) Total 23 Nr 
appear that the following substations are included; 
Stage 1 – 3 Nr 
Stage 2 – 6 Nr 
Stage 3 – 4 Nr 
Stage 4 – 4 Nr 
Stage 5 – 18 Nr 

Statutory undertakers – What level of detail and  Statutory undertakers  the level of detail is as that 
design was available when the estimate was 
shown on Auckland Council web site GIS viewer, 
produced?  
plus a site observation , For Dominion road we 
have greater details as a project was about to get 
underway for its upgrade.  Generally the storm 
water and sewer is near to the centre of the road, 
water is all over the place, the rest is either in the 
footpaths or overhead. 

Depot - Final summary tab -  4. Detailed design 
These are plugged figures that need to be 
and Construction, 5.Support Facilities 1. & 2. What 
combined with the temp depot, what is required in 
is the basis for the estimates of the $1,000,000 & 
addition to the existing bus/ traffic ops for just 
$2,000,000? They do not appear within the build 
Queen street stage has not been detailed. 
up for the ‘Depot Link’ 

How many Light Rail Vehicles should be included  The vehicles  costs have been included by the 
and what is the unit price? 
others 
Post response note: 
$6,130,000 per LRV 
Option 9a 22 Nr, Option 4 54 Nr 
 
ALR REQUESTS FOR CLARIFICATION 141204 
PAGE 1 of 3 

Auckland Transport – City Centre Future Access Study 2 Capex Peer Review  Continuation Page 2 
 
Nr 
Initial Observations 
Response (04-Dec-14) 

Design  Costs  appear  very  low  at  4%  of  direct  Only detailed design is at 4% as this is the bit the 
construction  costs.  Ranges  for  similar  light  rail  contractors will do there is another 3% for I&R and 
projects globally are c. 15% to +20%. 
5% for Developed design a total of 11% possibly 
light overall. 
Post response note:  
3% (of total D&C cost) for Investigation and 
Reporting (I&R), includes planning, approvals and 
funding activities. 
5% (of total D&C cost) for Developed design, 
includes preliminary design, reference design, 
detailed design, procurement and programme and 
project management (3% for the design and 
procurement, 2% for management). 

There appears to be errors in the ‘Final Summary’ 
This has been corrected 
tab. Calculations for columns Stage 1 Total, Stage 
2 Total, Stages 1 – 3 do not pick up all of the cells. 
The Total column appears to be correct. 

The temporary depot has a very detailed cost plan 
Correct it is a plugged figure based on advice from 
totalling $15,270,308. Then the stage 2 depot 
Arup there is no details of the requirements 
has a round $50,000,000 in the estimate with no 
back up. The round number seems to be a plug 
figure rather than a cost estimate. 

The cost allowance for substations appears to be 
I was concerned with this cost in the last update 
very low on first inspection 
this has been increased to $305k each, do T&T 
have any better current information 

Light rail systems, signalling and telecoms 
Signalling is based on the number of intersections 
appears to be set at a very low price point and 
that need traffic light alterations , telecoms is for 
may not include all scope required for a wire free 
the backbone only the head equipment is included 
light rail system. 
in the  support facilities, if they have any better 
information this would be appreciated 

Statutory undertakers – Appears to have been 
This has recently been increased due to the 
priced very low when compared to other light rail 
requirement to move 195m of kerb line at each 
systems in major city centre locations. 
station, see also comment on Query 3 the amount 
not included is $63m 

Project Management costs.  – Final summary 
PM costs of 7-11% appear high to me Victoria 
tab -  3. Developed design reporting including 
what are your thoughts 
Design & Construct Contract monitoring, 
5.Programme and Project Management. The total 
of these is 2%. We would expect to see a lot 
higher percentage, possibly in the range of 7% to 
+11%. 

The Highway costs appear to be low. Turner & 
Highway costs have been based on the clearance 
Townsend need to understand the route in more 
of any obstructions in the centre of the road, is 
detail to comment further.  
has generally been assumed that the tracks run 
down the centre of the road and there would be 
little change to the road profile, a stitch make up 
has been included in the track bed and a similar 
item has also been included in the station/ station 
footpaths 
ALR REQUESTS FOR CLARIFICATION 141204 
PAGE 2 of 3 

Auckland Transport – City Centre Future Access Study 2 Capex Peer Review  Continuation Page 3 
Nr 
Initial Observations 
Response (04-Dec-14) 

The project is the first wire free light rail system in 
The risk assessed contingency is being worked on, 
New Zealand and the first 100% wire free system 
currently it is lower than that detailed on the 
globally we understand. The P50 risk allowance 
spread sheet of 20% 
appears to be low when compared to other 
projects at this stage of development and 
considering no project of this nature has been 
constructed 
10 
Spreadsheet, CCFAS2 Draft Estimate estimate-
These have been corrected 
2.12.2014, tab HR & LR has a lot of cells 
containing #VALUE! 
11 
Preliminaries & Traffic Management are lower 
P&G  For NZ a P&G of over 24% for a design and 
than expected with respect to the direct 
build contract would be surprising , it would be 
construction cost component at a composite rate 
useful to know  what form of procurement and 
of 24%. Benchmarked light rail data indicates a 
associate P&G % then have information on  
preliminaries and traffic management composite 
percentage over 25%, with some examples closer 
[P&G = Preliminaries & General] 
to 48% and above. 
 
ALR REQUESTS FOR CLARIFICATION 141204 
PAGE 3 of 3 


Auckland Transport – Commercial in Confidence 
City Centre Future Access Study 2 
Appendix 4 
Additional power and rail systems notes 
 
  mak i ng   the  di ff er en c e  

Notes: Auckland Transport LR Peer Review (04-Dec-14) 
Light Rail 
 
Power/Substations 

The quantity of substations needs to be revised, at present the quantity is aligned 
with the number of stops, instead of the usual 1.5-2km along the route; the 
substation spacing was detailed by email from Arup’s Andy Wood on 04/12/2014. 

The rate for the substation is significantly low. It appears that general distribution 
11kV kiosk substations have been costed, these are not the type of substation 
required for light rail power reticulation. This type of substation may be the source 
of the power for the light rail substation. 

Internal cabling cost will be higher due to cable, trays, termination, testing and 
commissioning. 

No allowance appears to have been made for AC and DC commissioning. 
 
Power/Underground 

The allowance for the light rail substation feeders is significantly low. The feeder 
route will generally be routed within the road footprint to avoid services and can be 
more than one kilometre in length. This means the installation of cable jointing and 
change of direction pits along the buried route and a much lower trenching 
productivity rate, road closure fees and more traffic management. Metre rate= 
$1,563 

Substation feeder cable: The allowance appears to be too high, this takes into 
account the cost of the cable (11kV 3 core 240 mm² XLPE), cable hauling, cable 
jointing and termination. Metre rate= $172 
 
Power/Charger stations 

There is no cost breakdown. There is most likely a requirement for 2 Nr 400 mm² 
DC feeder cables to each charger station with an approximate length of 1,320 m 
between the substation and the charger station. The cost of the cable supply and 
installation is approximately $285,000, an additional amount of $50,000 per 
charger unit will also be required.  
 
Telecommunications 

Ducts: The duct installation rate is too low, based on a first principles estimate for 
a 0.5 x 1.2 m trench with a productivity of 25 m per crew per day. 

Fibre cable: The installation of a 24 core single mode optical fibre cable is 
assumed. The rate appears to be at least 50% too low considering OTDR testing, 
cable supply and installation. 
Heavy Rail 
 
The cable support system cost is at least 20% too low based on a first principles estimate 
for 100mm (Comms), 150mm (signalling) and 200mm (HVAC) galvanised steel trough 
(GST).