Missing Tender Documents, Clarifications, and Definition of Early Works in Regards to Otahuhu and Manukau Interchange Projects

Ben Ross made this Official Information request to Auckland Transport

The request was successful.

From: Ben Ross

Dear Auckland Transport,

I am seeking information and clarification around the status of the Otahuhu and Manukau Transport Interchanges please.

Context

From a communication forwarded to me that Auckland Transport had written in regards to Otahuhu and Manukau Transport Interchanges it was stated:

In relation to your question on Manukau and Otahuhu Bus Interchanges, here is a response.
At the moment, Auckland Transport are operating in a very uncertain funding environment as they deal with potentially lower LTP capital expenditure in the Basic Transport Network (BTN) versus that in the Auckland Plan Transport Network (APTN).
Auckland Transport have opted to progress design and potentially early works (within funding) on projects that would be funded in earlier years under the APTN to ensure momentum is not lost.
And in the case of these two projects, the following would be the desired timeline without the constrained BTN funding:
• Construction on the Manukau Bus Interchange project would start in the 1st quarter of 2015 with target completion in late 2015. Currently, the detailed design process is underway.
• Construction of the Otahuhu Bus Train Interchange would start later this month with expected completion in late 2015. Currently, the detailed design process is underway.

In addition, Auckland Transport are currently exploring re-prioritisation options for these 2 projects. As this is currently being worked through, no update to the draft LTP has been made. If re-prioritisation cannot be achieved in 2014/15 and in the early years of the LTP, Auckland Transport would only deliver on initial improvements within the current funding, with the delivery of full specification in 2020/21.
Current Basic Transport Network (the Mayors proposal) budgeted figures:
Manukau Bus Interchange
• We have design funding of $3.8m in 2014/15
• Then there is no funding provided in the BTN programme until 2020/21
• Total required funding is planned at $23.9m (inflated)
Otahuhu Bus Train Interchange
• We have design and some early works funding of $6.3m in 2014/15
• Then there is no funding provided in the BTN programme until 2020/21
• Total required funding is planned at $26.8m (inflated)

My questions to Auckland Transport are the following:
1. What is the definition of Early Works for Otahuhu Transport Interchange, in other words for $6.3m for the 2014/2015 year what does it get us in regards to Otahuhu Transport Interchange if reprioritisation is not successful in allowing the full set of works for Otahuhu Transport Interchange
2. The Tender Documents either open or closed for the construction of these “early works” for Otahuhu Transport Interchange cannot be found on the various Auckland Transport pages including these two:
a. https://at.govt.nz/media/618879/NZTA-Awa...
b. https://www.tenderlink.com/aucklandtrans...
Is there a particular reason why these tender documents are not publicly accessible or not on your Awarded Contracts PDF
3. Is there an updated version of the https://at.govt.nz/media/665907/CDD-Forw... which is meant to be updated monthly but has not been done so since August 2014
4. Are the designs for the Manukau Transport Interchange able to be released into the public domain yet? If not when so please. What will happen with those designs if the Basic Transport Network continues and the Manukau Interchange cannot be built until 2020/2021?
Please note I will be forwarding a LGOIMA directly to Auckland Council on what happens to Lot 59 where the Interchange sits if the Manukau Interchange does not proceed until 2020/2021

I look forward to your reply
Yours faithfully,

Ben Ross

Link to this

Ben Ross left an annotation ()

Link to this

From: Auckland Transport No Reply

Dear Customer

Thank you for contacting Auckland Transport about LGOIMA: OTAHUHU
TRANSPORT INTERCHANGE INFORMATION.  

Your reference number is CAS-446312-M0Z8M4.

Your enquiry will be referred to a member of our customer services team,
who will respond to you directly or refer your query to the appropriate
business unit.

If you have requested feedback, we aim to respond to all correspondence
within 20 working days. If your enquiry cannot be responded to in full
within 20 working days, we will inform you of progress and let you know
when to expect a final response.

If you have an urgent enquiry, please phone our call centre on 09 355
3553. The Auckland Transport call centre is open 24 hours a day, 7 days a
week, including public holidays.

Kind regards

Auckland Transport
Private Bag 92250, Auckland 1142
P 09 355 3553 | F 09 355 3550
[1]www.aucklandtransport.govt.nz

References

Visible links
1. http://www.aucklandtransport.govt.nz/

Link to this

From: Customer Liaison


Attachment CAS 446312 M0Z8M4 Ack.pdf
40K Download View as HTML


Good morning Mr Ross,

Please find attached an acknowledgement for information requested under
the Local Government Official Information and Meetings Act 1987 from
Auckland Transport.

 

Kind regards

 

Jo Garwood | Auckland Transport
6 Henderson Valley Rd, Henderson, Auckland 0612
Private Bag 92250, Auckland 1142

P 09 355 3553 | F 09 355 3550 | [1]www.aucklandtransport.govt.nz

References

Visible links
1. http://www.aucklandtransport.govt.nz/

Link to this

From: Customer Liaison


Attachment CAS 446312 M0Z8M4 Final.pdf
183K Download View as HTML


Good morning Mr Ross,

Please find attached the information requested under the Local Government
Official Information and Meetings Act 1987 from Auckland Transport.

 

Kind regards

 

Jo Garwood | Auckland Transport
6 Henderson Valley Rd, Henderson, Auckland 0612
Private Bag 92250, Auckland 1142

P 09 355 3553 | F 09 355 3550 | [1]www.aucklandtransport.govt.nz

References

Visible links
1. http://www.aucklandtransport.govt.nz/

Link to this

Things to do with this request

Anyone:
Auckland Transport only: