EECA LEVCF FUND 03-149
Special Report to claim 100% remaining available funding from Milestone 2
Milestone Purchase and registration of a 2018 model electric campervan for use in New Zealand
description • Confirmation of NI and SI itineraries and location for the instal ation of EV charging stations
• Minimum of 20 EV chargers in any island and at least two locations in each island to comprise
of multiple chargers
Deliverable A report that contains, as a minimum, the fol owing contents:
• Descriptions and photographs of the 2018 model electric campervan purchased
• Confirmation and registration for use in New Zealand
• Descriptions of the NI and SI itineraries
• The identified locations for the EV charging stations instal ations, and
• Any other information that you believe EECA should be aware of.
Funding
Progress of Funding: $16,394 out of $30,000. Claiming remaining $23k this period. As per
Claim
discussion 5Oct, funding to be release upon receipt of this report.
Tasks delivered Description • Nissan eNV200 purchased for internal crew use to test the electric experience of charging in
s and
NZ and to test the electric itineraries developed to support the longer-term motorhome build
photograph • See evidence as fol ows: publication covering the intent behind the project & a general vehicle
s of the
review https://www.autocar.co.nz/commercial-reviews/2014-britz-nissan-env200-sleeper-van
2018
model
electric
campervan
purchased
• See evidence as fol ows: photos of the vehicle (inside and out) on the road in test by
thl crew
Confirmati
• See evidence as fol ows: Vehicle was seen by Richard Briggs 6th September while on the road
on and
testing the North Island Itineraries, along with COF and rego from vehicle
registration
for use in
New
Zealand
9(2)(a)
Oct 18 –
Milestone 2
COMMERCIAL IN CONFIDENCE
EECA LEVCF FUND 03-149
Description • Britz have created a beautiful website to capture the electric vehicle motorhome proposition,
s of the NI
this can be viewed on www.BritzEV.com with ful itinerary descriptions covering both the
and SI
North and South Island along with links and visuals displaying al relevant day and overnight
itineraries
charging requirements to successful y cover the route
• See evidence as fol ows: North (Coastal Loop) and South Island Itineraries
• See evidence as fol ows: Example itinerary days for Day 1-3 North (Coastal Loop) Itineraries
The
• 19 locations have been identified for charging stations to be instal ed supporting the BritzEV
identified
itineraries along with 11 additional holiday parks being approached to support the itineraries
locations
Oct 18 –
Milestone 2
COMMERCIAL IN CONFIDENCE
EECA LEVCF FUND 03-149
for the EV
as optional add-ons for travel. 80+% of these locations have committed to double head
charging
charging units
stations
• See evidence as fol ows: the below North and South Island visuals are represented on
instal ation
www.BritzEV.com website indicating al the locations for EV charging stations that wil be
s
instal ed as a part of this EECA funding project.
• See evidence as fol ows: optional addons holiday parks are represented on the website as
fol ows, along with an example working list between HPNZ,
thl and ChargeMaster and example
indication from Fergus, Chair at HPNZ on purchase confirmations coming in & master record of
confirmations for purchase
We hope this satisfies requirements against EECA 03-149 agreement.
Oct 18 –
Milestone 2