This is an HTML version of an attachment to the Official Information request 'Light Rail Alignment'.










   
 
1 April 2019 
 
 
 
 
George W 
[FYI request #9810 email]  
REF: OIA-4831 
 
Dear George 
 
Request made under the Official Information Act 1982 
 
Thank you for your email of 9 March 2019 requesting the following information under the Official 
Information Act 1982 (the Act): 
 
I am requesting the route alignment for the light rail projects south and west in Auckland, as 
well as what the stations will be. 

 
If this is finalised yet I request the latest working alignment and stops. 
 
In May 2018, the Minister of Transport mandated the NZ Transport Agency to lead the delivery of 
the City Centre to Māngere Light Rail (CC2M) on an accelerated basis. 
 
To prepare to deliver CC2M, the Transport Agency immediately established an integrated project 
team with Auckland Transport (AT), the Auckland Council, and HLC to appropriately leverage the 
knowledge and skill sets of these organisations.  The initial focus was to develop an Indicative 
Business Case (IBC) by December 2018 in line with the the Transport Agency’s best practice 
guidelines to support an accelerated delivery of the project. To meet this timeline, the Transport 
Agency and its partners adopted the scheme developed by AT within the Auckland Transport 
Alignment Project (ATAP) and constrained development of the scheme to fit with the mandate of 
accelerated delivery.   
 
NZ Infra, a joint venture of New Zealand Super Fund (NZSF) and CDPQ Infra, has presented an 
unsolicited alternative approach to fund, design, build and operate light rail in Auckland, based on a 
public-public investment model. This is currently being reviewed by the Ministry of Transport and 
Treasury. The light rail project team has been supporting this review. 
 
An IBC is being developed and shared with our project partners, including the Ministry of Transport, 
for review and feedback. However, further work is required to progress the IBC to a Detailed 
Business Case. Until the Ministry of Transport/Treasury review of the NZ Infra unsolicited proposal is 
complete, key decisions arising from the IBC cannot be submitted to the Transport Agency’s Board 
for endorsement as it would be inappropriate to consider it in isolation.   


To provide certainty as soon as possible, the Government requested the Ministry of Transport and 
Treasury provide their advice on alternative funding, delivery and operating models in March 2019. 
Market engagement was temporarily deferred during this time. This advice has now been received 
by the Ministers and is being considered.  
 
Parts of the IBC will soon be publicly available on the CC2M project website at 
www.nzta.govt.nz/CC2M with some redactions made under the Act. Therefore, I am refusing your 
request for information regarding the CC2M line under section 18 (d) of the Act as the information 
requested will soon be publicly available. 
 
Along with our partners we are progressing work on a corridor to connect the north-western 
suburbs. It will provide a critical connection for these suburbs to help them develop in a sustainable 
way. 
 
Investigations for the City Centre to North West (CC2NW) line are at a very early stage and further 
work needs to be undertaken to develop a business case. 
 
Factors that will be considered as part of a business case assessment include:  
•  how best to support growth and desired land use outcomes for the North West area  
•  opportunities and constraints provided by the current State Highway 16 corridor  
•  integration with and opportunities provided by the wider proposed transport network.  
 
The business case will identify a preferred route and potential stations and stops along the corridor 
for  further  investigation. When  this  work  is  complete,  the  NZ  Transport  Agency  will  have  a  better 
understanding of both the timeline for delivery as well as potential changes and impacts from both a 
transport and urban development perspective.  
 
I am refusing your request for information relating to the CC2NW line under section 18 (e) as the 
document alleged to contain the information requested does not exist. 
 
With respect to the information that has been withheld, I do not consider there are any other 
factors which would render it desirable, in the public interest, to make the information available. 
 
Under section 28 of the Act, you have the right to ask the Ombudsman to review my decision to 
withhold some information and to refuse parts of this request. The contact details for the 
Ombudsman can be located at www.ombudsman.parliament.nz. 
 
If you would like to discuss this reply with the NZ Transport Agency, please contact the Auckland 
Light Rail team by email on [email address].  
 
 
Yours sincerely 
 
 
Stephen Smith  
Senior Manager – Auckland Light Rail