This is an HTML version of an attachment to the Official Information request 'Request for Supporting Analysis used to identify the Golden Mile Options'.
 
Evaluation Framework 
The evaluation framework used to assess 21 scenarios that passed through an initial filter is shown 
overleaf.  The framework will be further developed and added to before it is used for the evaluation of 
short list options. 
Other matters considered during the development of critical success factors within this framework 
included: 
1982
•  impact on businesses on Golden Mile - while this is an important consideration for LGWM, at long-
list stage, given the limited detail within the scenarios impact on business will generally be 
Act 
proportional to the amount of physical works that are undertaken.  A more nuanced assessment 
against this criterion may be introduced when concept designs for each short list option are 
available.  
•  opportunities for businesses on the Golden Mile – is also an important consideration for LGWM but 
ultimately is a function of the objectives (4) and (5) 
•  ability to accommodate an increased bus throughput – this is a function of improving bus travel 
times and travel time reliability.  Therefore, if investment objective 1 is achieved it will enable some 
increase in bus throughput.  Nonetheless the additional capacity for bus throughput will be very 
dependent on the combination of interventions in the corridor.  Therefore, at long list stage, the 
Information 
differences between scenarios will not be discernible.  This criterion may be used when concept 
designs are developed for shortlist options. 
•  compatibility with proposals to create parallel bus corridors - unless the parallel bus corridor does 
not follow the Quays, this criterion is unlikely to differentiate between scenarios. 
 
Official 
 
the 
under 
Released 
Page 1 of 3 

 
INVESTMENT OBJECTIVES 
1: Improve bus travel times and travel time reliability along the Golden 
High Improvement 
Medium Improvement 
Low Improvement 
Negative 
Mile 
Bus Stop Delay 
Bus stop delay is significantly reduced, 
Some reduction to bus stop delay expected, 
Minimal change 
Increased bus stop delay 
•  Close spacing 
addressing all key issues 
as only some issues addressed. 
•  Dwell times 
T
•  Short length stops 
RS
Signal controlled intersections 
Significantly reduced delay to buses expected as 
Some reduced delay to buses expected, with 
Minimal change 
Increased intersection delay 
SMEN
TO
multiple conflicting movements removed. 
slightly higher proportion of green time 
expected 
1982
ES
C
allocated to buses.  
SS
 FA
A
 
Interaction with general traffic 
All interactions with general traffic along the 
Some reduction in interaction between buses  Minimal change 
Increased interaction between buses 
 
•  Sides roads  
corridor section removed. 
and general traffic along the corridor. 
and general traffic. 
Act 
•  Along corridor 
•  Intersection approaches 
2: Improve convenience and comfort of waiting for, boarding and alighting  High Improvement 
Medium Improvement 
Low Improvement 
Negative 
buses along the Golden Mile 

Waiting space available 
Space available for large waiting area, free of 
Some increase in waiting area at bus stops.  
Minimal change 
Decrease in waiting area at stops. 
 
RS
pedestrian movements. 
SMEN
TO
Legibility of bus stops 
Bus stops regularly spaced, with standard length  Some improvement to bus stop legibility.  
Minimal change 
Decreased bus stop legibility with 
ES
C
•  Bus stopping pattern 
& simple stopping patterns. 
complex stopping patterns and/or 
SS
FA
A
•  Ease of use 
long stops. 
Information 
3: Reduce the number of crashes within the Golden Mile that result in 
High Improvement 
Medium Improvement 
Low Improvement 
Negative 
pedestrian injury 
Delay at signalised intersections, leading to increased pedestrian 
Multiple conflicting traffic movements removed.  Some reduced delay to buses expected, with 
Minimal change 
Increase in pedestrian delay. 

compliance. 
slightly higher proportion of green time 
 
allocated to pedestrians. 
RS
Official 
SMEN
TO
Conflict between pedestrians and vehicles turning into or out of side roads 
All vehicle movements in and out of side streets 
Some vehicle movements in and out of side 
Minimal change 
Increased vehicle movements in and 
ES
C
at priority-controlled intersections with side streets 
closed. 
streets closed. 
out of side streets. 
SS
FA
A
Conflict between vehicles and pedestrians when crossing at uncontrolled 
General traffic removed from full section of the 
General traffic volume reduced along the 
Minimal change 
Increased general traffic along the 
the 
locations 
corridor 
corridor  
corridor 
4: Increase the capacity for pedestrians to move within the corridor by 
High Improvement 
Medium Improvement 
Low Improvement 
Negative 
improving walking LOS along and across Golden Mile 
Footway Congestion  
Path width enables higher pedestrian flow 
Path width is sufficient to handle current 
Minimal change 
Reduced width or more 
•  width of path  
without congestion. 
volume without congestion. 
obstructions. 
under 
•  obstructions in path 
Suits users of all needs. 
T  
 
Connectivity (Both along and across the GM) 
High level of priority for pedestrian movements 
Pedestrians need to pause and give way 
Minimal change 
Frequent need to give way to 
RS
•  frequency of signal-controlled crossing  
along the Golden Mile (e.g. where side streets 
along the mile. 
vehicles.  
SMEN
TO
•  ease / ability to cross at uncontrolled locations 
are closed). 
ES
C
Safe informal crossing points (e.g. median 
Unsafe informal crossing, 
SS
FA
•  permeability of the corridor 
Safe to cross the Golden Mile at any location 
and low enough volume) 
pedestrians likely to take risks. 
A
(with caution). 
Moderately spaced formal crossings (75m-
Widely spaced formal crossings 
Closely spaced formal crossings (no more than 
125m) 
(more than 125m) 
Released 75m apart). 
Page 2 of 3 

 
5: Improve the place quality of the Golden Mile 
High Improvement 
Medium Improvement 
Low Improvement 
Negative 

Environmental comfort 
Improvement to all 
Improvement to some 
Minimal change 
Reduction from current 
 
(considers noise, pollution, vehicle traffic volume, space for vegetation/LID) 
RS
SMEN
TO
Opportunity for public realm enhancements 
Improvement to all 
Improvement to some 
Minimal change 
Reduction from current 
ES
C
(feels safe, relaxed, provides for dwelling, seating, events, identity 
SS
FA
A
contributors (like art works or celebrating heritage places)  space for 
hospitality) 
 
1982
CRITICAL SUCCESS FACTORS 
1.  Improved level of service for cycling 
Greatly Achieved  
Somewhat Achieved 
Minimally Achieved 
Negative 
Act 
• 
scenario or option creates additional 1.5m-2.5m road 
• 
scenario or option reduces the number of 
• 
cycling LOS similar existing 
• 
less space available for cyclists;  
width for people who cycle / use micro-mobility;  
traffic conflicts for cyclists / micro-mobility 
• 
additional restrictions on use of Golden Mile for 
• 
scenario or option reduces the number of traffic conflicts 
users; 
cycling;  
for cyclists / micro-mobility users;  
2.  Resilience to network operational disruptions 
Greatly Achieved  
Somewhat Achieved 
Minimally Achieved 
Negative 
• 
carriageway layout increases ability for buses to pass lane 
• 
not applicable 
• 
existing diversion routes are 
• 
the number of available bus diversion routes are 
closures or broken-down vehicles 
unaffected (remain available);  
reduced;  
• 
ability for buses to pass lane 
• 
the ability for buses to pass lane closures is reduced 
closures is unchanged 
3.  Increase flexibility and ability to adapt as the 
Greatly Achieved  
Somewhat Achieved 
Minimally Achieved 
Negative 
Information 
city’s transport networks evolve 
• 
scenario or option is equally compatible with a Taranaki 
• 
not applicable 
• 
not applicable 
• 
scenario or option is compatible either with a 
Street or Kent/Cambridge bus / MRT interchange 
Taranaki Street or Kent/Cambridge bus / MRT 
interchange 
4.  Ability to Demonstrate Tangible 
Greatly Achieved  
Somewhat Achieved 
Minimally Achieved 
Negative 
Official 
Improvements within the 2018-21 / 2021-24 
• 
it is possible to complete delivery in or before 2022 
• 
it is possible to complete delivery in or 
• 
it is possible to start, but not 
• 
it is not possible to start delivery before 2024 
NLTP periods 
• 
Supports increased volumes of pedestrians and is an 
before 2024 
complete, delivery before 2024 
environment that people want to spend time in and 
the 
therefore $ 
 
under 
Released 
Page 3 of 3