DIGITISATION PROJECT WORKSTREAMS
1.

High needs formats

(film, 2” video tape, 1” video tape, UMatic video tape)

Productivity rate 2 : 1

(2 hours staff time = I hour of digitised product)
2.
Commodity formats

(Betacam SP, Betacam SX, DigiBeta)

Productivity rate 0.75 : 1

(0.75 hours staff time = I hour of digitised product)
Stream 1
contractors
productivity
output hours
Year 1
1
2 : 1
750
Year 2
2
2 : 1
1,500
Year 3
4
2 : 1
3,000
5,250
Stream 2
contractors
productivity
output hours
Year 1
2
0.75 : 1
4,000
Year 2
3
0.75 : 1
6,000
Year 3
5
0.75 : 1
10,000
20,000
BASELINE WORKSTREAM

Digitised output of transition from Production Library to Archiving activity, 

independent of Digitisation Project work:
Baseline
staff
output hours
Year 1
1
1,500
Year 2
2.5
3,750
Year 3
3
4,500
9,750

CONTENT

Television programmes are seldom exactly one hour long. The majority of those 

selected for digitisation are likely to be approximately 30 minutes, with lesser 

quantities of longer and shorter programmes. On that basis an estimate can be 

made of the number of individual titles represented by the Digitisation Project 

output:
Output
hours
programmes
Year 1
4,750
10,450
Year 2
7,500
16,500
Year 3
13,000
28,600
55,550