Infrastructure investment and correspondence for in Bastia Hill
J Buckingham made this Official Information request to Whanganui District Council
The request was partially successful.
From: J Buckingham
Dear Whanganui District Council,
Please provide correspondence, reports, studies and contractor activities completed or planned in relation to the condition of, investment in and upgrades required or repairs to the three waters and footpath infrastructure in the Bastia Hill area from financial year 2017/18 to date.
For the avoidance of doubt, this means the area up from Anzac Parade for the access roads: Mount View Road, Wairere Road, Georgetti Road and Shakespeare Road and the sub roads D'Arcy, Iris and Bastia Avenue.
Yours faithfully,
J Buckingham
From: WDC Information Request
Whanganui District Council
Dear J Buckingham,
I am writing to acknowledge receipt of your official information request dated 25 October 2022 asking for information relating to infrastructure investment in the Bastia Hill area.
We received your request on 25 October 2022. We will endeavour to respond to your request as soon as possible and in any event no later than 22 November 2022, being 20 working days after the day your request was received. If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.
If you have any queries, please feel free to contact me on (06) 349 0001 or by return email. If any additional factors come to light which are relevant to your request, please do not hesitate to contact me so that these can be taken into account.
Kind regards
Hayley Fitzgerald
show quoted sections
From: WDC Information Request
Whanganui District Council
Hi Jo,
Thanks for your time on the phone today. As advised, your request, as currently worded, would require a considerable amount of staff resources to search and collate for the information requested.
Thank you for refining your request to the following.
* Can Council confirm whether any investment or upgrade has been made to three waters and footpath infrastructure in the Bastia Hill area since the 2017/2018 financial year.
*Can council confirm whether any investment or upgrade to the three waters and footpath infrastructure in the Bastia Hill area is planned?
(Bastia Hill area - this means the area up from Anzac Parade for the access roads: Mount View Road, Wairere Road, Georgetti Road and Shakespeare Road and the sub roads D'Arcy, Iris and Bastia Avenue)
Please let me know if this is not how you intended your refinement to read.
We will be in touch in due course as per our earlier email. If you have any queries, please feel free to contact me on (06) 349 0001 or by return email. If any additional factors come to light which are relevant to your request, please do not hesitate to contact me so that these can be taken into account.
Kind regards,
Hayley Fitzgerald
show quoted sections
From: WDC Information Request
Whanganui District Council
Dear Ms Buckingham,
I refer to your official information request dated 25 October 2022 asking
for information relating to infrastructure investment in the Bastia Hill
area.
The information you have requested is as follows.
* Can Council confirm whether any investment or upgrade has been made to
three waters and footpath infrastructure in the Bastia Hill area since the
2017/2018 financial year.
Footpath Infrastructure
Since the 2017/2018 financial year investment comprised concrete repairs,
totalling approximately 19.1 square metres to Wairere Road (February 2020)
and 18.5 square metres to Bastia Avenue (November 2019).
Stormwater and Wastewater
No investments or upgrades have been made in this area over this time,
only routine maintenance activities.
Potable Water
There have been no water supply upgrades in this area, over this time. The
last major capital works programme was to the Ikitara Road pump station.
*Can council confirm whether any investment or upgrade to the three waters
and footpath infrastructure in the Bastia Hill area is planned?
Footpath Infrastructure
There are no renewals recorded (or planned for in the most recent forward
works programme to the Bastia Hill area). However, the next footpath
network condition survey is planned for February 2023, which will inform
and update forward works at a network level accordingly.
Stormwater and Wastewater
There are no planned investments or upgrades.
Potable Water
There are no planned investments or upgrades. Future projects will be
based on the criticality model and will be planned within the LTP.
You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available at
[1]www.ombudsman.parliament.nz or freephone 0800 802 602.
If you wish to discuss this decision with us, please feel free to contact
me on 06 349 0001 or by return email.
Yours sincerely
Hayley Fitzgerald
On behalf of
Rob Goldsbury
General Counsel
show quoted sections