Costs of Govt decision to cancel iReX

Miss W. Forest made this Official Information request to KiwiRail

The request was refused by KiwiRail.

From: Miss W. Forest

Dear KiwiRail,

Provide the total actual cost and / or estimated cost of the cancellation of iReX project.

This is aggregate of all either actual and / or estimated costs and thus does not fall into commercial in confidence.

If you refuse to release the information, please explain precisely why releasing the aggregate amount would prejudice or disadvantage you carrying individual cost items under it that make the aggregate estimate and / or actual costs.

I believe that you have provided estimates to the ministry for them to make the decision and this information ought to be public.

Yours faithfully,

Miss W. Forest

Link to this

From: Dave Allard
KiwiRail


Attachment image001.png
3K Download


Good afternoon Miss Forest

 

You have requested under the OIA: Provide the total actual cost and / or
estimated cost of the cancellation of iReX project.

We also received a transfer from the Ministry of Transport on 15 October
2024 for the same information.

 

You also noted in relation to your response:

‘This is aggregate of all either actual and / or estimated costs and thus
does not fall into commercial in confidence.

If you refuse to release the information, please explain precisely why
releasing the aggregate amount would prejudice or disadvantage you
carrying individual cost items under it that make the aggregate estimate
and / or actual costs.

I believe that you have provided estimates to the ministry for them to
make the decision and this information ought to be public.

 

We can provide you with the total costs for iReX to 30 June 2024, by
referencing to KiwiRail’s annual integrated report as this is publicly
available information (refer to pages 95-96, point 26). You can find the
report here on KiwiRail’s website:
[1]Annual-Integrated-Report-2024-KiwiRail.pdf

 

We note that the costs described in the annual report are noted as
excluding settlement costs relating to exiting the ship building
contracts.

 

This is because of the ongoing negotiations for exiting the contracts,
which are commercially sensitive. We have decided to refuse the part of
your request that relates to the total estimated future costs for IReX
including for exiting the ship build contract under section 9(2)(b), 9
(2)(ba) and 9(2)(j) of the Official Information Act due to the ongoing
commercial sensitivity, obligations of confidence and ongoing negotiations
related to the cost information.

 

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available at
www.ombudsman.parliament.nz.

If you wish to discuss this decision with us, please feel free to contact
me directly at this email, or on the number below.

 

Kind regards

 

Dave

 

Dave Allard  | Senior Government Relations Advisor

DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand

[2]Description: Description: cid:image001.png@01D46098.E77643D0

[3]www.kiwirail.co.nz

 

-----Original Message-----

From: Miss W. Forest <[4][FOI #28745 email]>

Sent: Sunday, October 13, 2024 10:09 PM

To: KiwiRail <[5][email address]>

Subject: Official Information request - Costs of Govt decision to cancel
iReX

 

CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you
know the content is safe.

 

Dear KiwiRail,

 

Provide the total actual cost and / or estimated cost of the cancellation
of iReX project.

 

This is aggregate of all either actual and / or estimated costs and thus
does not fall into commercial in confidence.

 

If you refuse to release the information, please explain precisely why
releasing the aggregate amount would prejudice or disadvantage you
carrying individual cost items under it that make the aggregate estimate
and / or actual costs.

 

I believe that you have provided estimates to the ministry for them to
make the decision and this information ought to be public.

 

Yours faithfully,

 

Miss W. Forest

 

-------------------------------------------------------------------

 

This is an Official Information request made via the FYI website.

 

Please use this email address for all replies to this request:

[6][FOI #28745 email]

 

Is [7][KiwiRail request email] the wrong address for Official Information
requests to KiwiRail? If so, please contact us using this form:

[8]https://fyi.org.nz/change_request/new?bo...

 

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:

[9]https://fyi.org.nz/help/officers

 

If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.

 

 

-------------------------------------------------------------------

 

References

Visible links
1. https://www.kiwirail.co.nz/assets/Upload...
3. http://www.kiwirail.co.nz/
4. mailto:[FOI #28745 email]
5. mailto:[email address]
6. mailto:[FOI #28745 email]
7. mailto:[KiwiRail request email]
8. https://fyi.org.nz/change_request/new?bo...
9. https://fyi.org.nz/help/officers

hide quoted sections

Link to this

Things to do with this request

Anyone:
KiwiRail only: