Since the 5th National Government has taken office on 19 November 2008, how much funding has KiwiRail received, and broadly, which areas has this funding used?
Yours faithfully,
Iain Palmer
From: OCU
KiwiRail
Good afternoon Mr Palmer
We acknowledge receipt of the below Official Information Act 1982 request.
Under the Act, KiwiRail has up to 20 working days from the date of
receiving your request to respond. Therefore, you can expect a response
on or before Friday 10 March 2017.
This calculation takes into account KiwiRail receiving your request
outside normal business hours.
We will be in touch with you if it is necessary to clarify any aspect of
your request.
Kind regards
Louise
Louise Jago | Communications Co-ordinator
Ph: +64-4-498 3372 (internal extn 43372) | Fax: +64-4-473 1589 | Mob:
+64-027 407 1718
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand
[1]Description: Description: KiwiRail Logo email
Backbone of integrated transport networks
Please consider the environment before printing
show quoted sections
From: OCU
KiwiRail
[1][FOI #5355 email]
Dear Mr Palmer
Thank you for your email to KiwiRail of 9 February 2017, in which you make
the following request:
“Since the 5th National Government has taken office on 19 November 2008,
how much funding has KiwiRail received, and broadly, which areas has this
funding used?”
Your request has been considered under the Official Information Act 1982
(the Act).
Since 1 July 2008, KiwiRail has received $2.1bn of Crown investment. The
majority of this investment has contributed to KiwiRail’s ‘below rail’
costs, including maintaining and improving tracks, bridges and tunnels.
Costs associated with the operational side of the business – running the
trains and ferries (also referred to as ‘above rail’ costs) - are largely
covered by the revenue that the company earns. Over the same period,
KiwiRail also received $1.4bn in Revenue Grants, mainly for infrastructure
upgrades for public transport in Auckland and Wellington metropolitan
areas.
As an example of how KiwiRail uses its funding, in the financial year
2015/16 KiwiRail made a capital investment of around $155 million to
support freight critical routes and replace or upgrade infrastructure such
as tunnels and bridges. In addition work was undertaken to lay 147 km of
new track, de-stress 1,010 km of line and replace 2100 bridge timber spans
and 322 bridge timber piers. We invested in improvements to increase
reliability for freight customers, spending $18 million on new wagons and
containers.
To find out more about the Crown’s investment in KiwiRail, you may like to
see our Annual Reports, which can be found on our website at
[2]http://www.kiwirail.co.nz/media/publicat....
Under s28(3) of the Act, you have the right to seek an investigation and
review of this decision by way of complaint to the Ombudsman. Refer to
[3]www.ombudsman.parliament.nz for more information.
Regards
Official Correspondence Unit
KiwiRail
References
Visible links
1. mailto:[FOI #5355 email]
2. http://www.kiwirail.co.nz/media/publicat...
3. http://www.ombudsman.parliament.nz/
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence