Amyes Road Intersection

Cody C made this Official Information request to KiwiRail

The request was successful.

From: Cody C

Dear KiwiRail,

Are there any improvements planned for the Amyes Road Intersection in the next 10 years? Please supply details. If not, how would someone propose said improvements? Further, is this railway line in use anymore? If not, what is the typical process for disposal / removal?

For clarity, I am referring to the intersection of Shands Road and Amyes Road in Christchurch.

Yours faithfully,

Cody C

Link to this

From: Scarlett Dellow
KiwiRail

Kia ora Cody,

I'd like to acknowledge receipt of your official information request for information on the Amyes Road Intersection.

We received your request on 1 June 2023, and will endeavour to respond to your request as soon as possible and in any event no later than 30 June 2023, i.e. the 20 working days after the day your request was received.

If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.

Dave Allard, who is cc’d, will be looking after your request, so any questions please get in touch with him at [email address] or on 027 201 8182.

Thanks,
Scarlett Dellow  |  Communications Coordinator
MOB: +64 27 234 0003
Second Floor, KiwiRail Building Millennium Centre, 604 Great South Road, Ellerslie, 1051 | Private Bag 92138, Auckland 1142, New Zealand

www.kiwirail.co.nz
Please consider the environment before printing.

The content of this message and any attachments may be privileged or confidential. If you
have received this email in error please notify the sender and delete the email - unauthorised
use is expressly prohibited. This email may have been corrupted or interfered with. KiwiRail
does not warrant that this email and its contents are free from computer viruses or other defects.

show quoted sections

Link to this

From: Dave Allard
KiwiRail

Good afternoon Cody
Our response below -

KiwiRail does not have any current upgrade plans for the Amyes/ Shand Road level crossing in the next 10 years.
The planning of any future upgrades for this level crossing are being investigated, but are subject to further discussions between KiwiRail, stakeholders and future council plans.
There is no process for members of the public to propose improvements, but as noted above, KiwiRail works with local councils and Waka Kotahi in considering the road/rail interface.

The Hornby line is still considered an active line and KiwiRail has expressed no interest in the closure of this line.

Kind regards
Dave

Dave Allard  | Senior Government Relations Advisor
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

www.kiwirail.co.nz

show quoted sections

Link to this

From: Cody C

Dear Dave Allard,

Thank you for your complete answer.

Yours sincerely,

Cody C

Link to this

From: Cody C

Dear Dave Allard,

Please supply the total number of movements for the past 12 months (or most recent period) on the Southbridge Branch, for example as it relates to the span from SH1 through Amyes Road.

Yours sincerely,

Cody C

Link to this

From: Dave Allard
KiwiRail

Thanks Cody

Acknowledging your request, will ask our team for the numbers.

Cheers
Dave

show quoted sections

Link to this

From: Dave Allard
KiwiRail

Good afternoon Cody

We have two recorded movement on that line within the last 12- months with a work train delivering materials to the end of the line.

Kind regards
Dave

show quoted sections

Link to this

From: Cody C

Dear Dave Allard,

Thank you.

Yours sincerely,

Cody C

Link to this